UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 6-K
Report of Foreign
Private Issuer
Pursuant to Rule 13a-16 or 15d-16 of
the Securities Exchange Act of 1934
For the month of December 2023
Commission File Number 001-41489
enCore Energy
Corp.
(Translation of registrant’s name into English)
101 N. Shoreline Blvd. Suite 450, Corpus
Christi, TX 78401
(Address of principal executive offices)
Indicate by check mark whether the registrant
files or will file annual reports under cover of Form 20-F or Form 40F:
Form 20-F ☐ Form 40-F ☒
The following documents are being submitted herewith:
SIGNATURES
Pursuant to the requirements of the Securities
Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
|
enCore Energy Corp. |
|
(Registrant) |
|
|
Date: December 6,
2023 |
By: |
/s/ Carrie Mierkey |
|
Name: |
Carrie Mierkey |
|
Title: |
Chief Financial Officer |
2
EXHIBIT 99.1
enCore Energy Enters US$70 Million Transaction
with Boss Energy; Proceeds to Accelerate Company-Wide Uranium Production Plans
NYSE American:EU
TSXV:EU
www.encoreuranium.com
DALLAS, Dec. 6, 2023 /CNW/ - enCore Energy Corp.
(NYSE American: EU) (TSXV: EU) (the "Company" or "enCore") is pleased to announce that it has
entered into a Master Transaction Agreement ("Agreement") with Boss Energy Limited ("Boss Energy"), a leading Australian
emerging ISR uranium producer, which, upon completion, will result in the sale of a 30% ownership interest in enCore's Alta Mesa project
("Alta Mesa") to Boss Energy for US$60 million, an investment of US$10 million into enCore common shares by Boss Energy, a loan
of up to 200,000 pounds U3O8 for enCore's commercial use over the next year, and the formation of a strategic collaboration
on the use and joint development of enCore's proprietary Prompt Fission Neutron ("PFN") technology for uranium exploration and
production.
The transaction, expected to be completed in February
2024, provides enCore with the financial capacity to significantly accelerate its uranium production pipeline across South Texas through
the development of multiple satellite operations. In addition, the transaction paves the way for aggressive expansion, consolidation
and development of enCore's Dewey Terrace and Dewey-Burdock projects straddling the Wyoming-South Dakota border and enables the Company
to quicken development of its Gas Hills project in Wyoming.
Alta Mesa is an In Situ Recovery ("ISR")
uranium project in South Texas, with a fully licensed Central Processing Plan ("CPP") with 1.5 million pounds U3O8
per year capacity through the existing ion exchange ("IX") circuit that is planned for restart in early 2024. The CPP
has the capacity to process, dry, and package up to 2 million pounds U3O8 per year, and that capacity can be met
with the installation of additional IX resin processing circuits similar to those in use at enCore's Rosita CPP. The project hosts a National
Instrument 43-101 resource of 3.41 million pounds at 0.109% U3O8 in the Measured and Indicated category with an
additional 16.79 million pounds at 0.120% U3O8 in the Inferred category, and there is significant potential to grow
the mineral resources within the approximately 200,000 acre (80,900 Ha) project area. In February 2023, enCore acquired the Alta
Mesa project for US$120 million from Energy Fuels, Inc.
William M. Sheriff, Executive Chairman, and Paul Goranson,
Chief Executive Officer, will host an online webinar on Thursday December 7th, 2023 at 11:00 AM ET. To join the webinar please register
at: https://us02web.zoom.us/webinar/register/WN_LrznPkW1TkaJiL2rWM9fKg.
William M. Sheriff, enCore's Executive Chair, stated:
"enCore is eager to accelerate its production and development activities across our entire portfolio of assets. This transaction
provides enCore with proceeds of US$70 million on closing, giving us the financial flexibility to ramp up our efforts in Texas, Wyoming
and South Dakota. The accelerated production plan is designed to take advantage of what is projected to be a very strong uranium
market over the next decade, with the world's rapidly growing focus on nuclear energy as a clean and reliable energy source. This
surge in demand is coming at a time when the supply of uranium is already tight, with a heavy reliance on imports through Russia. In this
70/30 partnership with Boss Energy, a AUD$1.5 billion market capitalization emerging ISR producer, enCore will continue as manager of
the Alta Mesa joint venture. This accretive transaction provides us with the means to expand our future production profile on an
aggressively expedited timeline."
