TSX: ASND
www.ascendantresources.com
- Completes Requirement for Project Ownership to Increase to
80%
- Robust economics to drive construction funding
- solid operating basis to drive initial production
- Optimization program commenced to further enhance
economics
Highlights of the 2023 Definitive Feasibility Study
include:
- Post-tax NPV8% of US$147
million and 39% IRR
- Average annual payable zinc equivalent ("ZnEq") production of
124 million lbs per annum over first 5 years
- Average All-in Sustaining Cost ("AISC") of US$0.59/lb ZnEq over first 5 years
- Robust Average EBITDA of US$75.5
million per annum over the first 5 years
- Upfront capex requirement of US$164
million (including US$12
million of contingency)
- Inaugural NI 43-101 compliant Proven and Probable Reserves in
the North Zone and South Zones of 14.6Mt at an average NSR of
US$66.1/tonne
- Updated NI 43-101 compliant Mineral Resource of:
-
- North Zone: 8.9Mt at 10.52% ZnEq Measured and Indicated
and additional Inferred Resources of 0.5Mt at 6.62% ZnEq
- South Zone: 10.0Mt at 1.22% Copper Equivalent ("CuEq") and
additional Inferred resources of 8.1MT at 1.16% Cu Eq.
- Fulfilled option requirement to deliver 80% indirect ownership
in the Lagoa Salgada Project;
- Metallurgical results confirm strong metal recoveries and
saleable concentrates
- Optimization Program commenced to enhance NPV, IRR and
operational efficiencies targeted for completion by year end.
TORONTO, July 25,
2023 /CNW/ - Ascendant Resources Inc.
(TSX: ASND) (FRA: 2D9) ("Ascendant" or the "Company") is pleased to
announce results of its initial NI 43-101 Feasibility Study ("FS")
for its Venda Nova deposit at its Lagoa Salgada VMS Project in
Portugal, based upon an updated
Mineral Reserves and Resources Estimate. The completion of the FS
satisfies Ascendant's earn-in option requirements to move to 80%
ownership, subject to closing documentation with all other
conditions having previously been met.
The FS was completed by QUADRANTE, a multidisciplinary
engineering and consulting company with more than 25 years of
experience in Europe, Africa and the Americas. Mine planning, design
and engineering was undertaken by IGAN INGENIERÍA, an independent
consulting firm specializing in mine planning and engineering for
open pit and underground mining projects and operations based in
Spain. The DFS is based on the NI
43-101 Mineral Resource estimate completed by MICON International
dated May 31, 2023 and Mineral
Reserves estimate completed by IGAN dated June 16, 2023. Golder Associates has been engaged
to provide a comprehensive peer review of the entire report. The FS
report will be posted to the Company's profile on SEDAR
imminently.
Mark Brennan, Executive Chairman
of Ascendant stated, "We are very pleased to have completed this
initial feasibility study for the Venda Nova deposit at Lagoa
Salgada. It is the first comprehensive study covering all aspects
of the operations required for the commercialization of the
project. It will also serve to secure our 80% interest in what is
proving to be a robust project, even at this very early stage in
its development. Lagoa Salgada remains a discovery project with
significant upside potential expected as we optimize these results
and as we continue to expand the resource base."
He added, "We believe the results of the FS demonstrate a
solid, economically robust project for what has always been the
initial development phase for the larger potential we see for the
Lagoa Salgada property. Given the nature of VMS deposits to occur
in clusters on the Iberian Pyrite Belt, we see evidence of
potential for several more deposits to be defined in the coming
years to enhance the overall value proposition at Lagoa.
Furthermore, we expect these results to support our current
financing discussions and construction decision in the coming
months."
Optimization
Opportunities
While completing the FS satisfies the requirements for Ascendant
to earn an 80% interest in the project as required under the Earn
In Option agreement, the Company believes that with additional time
now available, the following near-term optimization opportunities
exist to further enhance the FS prior to commencing development
work over the next six months. The Company's initial focus will be
as follows:
- Optimize mine ore sequencing to maximize revenues in the
initial years.
