Presidential Permit Application for Emera’s Atlantic Link Subsea Transmission Project
December 04 2017 - 2:42PM
Business Wire
Clean Power Northeast Development, a subsidiary of Emera Inc.,
has applied to the U.S. Department of Energy for a Presidential
Permit, requesting authorization to build the Atlantic Link subsea
electric transmission project. The application has been deemed
complete and the project’s submission notice was published today in
the U.S. Federal Register.
Atlantic Link is a proposed 1,000-megawatt (MW) high-voltage
direct current (HVDC) transmission interconnection of approximately
375 miles to deliver wind and hydro power from Atlantic Canada
directly to Massachusetts. The subsea cable would run from Coleson
Cove, New Brunswick to Plymouth, Massachusetts, making landfall
near the retiring Pilgrim nuclear station. Atlantic Link’s proposed
in-service date is late 2022. A Presidential Permit is required to
authorize the construction, connection, operation and maintenance
of a transmission line between the United States and Canada.
Atlantic Link has been proposed in response to the Massachusetts
Clean Energy RFP, a competitive solicitation for clean energy
delivery to the Commonwealth of Massachusetts. Responses to the RFP
were submitted in late July.
Atlantic Link’s application for a Presidential Permit initiates
a formal review of the project by U.S. federal government agencies.
The review process will examine environmental impacts of the
project, as well as its impact on electric reliability.
“The request for a Presidential Permit is a significant
milestone for Atlantic Link to ensure we continue to stay on track
with our project schedule,” said Dan Muldoon, Emera’s Executive
Vice-President for Major Renewables and Alternative Energy.
“Atlantic Link is a reliable, cost-effective solution to help
Massachusetts meet its energy diversity and greenhouse gas
emissions reduction goals. This transmission line’s direct
connection to Massachusetts will ensure benefits such as energy,
taxes, construction activity and low income programs all stay with
Massachusetts residents and electricity customers.”
Last month, the Atlantic Link project received a certificate
from Massachusetts Energy and Environmental Affairs regarding the
scope of required environmental assessment under the state’s
Environmental Policy Act (MEPA).
The Atlantic Link is proposing to deliver 5.69 terawatt hours
(TWh) of clean energy annually, directly to southeastern
Massachusetts, for a delivered price that remains fixed for 20
years. Approximately 70 per cent of the energy would be from seven
proposed wind farms to be built in New Brunswick and Nova Scotia,
with the remaining 30 per cent coming from two hydro suppliers in
Atlantic Canada, Nalcor Energy and NB Power.
Energy supply for Atlantic Link resulted from a competitive Open
Solicitation process initiated by Clean Power Northeast Development
in January 2017. The process was overseen by an independent
administrator. Commercial arrangements are in place between Clean
Power Northeast and the selected wind and hydro suppliers.
Atlantic Link is 100% owned by Clean Power Northeast
Development. NB Power holds an option to participate in the
Atlantic Link project as a minority investor.
About Atlantic LinkAtlantic Link is a 1,000-megawatt (MW)
high-voltage direct current (HVDC) subsea transmission project to
deliver clean energy from Atlantic Canada to Massachusetts. The
project includes a new converter station and substation to be
constructed at the landing site in Plymouth, Massachusetts as well
as similar facilities at the cable’s origination point at Coleson
Cove, New Brunswick. Virtually the entire length of the new,
approximately 375-mile-long transmission interconnection would be
installed underwater. Atlantic Link is being developed by Emera
Inc. subsidiary Clean Power Northeast Development. The project web
site is www.atlanticlink.com.
Forward Looking InformationThis news release contains
forward-looking information within the meaning of applicable
securities laws. By its nature, forward-looking information
requires Emera to make assumptions and is subject to inherent risks
and uncertainties. These statements reflect Emera management’s
current beliefs and are based on information currently available to
Emera management. There is a risk that predictions, forecasts,
conclusions and projections that constitute forward-looking
information will not prove to be accurate, that Emera’s assumptions
may not be correct and that actual results may differ materially
from such forward-looking information. Additional detailed
information about these assumptions, risks and uncertainties is
included in Emera’s securities regulatory filings, including under
the heading “Business Risks and Risk Management” in Emera’s annual
Management’s Discussion and Analysis, and under the heading
“Principal Risks and Uncertainties” in the notes to Emera’s annual
and interim financial statements, which can be found on SEDAR at
www.sedar.com.
About Emera Inc.Emera Inc. is a geographically diverse
energy and services company headquartered in Halifax, Nova Scotia
with approximately $28 billion in assets and 2016 revenues of more
than $4 billion. The company invests in electricity generation,
transmission and distribution, gas transmission and distribution,
and utility energy services with a strategic focus on
transformation from high carbon to low carbon energy sources. Emera
has investments throughout North America, and in four Caribbean
countries. Emera continues to target achieving a minimum of 75% of
its adjusted net income from rate-regulated businesses. Emera’s
common and preferred shares are listed on the Toronto Stock
Exchange and trade respectively under the symbol EMA, EMA.PR.A,
EMA.PR.B, EMA.PR.C, EMA.PR.E, and EMA.PR.F. Depositary receipts
representing common shares of Emera are listed on the Barbados
Stock Exchange under the symbol EMABDR. Additional Information can
be accessed at www.emera.com or
at www.sedar.com.
View source
version on businesswire.com: http://www.businesswire.com/news/home/20171204006005/en/
Clean Power Northeast DevelopmentGerald WeseenVice President, US
Government Affairs(617) 530-1309 - o(857) 288-9505 -
mgerald.weseen@emera.comorInvestor Inquiries:Emera Inc.Ken
McOnieVice President, Investor Relations & Treasurer(902)
428-6945Kenneth.McOnie@Emera.com
Emera (TSX:EMA.PR.A)
Historical Stock Chart
From Oct 2024 to Nov 2024
Emera (TSX:EMA.PR.A)
Historical Stock Chart
From Nov 2023 to Nov 2024