Paul Goranson, enCore's Chief Executive Officer, added:
"We are pleased to welcome Boss Energy, with its experienced management team, as a partner at Alta Mesa, which hosts a 200,000 acre
land position within the heart of the Texas Uranium Belt. The capital received on closing will allow enCore to ramp up both exploration
and development drilling not only at Alta Mesa but across our entire US portfolio. Existing licenses, at both the Rosita and Alta Mesa
CPPs, enable enCore to more than double the combined production capacity of both CPPs without further permits or license amendments. Deployment
of the same satellite IX resin operating process utilized at Rosita will allow the full use of the 2 million pounds of uranium per year
processing capacity at Alta Mesa. Finally, we look forward to collaborating with Boss Energy to advance our proprietary PFN technology,
which provides enCore with the tools to analyze uranium data in real time, representing a major advantage in cost and time to install
wellfields utilized in the ISR process."
Transaction Terms
The key terms of the Agreement include:
- A joint venture on Alta Mesa with enCore holding a 70% joint venture
interest and remaining the project manager, and Boss Energy holding a 30% joint venture interest in exchange for a payment of US$60 million
to enCore;
- A private placement by Boss Energy of US$10 million into enCore
shares at a price of US$3.90 per share;
- A Strategic Collaboration Agreement on the use and joint technological
advancement of enCore's proprietary PFN technology for real-time uranium analysis;
- A loan from Boss Energy to enCore of up to 200,000 pounds of physical
uranium at commercial rates from Boss Energy's strategic stockpile, allowing enCore the flexibility to optimize its contracts and potential
spot sales. The loan can be repaid in cash or in kind with uranium.
Pursuant to the Agreement, enCore will establish a
new subsidiary (the "JV Company") to hold the Alta Mesa project that will, on closing, be owned 70% by an existing subsidiary
of enCore and 30% by a new US subsidiary of Boss Energy. In consideration for its 30% interest in the JV Company, Boss Energy will,
on closing, pay enCore US$60 million in cash, and concurrently purchase US$10 million in common shares of enCore at a price of US$3.90
per common share. enCore will act as Manager of the JV Company for so long as enCore remains majority owner and will be entitled
to customary management fees. The JV Company will distribute uranium from production at Alta Mesa on a pro-rata basis to enCore
and Boss Energy's ownership interest. Dilution of a party's interest below 10% will result in the right of the other party to acquire
that interest or that interest being converted to a 1% production royalty on Alta Mesa.
In connection with the Agreement, the parties will
enter into a uranium loan agreement providing for up to 200,000 pounds of uranium to be loaned by Boss Energy to enCore. The loan
plus interest of 9% will be repayable in 12 months in cash or uranium at the election of Boss Energy.
The parties will also enter into a strategic collaboration
agreement providing for the joint collaboration and research to develop the Company's PFN technology, to be funded equally by each party.
Closing of the transactions contemplated under the
Agreement is expected to occur in February of 2024 and may be extended in certain circumstances. Closing is subject to certain customary
conditions, including certain regulatory approvals and stock exchange approvals, in addition to Boss Energy completing a financing to
fund the cash payments on closing. The Agreement also provides for customary deal protections and a break fee in the event the funding
condition is not met.
Alta Mesa ISR Uranium Central Processing Plant ("Alta Mesa CPP")
& Wellfield
The Alta Mesa CPP and Wellfield hosts a fully licensed
and constructed ISR uranium plant, located on approximately 200,000 acres of private land in the state of Texas. Alta Mesa will be enCore's
second producing location, planned for production in the first half of 2024 following the recently announced resumption of uranium production
at the South Texas Rosita Uranium Processing Plant ("Rosita").
Primary operating capacity at the Alta Mesa CPP is
1.5 million pounds of U3O8 (uranium) per year with additional back-end capacity of 0.5 million pounds of U3O8
per year, using feed from remote satellite IX facilities that can be installed across the approximately 200,000 acre project area
or on other projects. This will utilize fully the CPP's existing capacity of 2 million pounds of U3O8 per
year.
Alta Mesa CPP and Wellfield highlights:
- The Alta Mesa CPP is enCore's third fully licensed production
facility, along with the Rosita CPP and Kingsville Dome CPP, all located in the business-friendly state of Texas. There are only eleven
(11) licensed and constructed uranium production facilities in the United States (US);
- Advancing the Alta Mesa CPP, in conjunction with planned production
in 2023 at the Rosita CPP, will cement enCore's position as the early leader in ISR uranium production in the United States;
- Alta Mesa CPP's operations are located on private land, with 100%
of minerals privately owned, and in a supportive jurisdiction with primary regulatory authority residing with the State of Texas;
- The Alta Mesa CPP utilizes well-known ISR technology to extract
uranium in a non-invasive process using natural groundwater and oxygen, coupled with a proven ion exchange process, to recover the uranium.
