Golar Power completes 96 hour reliability test at 1.5GW Sergipe Power Plant
March 17 2020 - 1:05PM
Golar Power Limited (“Golar Power”) has
successfully completed today the final operational test at the
1.5GW Sergipe Power Plant.
The test involves supplying the maximum load of
the plant (1.5 GW) to the National Interconnected System (SIN) for
a period of 96 continuous hours. The test is the final requirement
of the National System Operator (ONS) in order to start commercial
operations under the 25-year power purchase agreements.
For the test, the three gas turbines, the steam
turbine and three heat recovery boilers operated in a combined
cycle and delivered a volume in excess of 1.5GW, for 96 continuous
hours. The test was successfully completed this morning at 03:00am
(GMT).
Hamilton, Bermuda
March 17, 2020
Enquiries:
Golar Management Limited: + 44 207 063 7900
Eduardo Maranhao
Stuart Buchanan
Gol Linhas Aereas Inteli... (NYSE:GOL)
Historical Stock Chart
From Sep 2024 to Oct 2024
Gol Linhas Aereas Inteli... (NYSE:GOL)
Historical Stock Chart
From Oct 2023 to Oct 2024