Argonaut Gold Inc. (TSX: AR) (the "Company",
"Argonaut Gold" or "Argonaut") is pleased to announce today a
reaffirmation of the estimated cost to completion of its 100% owned
Magino project and a funding package which is expected to fully
finance construction of the project.
Debt Commitment
The Company has received a binding commitment
letter from a syndicate of lenders for the financing of a six year,
US$200 million term loan credit facility and a three year revolving
credit facility of US$50 million (the "Facilities"), for a total
debt Facilities limit of US$250 million. The proceeds of the
Facilities are to be used to refinance the Company's existing debt
and for general corporate purposes, including ongoing development
and expansion capital of the Magino project in Ontario, Canada and
other producing assets.
Larry Radford, President and CEO of Argonaut,
commented: "Magino is a long life, low cost mine in an outstanding
mining jurisdiction. This debt financing arrangement, along side
the proposed equity financing, will put Argonaut Gold in a strong
financial position to complete the Magino project and move it
forward into production by the end of Q1 2023."
Key Facility Terms
The term loan facility of US$200 million is a
six year term and is to be repaid in 20 quarterly principal
repayments equal to 5.0% of the outstanding balance commencing on
September 30, 2023, with no penalty for voluntary prepayment.
The revolving credit facility of US$50 million
is a three year term.
The Facilities will bear an interest rate of
1.25% per annum on the committed but undrawn portions, and a rate
on drawn portions equal to the Adjusted Term Secured Overnight
Financing Rate plus 6.00% per annum.
US$80 million from the Facilities will be
available at closing to refinance existing secured debt, with
additional drawdowns available following satisfaction of conditions
precedent. Closing is expected by the end of August 2022.
In addition, conditions precedent to the
availability of the Facilities include, without limitation:
- mandatory gold
hedging by the Company covering 300,000 ounces at a certain minimum
hedge price between the years 2023 and 2027;
- Canadian dollar
to US dollar foreign exchange hedging program by the Company
covering the period up to project completion and rolling 12-month
coverage thereafter;
- a minimum of
US$150 million (net of fees and expenses) in equity to be raised,
of which US$123 million must be raised and spent prior to initial
drawdown;
- independent
technical engineers and the lenders to complete a detailed review
of:
- updated cost to
complete estimate and project schedule in respect of the Magino
project;
- grade control
drilling plan and master blasting plan;
- Magino project
operating costs;
- other
information reasonably requested by the independent technical
engineers;
- evidence that
sufficient funding is available to achieve project completion for
the Magino project; and
- other customary
conditions precedent.
Dave Ponczoch, CFO of Argonaut, said: "Under the
terms of the new Facilities, Argonaut is able to access up to
US$250 million as needed for corporate and development purposes.
The size and terms of the Facilities give Argonaut the flexibility
to meet all foreseeable requirements for the near future."
The Company anticipates that the debt financing
solution together with the equity contribution from the proposed
equity financing will fully finance the remaining portion of its
Magino project. Endeavour Financial assisted the Company as its
financial advisor.
Proposed Equity Financing
In addition, the Company announces that it is
commencing a marketed offering (the "Offering") of common shares of
the Company (the "Offered Shares"). The Offering will be conducted
through a syndicate of agents led by BMO Capital Markets,
Scotiabank and Cormark Securities.
The net proceeds of the Offering will be used
for the development of the Magino Project and for general corporate
purposes.
The Offered Shares will be offered in each of
the provinces and territories of Canada, other than Québec,
pursuant to a prospectus supplement to the Company's base shelf
prospectus dated June 2, 2022 (collectively, the "Prospectus") and
in the United States on a private placement basis to "qualified
institutional buyers" pursuant to an exemption from the
registration requirements of the United States Securities Act of
1933, as amended (the "U.S. Securities Act").
The Offering is expected to be priced in the
context of the market, with the final terms of the Offering to be
determined at the time of pricing. There can be no assurance as to
whether or when the Offering may be completed, or as to the actual
size or terms of the Offering. The closing of the Offering will be
subject to market and other customary conditions and Toronto Stock
Exchange approval.
In addition, the Company will grant to the
agents an option, exercisable in whole or in part in the sole
discretion of the agents at any time up to 30 days from and
including the closing date of the Offering, to offer to sell up to
an additional 15% of the Offered Shares pursuant to the proposed
Offering on the same terms and conditions to cover over-allotments,
if any, and for market stabilization purposes.
