The following table lists unplanned and planned production
outages at U.S. refineries as reported by Dow Jones Newswires. The
information is compiled from both official and unofficial refining
sources and doesn't purport to be a comprehensive list.
Three workers were injured at a fire at Exxon Mobil Corp.'s
(XOM) refinery in Baton Rouge, La., Wednesday morning. The company
declined to say where the fire took place and the cause is under
investigation, but an Exxon spokesman said general operations were
not affected.
BP PLC (BP) expected to begin maintenance at Pipestill 3A's
Merox unit at its Texas City, Texas, refinery Wednesday evening,
according to state environmental regulatory filing Tuesday.
Pipestill is another name for the crude distillation unit.
Tesoro Corp. (TSO) said that a sixth worker died Tuesday morning
after suffering critical injuries from the Anacortes, Wash.,
refinery fire on April 2. A seventh worker remains in serious
condition at a Seattle hospital.
For more detailed information, search Dow Jones Newswires using
the code N/REF.
Operator Refinery Capacity Description Restart
(in 000s
bbl/day)
UNPLANNED
CANADA
KNOC Newfoundland 115.0 Refinery to return to normal end-March
by end March. The entire plant
was idled early Jan. to advance
maintenance while repairs were
made at a hydrotreater damaged
by fire on Jan. 7.
Valero Quebec City 235.0 66,000-b/d FCCU shut by early-
Quebec day fire on Feb 2 was restarted
over the weekend and returning
to planned rates, Co. said April 12.
Production was impacted by
outage but no major supply
disruptions expected due to ample
inventories, Co. said.
Damage assessment was delayed
due to cold weather, ice on unit.
CARIBBEAN
EAST COAST
GULF COAST
Exxon Baton Rouge 503.0 Three workers injured in a fire
La. on April 14. Co. did not disclose
where it occurred but said general
operations were not affected.
Motiva Norco, La. 236.4 Crude unit, DU-5, shut by fire End
on Jan 22 seen restarting in March
end-March, the Co. said on
March 19.
Motiva Port Arthur 285.0 Restarted delayed coking unit
TX on April 11 after experiencing a
wet gas compressor trip, a filing
stated.
Valero Corpus 340.0 Unplanned maintenance at West March 30
Christi, TX Plant Complex 1 on March 28-30;
SMR Unit 13 cited as emissions
source in regulatory filing.
BP Texas City 455.8 Cat feed hydrotreating unit had
TX a process upset April 9.
MIDWEST
ROCKY MOUNTAINS
WEST COAST
Chevron El Segundo 279.0 Isomax plant shut March 19 n/a
CA due to "small" fire. No
estimate on restart.
Chevron Richmond 245.3 Refinery lost compressor
CA causing flaring April 7.
Tesoro Wilmington 100.0 Hydrocracker Unit Shut April 5.
Tesoro Anacortes 120.0 Fire at naptha unit April 2
WA killed six; one worker remains
in serious condition, company
said April 13.
All production operations to
temporarily shut down later this
month until repair are done and
investigations progress, company said
April 12. Supply will be met from
other companies' refineries or from
spot market. Plant was processing
70,000 b/d if crude after blast.
PLANNED
CANADA
Shell Montreal 130.0 The refinery will be converted
Quebec into a fuel terminal, Co. said
Jan. 7. No timeline provided.
CARIBBEAN
Valero Aruba 235.0 The plant, which
was shut in June for 2-3
months for economic reasons was
closed indefinitely in Nov.
EAST COAST
Hess Port Month-long turnaround work
Reading NJ will take place in April at
the plant's 70,000-b/d
FCCU; the refinery does not
process crude oil.
Sunoco Westville 145.0 Idling all Eagle Point refin- n/a
NJ ing operations indefinitely due
to poor economics, Co. said
Oct. 6.
Reformer unit shut in Girard n/a
Point section in early Oct
for economic reasons. Shutdown
to last 1-6 months.
Valero Delaware 210.0 PBF Investments has reached deal April 2012
to buy plant. Could be fully operational
by April 2012.
Western Yorktown 64.5 Planned work scheduled 3Q 2010. Q3 2010
VA
GULF COAST
Alon Krotz 100.0 Refinery will restart in
Springs, La. April.
BP Texas City 455.8 Ultraformer No. 4 restarted March 23
TX March 23 after shutting down
for repairs on March 19. Emis-
sions are expected to last
until March 27.
Planned maintenance related to
April 6 "J457 compressor" April 1-6.
Train 400 at resid hydrotreater
being restarted April 12 after
maintenance activity.
Maintenance on Pipestill 3A's April 17
Merox unit began April 14 and
to conclude April 17. Pipestill
is another name for a crude
distillation unit.
Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010
Miss. conversion project delayed
from 2008 to 2010 due to
economic factors.
Work is progressing on the
continuous catalytic reformer,
expected to be completed by
mid-2010, Co. said Feb. 25.
Co. is planning to put a premium
base-oil facility at plant.
Conoco Borger 146.0 Shuts FCCU April 7 for repairs April 14
Tx
Conoco Sweeny 247.0 Shuts unnamed unit for work, n/a
Tx April 8.