As previously reported, enCore continues work on the
refurbishment of the processing circuits. The elution circuit, used to strip uranium from the ion exchange beads, has been completed,
and represents a significant milestone in the pathway for production restart. All the process pumps for the startup IX circuit have been
rebuilt and replaced, including the main injection pumps. We anticipate completing the refurbishment of the startup portion of the IX
circuit before the end of 2023.
The yellowcake processing circuit refurbishment has
started with the rebuilding of key components of the yellowcake storage systems and ordering of long lead time items such as the filter
press and yellowcake transfer pumps. Refurbishment work commenced on the yellowcake drying system, and that work is expected to be completed
just prior to the anticipated production restart date.
Within Production Authorization Area 7 (PAA-7), enCore
is installing injection and production wells in the wellfield and has received and staged the equipment to install the pipelines to connect
the wellfield to the Alta Mesa CPP. All the necessary equipment for the startup of production in the PAA-7 wellfield has been received
or has been ordered with a confirmed delivery schedule.
Alta Mesa & Mesteña Grande Mineral
Resource Summary (0.30 GT cut-off)1,2 |
Tons
|
Avg. Grade
(% U3O8) |
Pounds
|
Total Measured Mineral Resource1 |
54,000 |
0.152 |
164,000 |
Alta Mesa Indicated Mineral Resource |
1,397,000 |
0.106 |
2,959,000 |
Mesteña Grande Indicated Mineral Resource |
119,000 |
0.120 |
287,000 |
Total Measured & Indicated Resources |
1,570,000 |
0.109 |
3,410,000 |
Alta Mesa Inferred Mineral Resource |
1,263,000 |
0.126 |
3,192,000 |
Mesteña Grande Inferred Mineral Resource |
5,733,000 |
0.119 |
13,601,000 |
Total Inferred Resources |
6,996,000 |
0.120 |
16,793,000 |
1,2 Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields. Wellfield recovery factors have not been applied to indicated and inferred mineral resources. As reported in the NI-43-101 Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, USA completed by Doug Beahm, PE, PG, of BRS Engineering. (Effective January 19, 2023). 2. Grade Thickness, or GT, is defined as the product of the mineral grade, as % U3O8, multiplied by the thickness, in feet, of the mineralization. Bold type represents potentially ISR recoverable uranium with a Grade Thickness of >0.3 which is considered suitable for inclusion in a wellfield. |
To view enCore's South Texas projects please visit:
bit.ly/3fV9fTg.
The Company advises that it is not basing its production
decisions at Alta Mesa CPP or Rosita CPP on a feasibility study of mineral reserves demonstrating economic and technical viability. The
production decision is based on known past ISR and processing operations at these two production facilities and surrounding lands. However,
the Company understands that there is increased uncertainty, and consequently a higher risk of failure, when production is undertaken
in advance of a feasibility study. The Company has determined to proceed with a production decision based on past operations at
the Alta Mesa CPP and Rosita CPP, including past ISR operations in the known mineral resource areas.
Recommendations By the Board of Directors and Fairness Opinion
The Board of Directors of enCore (the "Board"),
after consultation with its financial and legal advisors, has unanimously approved the transaction. The Board, in conducting its review
of the transaction, was advised by Haywood Securities Inc. ("Haywood") and received a fairness opinion from Haywood which determined
that, in Haywood's opinion, based upon and subject to the assumptions, limitations and qualifications set out therein, the consideration
to be received by enCore in connection with the transaction is fair to enCore from a financial point of view. Hunton Andrews Kurth LLP
and Morton Law LLP are acting as legal advisors to enCore in connection with the Transaction.
John M. Seeley, Ph.D., P.G., C.P.G., enCore's Manager
of Geology and Exploration, and a Qualified Person under NI 43-101, has reviewed and approved the technical disclosure in this news release
on behalf of the Company.
About Boss Energy Limited
Boss Energy (ASX: BOE; OTCQX: BQSSF) with a market
capitalization of ~A$1.5 billion, has almost completed development of its Honeymoon Uranium Project in South Australia. The project is
on time and on budget. Annual production at Honeymoon is forecast to ramp up to 2.45Mlbs of U3O8. For
more information please visit www.bossenergy.com.
About enCore Energy Corp.
enCore Energy Corp., America's Clean Energy Company™,
is committed to providing clean, reliable, and affordable domestic nuclear energy as the newest uranium producer in the United States.
enCore solely utilizes In-Situ Recovery ("ISR") for uranium extraction, a well-known and proven technology co-developed by the
leaders at enCore Energy. In-Situ Recovery extracts uranium in a non-invasive process using natural groundwater and oxygen, coupled with
a proven ion exchange process, to recover the uranium. Uranium production commenced at enCore's licensed and past-producing South Texas
Rosita Central Processing Plant (CPP) in November 2023 and at its licensed and past-producing South Texas Alta Mesa CPP in 2024.