Copies of the Prospectus, following filing of
the prospectus supplement, may be obtained on SEDAR at
www.sedar.com and from BMO Capital Markets, Brampton Distribution
Centre C/O The Data Group of Companies, 9195 Torbram Road,
Brampton, Ontario L6S 6H2 by telephone at 905-791-3151 Ext 4020 or
by email at torbramwarehouse@datagroup.ca. The Prospectus contains
important detailed information about the Company and the proposed
Offering. Prospective investors should read the Prospectus and the
other documents the Company has filed on SEDAR at www.sedar.com
before making an investment decision.
Corporate Governance
The board of directors (the "Board") of Argonaut
formed a special committee (the "Special Committee") consisting of
unconflicted members of the Board, to consider the proposed terms
of the Offering, including the number of securities issuable, the
number of Offered Shares issuable to insiders and the offering
price being at a discount to the market price. The Special
Committee has met separately from the full Board. After careful
consideration, the Special Committee unanimously recommended that
the Company approve the terms of the Offering relating to these
matters.
The involvement of insiders in the transactions
referred to above in connection with the Offering are "related
party transactions" within the meaning of Multilateral Instrument
61-101 – Protection of Minority Security Holders in Special
Transactions ("MI 61-101") and the Company is relying on the
exemptions in sections 5.5(g) and 5.7(e) of MI 61-101 in connection
with such transactions.
Argonaut has made application to the TSX,
pursuant to the provisions of Section 604(e) of the TSX Company
Manual, for a "financial hardship" exemption from the requirements
to obtain shareholder approval of the Offering, on the basis that
absent the Offering the Company is in serious financial difficulty
due to the lack of available cash and funding resources. The
Offering is designed to improve the Company's financial situation.
The application was made upon the recommendation of the Special
Committee and was based on the determination that the transactions
are reasonable for Argonaut in the circumstances.
Argonaut expects that, as a consequence of its
financial hardship application, the TSX will commence a delisting
review of Argonaut, which is normal practice when a listed issuer
seeks to rely on this exemption. Although Argonaut believes that it
will be in compliance with all continued listing requirements of
the TSX and will be in a strong financial position upon the closing
of the Offering and the Facilities, no assurance can be provided as
to the outcome of such review or continued qualification for
listing on the TSX. There can be no assurance that the TSX will
accept the application for the use of the financial hardship
exemption from the requirement to obtain shareholder approval
described above.
Magino Construction Update
The Company has recently completed a detailed
review of the estimated cost to completion ("EAC") of its Magino
project and, consistent with the Company’s press release dated May
11, 2022, now estimates the EAC at approximately C$920 million, a
C$120 million increase from the December 14, 2021 EAC of C$800
million. As at May 31, 2022, the Company had committed
approximately C$659 million, had incurred approximately C$473
million, estimates the project is approximately 50% complete and
that the project remains on schedule for first gold pour by the end
of March 2023. The Magino project management team has been
augmented to improve project controls.
The updated EAC factors in the following
changes:
- an updated
estimate for the engineering, procurement, and construction
contract, including direct and indirect costs to maintain first
quarter 2023 production;
- incorporation
of actual contractor productivities;
- escalation of
pricing of consumables, such as diesel, explosives, etc.;
- refinement of
contingency to C$34 million (representing a reduction of C$26
million) and inclusion of management reserve of C$14 million, with
management reserve being defined as having an identified scope with
a lower probability of needing to be spent;
- alignment of
the EAC with the scope related to permitting;
- scope for
additional road construction; and
- COVID-19
costs.
The following diagrams display the updated EAC
breakdown for the Magino project by category and by capital item,
as compared to the prior EAC estimate. All figures in the chart
below are in Canadian dollars.
No securities regulatory authority has either
approved or disapproved of the contents of this news release. The
common shares of the Company have not been and will not be
registered under the U.S. Securities Act or any state securities
laws. Accordingly, the Offered Shares may not be offered or sold
within the United States unless registered under the U.S.
Securities Act and applicable state securities laws or pursuant to
exemptions from the registration requirements of the U.S.
