ZURICH--ABB Ltd (ABBN.VX) Tuesday said it won a contract worth
more than $100 million to build a new gas condensate processing
plant for Petroleum Development Oman in the Sultanate of Oman.
MAIN FACTS:
- The order was booked in the second quarter.
- The new Saih Nihayda Condensate Stabilization Plant will be
located near the Saih Nihayda gas plant in the north part of PDO
concession area, and will have the capacity to process 4,500
standard cubic meters of condensate per day.
- The new plant will be used as a backup for the existing
central processing plant to ensure continued gas production for
PDO's domestic and export customers.
- ABB will be responsible for the engineering, procurement and
construction (EPC) of the condensate stabilization facilities,
including project management, training, testing and on-site support
for operation and maintenance after start-up.
- In addition, ABB will supply power equipment such as low- and
medium-voltage switchgear, power transformers, the electrical
control system, as well as continuous emission monitoring systems
and other analytical instrumentation.