Management of Generation Mining Limited (TSX: GENM) (OTCQB:
GENMF) (“Gen Mining” or the “Company”) reflects on a
year that has been action-packed as we’ve advanced the Marathon
Palladium-Copper project in Northwestern Ontario (the “Marathon
Project”), held through the Company’s wholly-owned subsidiary
Generation PGM Inc. (“Gen PGM”), closer to construction. In
the 42 months since Gen Mining first acquired an interest in the
Marathon Project, the Company has significantly advanced the
Marathon Project towards becoming the next greenfield critical
minerals mine in Canada by preparing a feasibility study and 43-101
Technical Report, obtaining the federal and provincial government
environmental assessment approvals, entering into agreements with
affected Indigenous communities, including the Community Benefits
Agreement with the Biigtigong Nishnaabeg First Nation, and
advancing significant financing arrangements to fund construction
of the mine.
In January 2022 Gen Mining kicked off the year by completing the
acquisition of the remaining 16.5% interest in the Marathon Project
from Stillwater Canada Inc. (“Stillwater”), a subsidiary of
Sibanye Stillwater Limited (“Sibanye-Stillwater”). The
Company issued 21,759,332 common shares in Gen Mining to Stillwater
to hold 100% of the Marathon Project. As part of the transaction
the joint venture agreement between Stillwater and Gen PGM was
terminated. Sibanye-Stillwater (including its affiliates) owned
32,813,127 common shares of the Company, representing 18.2% of the
issued and outstanding common shares on a non-diluted basis as at
December 31, 2022.
In addition to acquiring 100% ownership interest in the Marathon
Project, the completion of the acquisition allowed Gen Mining to
proceed, in March 2022, with the first early deposit drawdown under
the streaming transaction with Wheaton Precious Metals Corp
(“Wheaton”) announced late in 2021, described more fully
below.
Late in January 2022 a Memorandum of Agreement was signed with
the Biigtigong Nishnaabeg (“BN”), an Indigenous community
located near the Project. Formalizing the Company’s commitment to
work with BN was a critical step in completing the Community
Benefits Agreement with BN, which was ratified by the BN community
and executed in mid-November 2022.
In March 2022, Gen PGM received the first of two C$20 million
payments from the Precious Metal Purchase Agreement (the
“PMPA”) with Wheaton. Under the terms of the PMPA, Wheaton
will pay Gen PGM total cash consideration of C$240 million in
return for a stream on all gold production and 22% of platinum
production from the Marathon Project. Wheaton will purchase (a)
100% of the payable gold production until 150 thousand ounces
(“koz”) have been delivered, thereafter dropping to 67% of
payable gold production for the life of the mine; and (b) 22% of
the payable platinum production until 120 koz have been delivered,
thereafter dropping to 15% for the life of mine. Wheaton will make
ongoing payments for the gold and platinum ounces delivered equal
to 18% of the spot prices (“Production Payment”) until the
value of gold and platinum delivered less the Production Payment is
equal to the upfront consideration of C$240 million, at which point
the Production Payment will increase to 22% of the spot prices.
Throughout the year, we added several experienced senior
executives to the team, with Christopher Stackhouse added as
Vice-President, Finance. Mauro Bassotti joined as Vice President,
Geology, Ann Wilkinson was appointed Vice President, Investor
Relations, and Ruben Wallin was appointed Vice President,
Sustainability. Adam Segal joined as General Counsel and Corporate
Secretary and Rod Thomas stepped down as Vice President,
Exploration while remaining on the board of directors. Kerry Knoll
migrated from his role as Executive Chairman to the role of
Chairman.
In May the Public hearings conducted by the Joint Review Panel
(“Panel”) for the Environmental Assessment of the Company’s
Marathon Project were concluded. The Panel process is the highest
standard of environmental assessment review in Canada. The
Project’s Environmental Impact Statement and other evidence were
subject to a rigorous review by the Panel and more than 50
participants. The Panel hearings, together with the Panel’s
subsequent report and recommendations, represented the culmination
of the Panel’s environmental review process that had been put on
hold by the Marathon Project’s previous proponent, Stillwater, in
January 2014, and restarted by the Company in July 2020.