Flint Corpus $250 mln project for new Spring 2010
Hills Christi, TX diesel desulfurization,
sulfur recovery unit to begin
in Fall 2008. Construction
to last 18 months.
Marathon Garyville 436.0 Plant operating at newly ex- n/a
LA panded capacity and may ex-
ceed it, the co. said on March
25.
Motiva Convent, LA 235.0 Planned turnaround maintenance Early
began Jan 28 at several un- April
specified process units. Re-
start seen in early April.
Motiva Port Arthur 285.0 Expansion project to increase 1Q
TX throughput capacity by 325,000 2012
b/d, to 610,000-b/d, slowed.
Completion now seen 1Q
2012, from 2010.
Valero Corpus 340.0 Plant shut; West Plant n/a
Christi, TX 50,000-b/d FCCU at reduced
rates since mid-Dec for
economic reasons.
36,000-b/d HCU in West Plant March
restarted, Co. said March 16,
after about 18 days of work
delayed from Feb.
Planned work on SMR unit began
at West Plant on April 12.
Complex 1 and 3 at West Plant
undergoing maintenance on
April 13-16.
Valero Norco, LA 250.0 Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker turnaround lasting
38 days has begun, Co. said
March 15.
77,000-b/d FCCU at reduced n/a
rates since mid-Dec for
economic reasons.
Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a
rates since mid-Dec for
economic reasons.
Valero Texas City 245.0 Repaired an exchanger leak
TX found in the alkylation unit
located at Complex 2, Co.
said March 15.
Marathon Texas City 76.0 FCCU being restaretd March 31
TX after completing required
maintenance.
MIDWEST
BP Toledo, OH 155.0 $400 million upgrade 2012
to start 2010.
Valero Memphis, TN 195.0 Crude unit restarted, while end-
overhaul of FCCU and alky- April
lation unit continues, the
company said March 26.
The entire plant had been
off-line since March 14.
Marathon Catlettsburg 226.0 Turnaround maintenance at un- n/a
KY specified units starts March
10. No restart estimate.
ROCKY MOUNTAIN
Western Bloomfield, 16.8 Co. announced plans Nov. 9
NM to idle plant and shift
production to Gallup plant.
Suncor Commerce 93.0 No. 1 Crude unit will shut for Mar 22
City, CO planned maintenance on Mar 6;
restart Mar 22.
Cryo Unit will shut for planned Apr 4
maintnenance Mar 20; restart
April 4.
Planned work at reformer unit Fall
deferred to Fall 2010 from Feb 2010
28 start date.
Tesoro Salt Lake 58.0 Major turnaround work will
City, Utah begin in 1Q 2010, the Co. said
on Feb 3.
Tesoro Mandan, N.D. 60.0 Planned turnaround will 2Q
begin 2Q 2010, the Co. said
on Feb 3.
WEST COAST
Exxon Torrance, CA 150.0 FCCU, alkylation unit shut Apr 10
March 20-21 as part of turn-
around maintenance that be-
gan March 1 at several units.
The work is expected to last
for 40 days, trade sources said
on Feb. 11.
BP Carson, CA 265.0 Planned flaring activity on
March 29-April 20 and, Co. reported
in filings.
Planned flaring activity reported
for April 4-9, an April 1 filing said.
Planned flaring for April 14-20, Co.
reported April 13.
Tesoro Golden Eagle 166.0 Turnaround work began in early n/a
Martinez, Dec at FCCU and alkylation
CA unit, the Co. said on Feb 3.
Restart timing unclear.
Other major turnaround mainte- 2011
nance deferred to 2011 from
late 2009, the Co. said Feb 3.
Tesoro Oahu, HI 94.0 Planned turnaround work will
Kapolei begin 3Q, 2010, the Co. said
on Feb 3.
Planned work deferred to 2011 from
late 2009, the Co. said Feb 3.
Chevron El Segundo 279.0 Reported flaring and cause was being
CA investigated, an April 9 filing said.
Order free Annual Report for BP plc
Visit http://djnewswires.ar.wilink.com/?link=BP or call
1-888-301-0513
Order free Annual Report for ConocoPhillips
Visit http://djnewswires.ar.wilink.com/?link=COP or call
1-888-301-0513
Order free Annual Report for Hess Corporation
Visit http://djnewswires.ar.wilink.com/?link=HES or call
1-888-301-0513
Order free Annual Report for Holly Corp.
Visit http://djnewswires.ar.wilink.com/?link=HOC or call
1-888-301-0513
Order free Annual Report for Marathon Oil Corporation
Visit http://djnewswires.ar.wilink.com/?link=MRO or call
1-888-301-0513
Order free Annual Report for Suncor Energy Inc.
Visit http://djnewswires.ar.wilink.com/?link=SU or call
1-888-301-0513
Order free Annual Report for Tesoro Corporation
Visit http://djnewswires.ar.wilink.com/?link=TSO or call
1-888-301-0513
Order free Annual Report for Exxon Mobil Corporation
Visit http://djnewswires.ar.wilink.com/?link=XOM or call
1-888-301-0513