- Optimization of the mining and processing rate to optimize NPV
and IRR; and
- Undertake further metallurgical test work to enhance metal
recoveries above those already achieved in tests to date
Project Overview
The Lagoa Salgada Project is located within the north-western
section of the prolific Iberian Pyrite Belt ("IBP") in Portugal, approximately 80km southeast of
Lisbon, accessible by national
highways and existing roads. The Project is comprised of a single
exploration permit covering an area of approximately 7,209
hectares. The Project represents a high-grade, polymetallic
zinc-lead-copper development and exploration opportunity in a low
risk, established and prolific jurisdiction where the project has
been accorded a Project of National Interest ("PIN") status.
Figure 1. Project Location
Updated Minerals Reserves and
Resources Estimate
Table 1. below outlines the initial NI 43-101 Proven and
Probable Mineral Reserves Estimate prepared by IGAN Ingenieria upon
which the FS was based. Table 2 provides the updated Mineral
Resource Estimate, prepared by Micon International Limited,
("Micon") identified for the Lagoa Salgada project to date. Infill
drilling in 2022 focused upon upgrading sufficient high-grade
mineralization in the North Zone and part of the mineralization in
the South Zone to the Measured and Indicated categories to support
the completion of the FS.
Future drilling is expected to add additional Resources as the
project moves forward to extend the overall mine life and it should
be noted both the North and South zones remain open to future
expansion along strike and at depth for future exploration. In
addition, several regional exploration targets have been identified
for future exploration work to further increase the known mineral
resources on the property, thereby extending the overall mine life
and/or potentially supporting a future expansion.
The estimated Proven and Probable Reserves total 14.6 million
metric tons (Mt), with 7.0Mt in the North Zone having an NSR of
84.1 $/t, and 7.6Mt in the South Zone with an NSR of 49.6 $/t,
sufficient to support an initial mine life of 14+ years based upon
a throughput rate of 1.2Mtpa through the plant as outlined in the
FS. Reserves were defined using an NSR calculation based upon
current metallurgical recoveries, payability, treatment charges and
mining methods.
The project has converted 77% of its Measured and Indicated
resources into reserves: additionally there are 0.5Mt at a grade of
6.62% ZnEq in the North Zone and 8.13Mt at a grade of 1.16% CuEq in
the South Zone of Inferred Resource. Additional drilling is
required to upgrade these additional resources to the Measured and
Indicated categories.
Table 1: Mineral Reserves
NSR cut-off grades were established following Mortimer's
approach to cut-off grades (Hall, 2014)
Table 1a: NSR cut-off values per mining method and
material
|
|
|
|
|
|
|
Mining
Method
|
Material
|
Mining
Cost
|
Processing
Cost
|
Boundary
cut-off
|
G&A
|
Volume
cut-off
|
LHOS
|
STWK
|
19.5
|
16.31
|
35.81
|
2.5
|
38.31
|
PMS
|
19.5
|
19.62
|
39.12
|
2.5
|
41.62
|
TMS
|
19.5
|
14.48
|
33.98
|
2.5
|
36.48
|
GOS
|
19.5
|
16.22
|
35.72
|
2.5
|
38.22
|
STR
|
19.5
|
16.31
|
35.81
|
2.5
|
38.31
|
CF
|
STWK
|
29.98
|
16.31
|
46.29
|
2.5
|
48.79
|
PMS
|
29.98
|
19.62
|
49.60
|
2.5
|
52.10
|
TMS
|
29.98
|
14.48
|
44.46
|
2.5
|
46.96
|
GOS
|
29.98
|
16.22
|
46.20
|
2.5
|
48.70
|
STR
|
29.98
|
16.31
|
46.29
|
2.5
|
48.79
|
Table 2: Mineral Resources (Inclusive of Reserves)
North Zone
South Zone
Mining
In line with previous studies, the mine is designed using a
single access ramp from surface and will target the extraction of
ore from the North and South Zones at a rate of 1.2 million tonnes
per annum ("Mtpa").