Future projects in enCore's production pipeline include
the Dewey-Burdock project in South Dakota and the Gas Hills project in Wyoming, along with significant uranium resource endowments in
New Mexico providing long term opportunities. The enCore team is led by industry experts with extensive knowledge and experience in all
aspects of ISR uranium operations and the nuclear fuel cycle. enCore diligently works to realize value from other owned assets, including
our proprietary uranium database that includes technical information from many past producing companies, from our various non-core assets,
and by leveraging our ISR expertise in researching opportunities that support the use of this technology as applied to other metals. enCore
is also committed to working with local communities and indigenous governments to create positive impact from corporate developments.
www.encoreuranium.com
Cautionary Note Regarding Forward Looking Statements:
Neither TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
release.
Certain information contained in this news release,
including: any information relating to the Company being a leading uranium company, statements regarding future or potential production,
and any other statements regarding future expectations, beliefs, goals or prospects; may constitute "forward-looking information"
and "forward-looking statements" within the meaning of applicable Canadian and United States securities laws and regulations
(collectively, "forward-looking statements"). All statements in this news release that are not statements of historical fact
(including statements containing the words "expects", "is expected", "does not expect", "plans",
"anticipates", "does not anticipate", "believes", "intends", "estimates", "projects",
"potential", "scheduled", "forecast", "budget" and similar expressions or variations (including
negative variations) of such words and phrases, or statements that certain actions, events or results "may", "could",
"would", "might" or "will" be taken) should be considered forward-looking statements. Such forward-looking
statements include statements regarding completion of the transactions contemplated in the Agreement, and regarding our planned extraction
and production operations. All such forward-looking statements are subject to important risk factors and uncertainties, many of
which are beyond the company's ability to control or predict. Forward-looking statements necessarily involve known and unknown risks,
including, without limitation, risks associated with general economic conditions; adverse industry events; future legislative and regulatory
developments; the ability of the parties to the Agreement to satisfy all conditions to closing of the transactions contemplated therein,
the ability of enCore to implement its business strategies; including commencement of production at Alta Mesa in the planned time frames
or at all; the expansion of operations to satellite locations; and other risks. A number of important factors could cause actual results
or events to differ materially from those indicated or implied by such forward-looking statements, including without limitation access
to capital risks in connection with the Agreement and otherwise, exploration and development risks, changes in commodity prices, access
to skilled mining personnel, the results of exploration and development activities; production risks; uninsured risks; regulatory risks;
defects in title; the availability of materials and equipment, timeliness of government approvals and unanticipated environmental impacts
on operations; litigation risks; risks posed by the economic and political environments in which the Company operates and intends to operate;
increased competition; assumptions regarding market trends and the expected demand and desires for the Company's products and proposed
products; reliance on industry equipment manufacturers, suppliers and others; the failure to adequately protect intellectual property;
the failure to adequately manage future growth; adverse market conditions, the failure to satisfy ongoing regulatory requirements and
factors relating to forward looking statements listed above which include risks as disclosed in the Company's annual information form
filings. Should one or more of these risks materialize, or should assumptions underlying the forward-looking statements prove incorrect,
actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. The
Company assumes no obligation to update the information in this communication, except as required by law. Additional information identifying
risks and uncertainties is contained in filings by the Company with the various securities commissions which are available online at www.sec.gov
and www.sedar.com. Forward-looking statements are provided for the purpose of providing information about the current expectations, beliefs
and plans of management. Such statements may not be appropriate for other purposes and readers should not place undue reliance on these
forward-looking statements, that speak only as of the date hereof, as there can be no assurance that the plans, intentions or expectations
upon which they are based will occur. Such information, although considered reasonable by management at the time of preparation, may prove
to be incorrect and actual results may differ materially from those anticipated. Forward-looking statements contained in this news release
are expressly qualified by this cautionary statement.
View original content to download multimedia:https://www.prnewswire.com/news-releases/encore-energy-enters-us70-million-transaction-with-boss-energy-proceeds-to-accelerate-company-wide-uranium-production-plans-302006893.html
SOURCE enCore Energy Corp.
View original content to download multimedia: http://www.newswire.ca/en/releases/archive/December2023/06/c8335.html
%CIK: 0001500881
For further information: William M. Sheriff, Executive Chairman,
972-333-2214, info@encoreuranium.com
CO: enCore Energy Corp.
CNW 06:00e 06-DEC-23
enCore Energy (AMEX:EU)
Historical Stock Chart
From Oct 2024 to Nov 2024
enCore Energy (AMEX:EU)
Historical Stock Chart
From Nov 2023 to Nov 2024