Aya Gold & Silver Inc. (TSX: AYA; OTCQX:
AYASF) (“Aya” or the “Corporation”) today provided an update on
construction progress at its Zgounder Silver Mine in the Kingdom of
Morocco. The expansion project was 98% complete as at August 30,
fully funded, and on budget.
The Corporation’s engineering, procurement, and
construction partner, Duro Felguera (“DF”), encountered issues
during commissioning of the hydraulic unit of the ball mill. As a
result of these issues, DF recently advised Aya that a rework of
the hydraulic unit piping is required. This does not impact the
integrity of the ball mill, the hydraulic unit or other equipment.
Commissioning of other subsystems is proceeding steadily, and the
crushing circuit is now operational.
As a result of the necessary rework, DF has
requested and obtained from Aya a two-month extension for hot
commissioning and ramp-up of the Zgounder expanded plant. All other
critical areas of the Zgounder expansion project are progressing to
plan or are in commissioning:
- Commissioning of
other areas of the plant continues to progress: ore has been
crushed throughout the entire crushing circuit and sent to the
silo.
- Work has begun
on the underground ramp from the 1,925m to 1,900m levels and will
continue to lower levels.
- The entire
mining site is now powered with renewable energy from the newly
built 60kV power line.
- The new
underground mobile workshop is in use.
- The primary
underground ventilation is working on all levels.
- The on-surface
cemented backfill mixing station and piping on all sublevels are
mechanically complete and will shortly be commissioned.
- All four
underground electrical substations have been deployed.
- The water dams
and other water storage infrastructures are operational.
- The new tailings
dam is in use.
- Water is being
recovered from the tailing dam.
- The base camp is
complete.
- The new assay
laboratory is near-complete with commissioning planned end of
September 2024.
Given the delay in hot-commissioning and ramp-up
of the Zgounder expanded plant, the Corporation’s 2024 production
guidance is under review. Aya expects to revisit its production
guidance based on construction progress and operational results by
latest November 14, 2024, when it will publish its third-quarter
2024 financial results.
"While there has been a slight delay in hot
commissioning, all critical aspects of the Zgounder Mine expansion
are advancing as planned, and the project remains on budget,” said
Benoit La Salle, President & CEO. “We are on track for a strong
finish to the year with additional operational milestones and
exploration drill results expected to further enhance stakeholder
value. We are confident that 2025 will be an exceptional year
following completion of the plant ramp-up.”
The technical information in this news release
has been reviewed and approved by Raphaël Beaudoin, P. Eng,
Vice-President, Operations for Aya, and a “Qualified Person” as
defined under NI 43-101.
About Aya Gold & Silver Inc.
Aya Gold & Silver Inc. is a rapidly growing,
Canada-based silver producer with operations in the Kingdom of
Morocco.
The only TSX-listed pure silver mining company,
Aya operates the high-grade Zgounder Silver Mine and is exploring
its properties along the prospective South-Atlas Fault, several of
which have hosted past-producing mines and historical resources.
Aya’s Moroccan mining assets are complemented by its Tijirit Gold
Project in Mauritania, which is being advanced to feasibility.
Aya’s management team has been focused on
maximising shareholder value by anchoring sustainability at the
heart of its operations, governance, and financial growth
plans.
For additional information, please visit Aya’s website at
www.ayagoldsilver.com.
Or contact
Benoit La Salle, FCPA, MBAPresident &
CEOBenoit.lasalle@ayagoldsilver.com |
Alex Ball VP, Corporate Development & IR
alex.ball@ayagoldsilver.com |
Forward-Looking Statements
This press release contains certain statements
that constitute forward-looking information within the meaning of
applicable securities laws (“forward-looking statements”), which
reflects management’s expectations regarding Aya’s future growth
and business prospects (including the timing and development of new
deposits and the success of exploration activities) and other
opportunities. Wherever possible, words such as “plan”, “update”,
“progress”, “on budget”, “continue”, “expects”, “advancing”,
“remains”, “on track”, “confident”, “exceptional”, and similar
expressions or statements that certain actions, events or results
“may”, “could”, “would”, “might”, “will”, or are “likely” to be
taken, occur or be achieved, have been used to identify such
forward-looking information. Specific forward-looking statements in
this press release include, but are not limited to, statements and
information with respect to advancement of the commissioning work
according to Aya’s plan, expected dates of hot commissioning, ramp
up and commercial production, capacities of production until the
company reaches commercial production, capacities of production in
2024 and statements with respect to Aya’s guidance for production.
Although the forward-looking information contained in this press
release reflect management’s current beliefs based upon information
currently available to management and based upon what management
believes to be reasonable assumptions, Aya cannot be certain that
actual results will be consistent with such forward-looking
information. Such forward-looking statements are based upon
assumptions, opinions and analysis made by management in light of
its experience, current conditions, and its expectations of future
developments that management believe to be reasonable and relevant
but that may prove to be incorrect. These assumptions include,
among other things, the ability to execute on the commissioning
plan, the ability to increase the resource at Zgounder, the ability
of these results to translate into an increase of resource, the
ability to obtain any requisite governmental approvals, obtaining
regulatory permits for on-site work, importing goods and machinery
and employment permits, the accuracy of Mineral Reserve and Mineral
Resource Estimates (including, but not limited to, ore tonnage and
ore grade estimates), the price of silver, the price of gold,
exchange rates, fuel and energy costs, future economic conditions,
anticipated future estimates of free cash flow, and courses of
action. Aya cautions you not to place undue reliance upon any such
forward-looking statements.
The risks and uncertainties that may affect
forward-looking statements include, among others: the inherent
risks involved in exploration and development of mineral
properties, including government approvals and permitting, changes
in economic conditions, changes in the worldwide price of silver
gold and other key inputs, changes in mine plans (including, but
not limited to, throughput and recoveries being affected by
metallurgical characteristics) and other factors, such as project
execution delays, many of which are beyond the control of Aya, as
well as other risks and uncertainties which are more fully
described in Aya’s 2023 Annual Information Form dated March 28,
2024, and in other filings of Aya with securities and regulatory
authorities which are available on SEDAR+ at www.sedarplus.ca. Aya
does not undertake any obligation to update forward-looking
statements should assumptions related to these plans, estimates,
projections, beliefs, and opinions change. Nothing in this document
should be construed as either an offer to sell or a solicitation to
buy or sell Aya securities. All references to Aya include its
subsidiaries unless the context requires otherwise.
Aya Gold & Silver (TSX:AYA)
Historical Stock Chart
From Nov 2024 to Dec 2024
Aya Gold & Silver (TSX:AYA)
Historical Stock Chart
From Dec 2023 to Dec 2024