Mining will be undertaken by targeting the various sub domains
within the ore deposit to maximize metallurgical recovery. As with
most VMS type deposits, the sub domains reflect a precious metal
rich gossan layer above a Massive Sulphide layer (further divided
into a Transition and Primary layer) and a layer of stockwork
mineralization each with its own metallurgical characteristics. The
mining methods defined are a combination of transverse
sublevel stoping and cut & fill. Paste backfill is to be
used for both mining methods to maximize ore recovery and
productivity while minimizing surface tailing disposition. The
initial years will focus on mining the higher-grade gossan and
massive sulphide zones in the North Zone, followed by the
South Zone as underground access is developed in the early years of
the operation to the South zone. Mining will be conducted using an
owner operated electric fleet which will reduce operating
costs.
Figure 2. Underground Mine Design
(In blue the main ramps and accesses and in green and violet the
ore blocks to be mined)
Metallurgy
Metallurgical test work was completed by Grinding Solutions
("GSL") in Cornwall, UK.
Confirmatory test work was developed by Maelgwyn Mineral Services,
South Africa to confirm metal
recoveries and saleable concentrates have been achieved in
principal domains. Further testing is required to confirm and
improve on current results as fully optimized circuit adjustments
are developed. The Company notes that its consultants have
indicated that the actual performance of operating mines in the
region have typically seen an improvement in concentrate quality
once an industrial scale operation is in production as compared to
lab testing.
The approach to flowsheet development was to prepare
representative master composites for each ore type, then proceed
through open circuit to identify and optimize flowsheet conditions
and reagent schemes. Locked cycle tests were then conducted on
principal master composites to demonstrate the anticipated overall
metallurgical performance within a closed circuit.
Tests were completed on blends of Primary Massive Sulphide
(PMS), Stockwork (STW), Gossan (GO), Transition Massive Sulphide
(TMS) and Stringer (STR) ores to allow comparison with individual
composite results and to assess the viability of co‐processing the
ore types.
Mineralogical assessments were undertaken to provide information
to refine the comminution/beneficiation process during
optimization, and to provide reasonable expectations for
metallurgical performance versus mineral liberation and association
within each ore type. Samples from various open and locked cycle
test products were used to characterize final concentrates and
tailings.
The developed metallurgical models were applied to mine
production schedules as part of the financial modelling process.
The resulting average recoveries over the life of the mine (LOM)
are presented in the table below:
Table 3. Achieved Recoveries by Metal and Domain
Table 4 below highlights the concentrate grade profile as
determined by the various metallurgical testwork. These results are
largely inline with other regional producers. The Project will
produce four concentrates, namely Zinc, Lead, Copper and a Tin
concentrate.
Table 4. Concentrate Technical Specifications
Processing
The mineral treatment plant is based on industry standard
methods and will mainly consist of different process areas where
the mineral will be crushed, ground, and then fed to several
flotation processes where Cu, Pb, Zn and Sn concentrates and Au/Ag
dore bars will be produced. Other than crushing, grinding,
dewatering and auxiliary services, common to all mineral domains,
the remaining process areas will be configured depending on the
mineral domain being processed. The mined material goes through a
grizzly feeder and primary jaw crusher, and then onto a grinding
circuit which consists of a SAG mill, ball mill, and vertical mill
in a closed circuit with hydrocyclones. The material is discharged
into a vibrating screen, with rejected pebbles recirculated to a
pebble crusher.
Grinded material will feed the copper and lead flotation
circuit, that includes aeration and conditioning tanks, rougher
cells, regrinding mill, and cleaning stages. The circuit can
produce bulk or separate Cu and Pb concentrates depending on the
mineral domain being processed. The zinc flotation circuit,
downstream process, consists of conditioning tanks, rougher cells,
regrinding mill, and cleaning stages.
Zinc flotation tailings, feed the sulphide flotation circuit to
remove sulphides before concentrating tin minerals. It includes
conditioning tanks, rougher cells, and cleaner stages. Rougher
tailings flow to the next area, while the concentrate is pumped to
the tailings management area. The tin recovery circuit will consist
of flotation and gravimetric concentration technologies. Flotation
includes conditioner and aeration tanks, rougher and cleaner
stages, with intermediate tin concentrate being processed using
multi-gravity separators to increase the final tin grade. A summary
Flowsheet is provided below.