Securities Act and applicable state securities laws. This news
release does not constitute an offer to sell or a solicitation of
an offer to buy any securities of the Company in any jurisdiction
in which such offer, solicitation or sale would be unlawful.
Cautionary Note Regarding
Forward-looking Statements
This press release contains certain
"forward-looking statements" and "forward-looking information"
under applicable Canadian securities laws concerning the business,
operations and financial performance and condition of Argonaut.
Forward-looking statements and forward-looking information include,
but are not limited to statements with respect to the use of
proceeds from the Offering and the Facilities, the Magino project,
the realization of mineral reserve estimates; the timing and amount
of estimated future production; costs of production; estimated
production and mine life of the various mineral projects of
Argonaut; timing of approval for modifications to existing permits;
permitting and legal processes in relation to mining permitting and
approval; the benefits of the development potential of the
properties of Argonaut; the future price of gold, copper, and
silver; the estimation of mineral reserves and resources; success
of exploration activities; and currency exchange rate fluctuations.
Except for statements of historical fact relating to Argonaut,
certain information contained herein constitutes forward-looking
statements. Forward-looking statements are frequently characterized
by words such as "plan," "expect," "project," "intend," "believe,"
"anticipate", "estimate" and other similar words, or statements
that certain events or conditions "may", "should" or "will" occur.
Forward-looking statements are based on the opinions and estimates
of management at the date the statements are made and are based on
a number of assumptions and subject to a variety of risks and
uncertainties and other factors that could cause actual events or
results to differ materially from those projected in the
forward-looking statements. Many of these assumptions are based on
factors and events that are not within the control of Argonaut and
there is no assurance they will prove to be correct.
Factors that could cause actual results to vary
materially from results anticipated by such forward-looking
statements include the possibility of project cost overruns or
unanticipated costs and expenses; variations in ore grade or
recovery rates; changes in market conditions; risks relating to the
availability and timeliness of permitting and governmental
approvals; risks relating to international operations; fluctuating
metal prices and currency exchange rates; changes in project
parameters; labour disputes and other risks of the mining industry,
failure of plant, equipment or processes to operate as
anticipated.
These factors are discussed in greater detail in
Argonaut's most recent Annual Information Form and in the most
recent Management's Discussion and Analysis filed on SEDAR, which
also provide additional general assumptions in connection with
these statements. Argonaut cautions that the foregoing list of
important factors is not exhaustive. Investors and others who base
themselves on forward-looking statements should carefully consider
the above factors as well as the uncertainties they represent and
the risk they entail. Argonaut believes that the expectations
reflected in those forward-looking statements are reasonable, but
no assurance can be given that these expectations will prove to be
correct and such forward-looking statements included in this press
release should not be unduly relied upon. These statements speak
only as of the date of this press release.
Although Argonaut has attempted to identify
important factors that could cause actual actions, events, or
results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be anticipated, estimated or
intended. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Argonaut undertakes no obligation to update forward-looking
statements if circumstances or management's estimates or opinions
should change except as required by applicable securities laws. The
reader is cautioned not to place undue reliance on forward-looking
statements. Statements concerning mineral reserve and resource
estimates may also be deemed to constitute forward-looking
statements to the extent they involve estimates of the
mineralization that will be encountered if the property is
developed. Comparative market information is as of a date prior to
the date of this document.
About Argonaut Gold
Argonaut Gold is a Canadian gold company engaged
in exploration, mine development and production. Its primary assets
are the El Castillo mine and San Agustin mine, which together form
the El Castillo Complex in Durango, Mexico, the La Colorada mine in
Sonora, Mexico and the Florida Canyon mine in Nevada, USA. The
Company also holds the construction stage Magino project, the
advanced exploration stage Cerro del Gallo project and several
other exploration stage projects, all of which are located in North
America.
For more information,
contact:
Argonaut Gold Inc.
Dan Symons
Corporate Development & Investor
Relations
Phone: 416-915-3107
Email: dan.symons@argonautgold.com
Source: Argonaut Gold Inc.
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/32e3a564-a36e-4633-99c2-022371a5eab4
Argonaut Gold (TSX:AR)
Historical Stock Chart
From Nov 2024 to Dec 2024
Argonaut Gold (TSX:AR)
Historical Stock Chart
From Dec 2023 to Dec 2024