Figure 3. Simplified Process Flow Diagram
Infrastructure
The Lagoa Salgada Project will be developed on a greenfield site
located in close proximity to the Grândola municipality, in the
Setúbal district, which benefits from well-established
infrastructure, including road and rail transport, power, and water
supply services. Transportation of supplies will be facilitated by
trucks from Portugal or Spanish
locations, while concentrate products will initially be shipped to
the Sines port by road (47km) and subsequently by ship to final
destinations.
The project site will have a compact layout that incorporates
essential components such as the tailings storage facility, ore and
waste dumps, water treatment infrastructure, and various buildings,
including administration, warehouse, laboratory, gatehouse, and
mobile equipment workshop. The processing facilities will consist
of a primary crusher building, ore stockpiles on the ROM pad, a
mill building, and a paste plant building.
The mine will be accessed via a portal and the ore will be
brought to the surface and stored as stockpiles, while waste
stockpiles will be utilized for constructing the embankments of the
Tailings Storage Facility.
The mine plan outlines the processing of 14.8 Mt of ore and the
generation of 1.9 Mt of waste rock. After accounting for
concentrate and underground backfill, a total of 11.3 Mt of
tailings, along with 1.0 Mt of development rock, will be deposited
in the TSF.
Figure 4 Site Layout
Capital Costs
Upfront capital costs are estimated at US$164 million inclusive of US$12 million in contingency. A further
US$102.9 million of sustaining
capital is planned over the 14.5 year mine life, including closure
costs. Pay back is in the order of 2 years with an after-tax IRR of
39%.
Table 5. Capital Costs
Operating Costs
Operating costs are summarized in Table 6 below. All costs are
based on a mining rate of 1.2Mtpa and relied on recent quotes from
various vendors which are consistent with other mines in the
region. On a zinc equivalent per pound basis, Life of Mine C1 Cash
Costs are estimated at US$0.67/lb and
All-In Sustaining Costs are US$0.71/lb over the life of mine.
Table 6. Operating Costs
Production and Operating Cost
Profile
The chart below highlights the expected production and AISC
profile at Venda Nova as per the FS. Production and cash flows are
expected to be stronger in the early years as the processing of the
higher-grade massive sulphide and gossan material is
undertaken.
Production over the mine life is expected to average 77 million
lbs of Zinc equivalent production per year but averages
approximately 124 million lbs of Zinc equivalent production over
the first five years. Similarly, AISC will average
US$0.71/lb per year LOM and
US$0.59/lb over the first five years
on a ZnEq basis.
Figure 5. Production and AISC
Overall Project
Economics
The Venda Nova project at Lagoa Salgada shows strong robust
economics with a Post-Tax NPV at an 8% discount rate of
US$147 million and an IRR of 39% for
a payback period of 2 years at long term consensus metal price
assumptions. Project economics are based on the current Proven and
Probable Reserves only for a mine life of 14.5 years and does not
factor in the upgrading of additional resources or potential future
exploration success.
Table 7 Economic Summary
The mine is expected to benefit from regional tax incentives in
Portugal. Contractual fiscal incentives for productive
investment in Portugal offers a
validity period of up to 10 years for investment projects with
relevant expenditures amounting to €3,000,000 or more. The fiscal
benefit corresponds to 10% of the project's relevant expenditures,
and this rate can be increased based on factors like the location
of the project and the creation of jobs. The benefit takes the form
of a tax credit deducted from the corporate income tax liability.
Additionally, there are provisions for exemptions or reductions in
municipal property tax, property transfer tax, and stamp duty.
These contractual fiscal incentives aim to attract productive
investments, boost economic growth, create employment
opportunities, and support strategic sectors in Portugal. The incentives provide companies
with tax benefits, such as tax credits, deductions, and exemptions,
encouraging investment in various sectors and regions.
In the case of Lagoa Salgada, the maximum tax benefit is
determined by considering the lower value between €24.75 million
(Maximum regional aid intensity applicable) or 15% of the initial
investment. The application method for this incentive involves a
50% reduction in income tax (equivalent to 21% of the taxable
income) until the maximum amount of tax benefit is attained.
The chart below demonstrates the robust free cash flow
generation expected, especially in the first five years of
operation. Cash flows during the first five years of production are
estimated to average US$56 million
per annum.
Figure 6. Free Cash Flow
The chart below highlights the NPV sensitivity to changes in
capital costs, various input costs and Zinc price assumptions.
Figure 7. NPV Sensitivity
Optimization
Opportunities
The completion of the Feasibility study completes the
requirements by Ascendant to Earn an 80% ownership in the project
as required under the Option Earn-In agreement. The Company
believes that with additional time now available, the following
near term optimization opportunities exist to further enhance the
FS prior to commencing development work over the next six months.
The Company's initial focus will be as follows:
- Optimize mine ore sequencing to maximize revenues in the
initial years.
- Optimization of the mining and processing rate to optimize NPV
and IRR;
- Undertake further metallurgical test work on available material
to enhance metal recoveries above those already achieved in tests
to date
On a longer-term basis, the Company has identified additional
areas to further increase the value of the Lagao Salgada project
such as;
- Additional metallurgical test work to continue to enhance
recoveries subject to additional new fresh core
- Increase in mineral reserves and resources to enhance the mine
life or support a larger scale operation via upgrading additional
known resources to the Proven and Probable categories, and the
addition of new ore through new exploration to define additional
resources on the numerous follow up targets known on the
property.
Qualified Persons
An NI 43-101 Technical Report supporting the DFS is being
prepared by Quadrante under the guidance of Mr. João Horta (M.Sc.,
MIMMM), who serves as Project Director at QUADRANTE and is a
"Qualified Person" in accordance with National Instrument 43-101 –
Standards of Disclosure for Mineral Projects. Although the
Qualified Person was not responsible for the completion of some of
the sections of the DFS, such as Geology, Mineral Processing and
Metallurgical, Mineral Resource, Reserve, Mining Methods, Recovery
Methods, TSF, Paste Fill, and Hydrogeological Study, the Qualified
Person at Quadrante has relied on the Qualified Persons listed
below who are the specialists in these fields for completion of
their respective portions of the DFS.
The scientific and technical information contained in this
release relating to the Geology and Mineral Resource Estimate has
been approved and verified by Mr. Charley Murahwi (MSc., P.Geo.,
FAusIMM), Senior Economic Geologist with Micon International
Limited, who is a "Qualified Person" in accordance with National
Instrument 43-101 - Standards of Disclosure for Mineral Projects.
Sampling, analytical, and test data underlying the Mineral Resource
Estimate was also approved and verified by Mr. Charley Murahwi.
The Mineral Reserve calculation and the Mining Methods section
was completed by IGAN Ingenieria under the supervision of Mr. Pablo
Gancedo Mínguez (CEng, MIMMM), who is a "Qualified Person" in
accordance with National Instrument 43-101 – Standards of
Disclosure for Mineral Projects.
The Tailings Storage Facility (TSF) study was completed by SLR
under the supervision of Mr. David
Ritchie (P.Eng, Principal Geotechnical Engineer at SLR), who
is a "Qualified Person" in accordance with National Instrument
43-101 – Standards of Disclosure for Mineral Projects.
Scientific and technical information contained in this release
in relation to metallurgical test work and the Recovery Methods
section has been approved and verified by Mr. David Castro López
(MIMMM), who serves as Process Engineer at Minepro Solutions and is
a "Qualified Person" in accordance with National Instrument 43-101
– Standards of Disclosure for Mineral Projects.
The Hydrogeological Study was completed by Dr. Rafael Fernández
Rubio (PhD, Specialist), which is a Special Consultant at FRASA and
is a "Qualified Person" in accordance with National Instrument
43-101 – Standards of Disclosure for Mineral Projects.
The Paste Fill study was completed by Mr. Frank Palkovits (P.Eng, B.Eng), Pastefill
Specialist at RMS and a "Qualified Person" in accordance with
National Instrument 43-101 – Standards of Disclosure for Mineral
Projects.
Review of Technical
Information
The scientific and technical information in this press release
has been reviewed and approved by Clinton Swemmer, Chief Technical
Officer for Ascendant Resources Ltd, who is a Qualified Person as
defined in National Instrument 43-101.
About Ascendant Resources
Inc.
Ascendant Resources is a Toronto-based mining company focused on the
exploration and development of the highly prospective Lagoa Salgada
VMS project located on the prolific Iberian Pyrite Belt in
Portugal. The Lagoa Salgada
project is a high-grade polymetallic project, demonstrating a
typical mineralization endowment of zinc, copper, lead, tin,
silver, and gold. Extensive exploration upside potential lies both
near deposit and at prospective step-out targets across the large
7,209-hectare property concession.
Located just 80km from Lisbon
and surrounded by exceptional infrastructure, Lagoa Salgada offers
a low-cost entry to a significant exploration and development
opportunity, already showing its mineable scale and cashflow
generation potential.
Ascendant currently holds a 50% interest in the Lagoa Salgada
project through its position in Redcorp - Empreendimentos Mineiros,
Lda, ("Redcorp") and has an earn-in opportunity to increase its
interest in the project to 80%. The Company's common shares are
principally listed on the Toronto Stock Exchange under the symbol
"ASND". For more information on Ascendant, please visit our website
at http://www.ascendantresources.com/.
Additional information relating to the Company, including the
Preliminary Economic Assessment referenced in this news release, is
available on SEDAR at www.sedar.com.
Forward Looking
Information
This press release contains statements that constitute
"forward-looking information" (collectively, "forward-looking
statements") within the meaning of the applicable Canadian
securities legislation. All statements, other than statements of
historical fact, are forward-looking statements and are based on
expectations, estimates and projections as at the date of this news
release. Any statement that discusses predictions, expectations,
beliefs, plans, projections, objectives, assumptions, future events
or performance (often but not always using phrases such as
"expects", or "does not expect", "is expected", "anticipates" or
"does not anticipate", "plans", "budget", "scheduled", "forecasts",
"estimates", "believes" or "intends" or variations of such words
and phrases or stating that certain actions, events or results
"may" or "could", "would", "might" or "will" be taken to occur or
be achieved) are not statements of historical fact and may be
forward-looking statements.
Forward-looking statements contained in this press release
include, without limitation, statements regarding the business, the
Lagoa Salgada project and timing of completion of studies. In
making the forward- looking statements contained in this press
release, Ascendant has made certain assumptions, including,
but not limited to its ability to enhance value through further
optimisation, the discovery potential of the project and ability to
define further deposits and the support for and ability to obtain
project financing and commence construction. Although
Ascendant believes that the expectations reflected in
forward-looking statements are reasonable, it can give no assurance
that the expectations of any forward-looking statements will prove
to be correct. Known and unknown risks, uncertainties, and other
factors which may cause the actual results and future events to
differ materially from those expressed or implied by such
forward-looking statements. Such factors include, but are not
limited to general business, economic, competitive, political and
social uncertainties. Accordingly, readers should not place undue
reliance on the forward-looking statements and information
contained in this press release. Except as required by law,
Ascendant disclaims any intention and assumes no obligation to
update or revise any forward-looking statements to reflect actual
results, whether as a result of new information, future events,
changes in assumptions, changes in factors affecting such
forward-looking statements or otherwise. Forward-looking
information is subject to a variety of risks and uncertainties,
which could cause actual events or results to differ from those
reflected in the forward-looking information, including, without
limitation, the risks described under the
heading "Risks Factors" in the Company's Annual Information Form
dated March 31, 2023 and under the
heading "Risks and Uncertainties" in the Company's Management's
Discussion and Analysis for the years ended December 31, 2022 and 2021 and other risks
identified in the Company's filings with Canadian securities
regulators, which filings are available on SEDAR at
www.sedar.com. The risk factors referred to above are not
an exhaustive list of the factors that may affect any of the
Company's forward-looking information. The Company's statements
containing forward-looking information are based on the beliefs,
expectations and opinions of management on the date the statements
are made, and the Company does not assume any obligation to update
such forward-looking information if circumstances or management's
beliefs, expectations or opinions should change, other than as
required by applicable law. For the reasons set forth above, one
should not place undue reliance on forward-looking
information.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/ascendant-resources-announces-post-tax-npv8-of-us147-million-and-39-irr-from-initial-feasibility-study-at-its-lagoa-salgada-project-in-portugal-301885724.html
SOURCE Ascendant Resources Inc.