In June we updated the markets on Phase II of our financing
activities (Phase I being the Wheaton PMPA) detailing our request
for proposal process (“RFP”) for the balance of the project
financing. The RFP process resulted in strong initial non-binding
expressions of interest from more than a dozen lenders including
commercial bank lenders, export credit financiers, private equity
companies, potential offtake partners and equipment lessors. The
interest was significant, with total non-binding financing offers
in excess of $1 billion. The Company analyzed the proposals with a
select group of lenders with a focus on maximizing capital from
non-equity sources while minimizing the cost of capital and
maximizing equity returns. Endeavour estimates that the project can
carry approximately US$400 million in senior debt based on the
Company’s Feasibility Study dated March 3, 2021.
In July 2022 Gen Mining announced an agreement with Valard
Equipment LP (“Valard”) for the lease of a construction camp
(the “Camp”) located in Marathon, Ontario until June 30,
2023 (the “Lease Term”) and an option, exercisable at Gen
PGM’s discretion, to purchase the Camp on or before the end of the
Lease Term. In connection with this agreement, Gen PGM has also
leased the existing serviced camp site from the Town of Marathon.
The Camp will be used to accommodate up to 286 workers for the
initial site preparation phase through the construction phase.
Additional accommodation capacity will be secured for the Marathon
Project as construction ramps up to the maximum peak of
approximately 1000 workers. The Camp has all the required
infrastructure services, including a commercial kitchen, a
recreation facility, a maintenance facility, and management
offices. BN will operate and service the Camp as part of Gen PGM’s
commitments to BN under the CBA.
In August 2022, the Panel delivered its report (the
“Report”) on the environmental assessment of the Marathon
Project. The Report sets out recommendations for the Company, and
the federal and provincial governments, to mitigate or minimize any
adverse effects of the Marathon Project. The delivery of the Report
was a precondition to the Federal and Provincial governments
delivering their decisions on the environmental assessment.
Also in August 2022, Gen PGM entered into an agreement with
Hycroft Mining Holding Corporation for the purchase of an unused,
surplus SAG mill and ball mill (the “Mills”) for
US$12,000,000, of which the first US$1,000,000 was paid by
September 30, 2022. The final payment of US$11,000,000 is due not
later than March 31, 2023. The agreement for the Mills reduced
risks associated with the procurement, logistics and
cost-uncertainty associated with some of the long-lead items for
the Project.
September saw receipt of the second CAD$20 million payment from
the PMPA with Wheaton. During construction of the Marathon Project
the remaining C$200 million will be payable in four staged
installments which are subject to various customary conditions
precedent being satisfied.
November represented the consolidation of a lot of hard work
with the ratification by the Biigtigong Nishnaabeg First Nation of
the CBA, and announcements by the Federal Minister of Environment
and Climate Change and the Ontario Minister of the Environment,
Conservation and Parks that the Company’s Marathon Project may
proceed.
The CBA between Gen PGM and BN describes the benefits the BN
community will receive from the Project and details how the
Project’s impact on the community will be mitigated. It includes
commitments from the Company regarding environmental management,
employment, training and education, business opportunities, social
and cultural support, and financial participation.
The Honourable Steven Guilbeault, Federal Minister of
Environment and Climate Change, and The Honourable David Piccini,
Ontario Minister of the Environment, Conservation and Parks, each
announced on November 30, 2022, that the Company’s Marathon Project
may proceed, subject to conditions set out in the federal decision
statement (the “Decision Statement”) and the provincial
approval order (the “Approval Order”), respectively. The
Decision Statement and Approval Order were made following a
thorough, multi-year, joint federal and provincial environmental
assessment process, with input received from Indigenous groups, the
public, federal government departments including the Ministry of
Environment Canada and Climate Change, Fisheries and Oceans Canada,
Natural Resources Canada and Transport Canada, and provincial
government departments including Ministry of Northern Development,
Mines, Natural Resources and Forestry, the Ministry of Environment,
Conservation and Parks, the Ministry of Transportation, the
Ministry of Labour, and the Technical Standards and Safety
Authority. The government decisions validate the work done to date
to develop the Marathon Project as a sustainable, environmentally
sensitive, low-cost producer of critical metals that are needed to
support emissions controls and the transition to a greener
economy.
Additionally, the Decision Statement and Approval Order included
conditions on such matters as ongoing consultation, follow-up
programs, reporting, information sharing, fish and fish habitat,
migratory birds, wildlife, greenhouse gas emissions, health and
socio-economic conditions of Indigenous peoples, the current use of
lands and resources for traditional purposes, and reclamation,
amongst other things. The Company is advancing the actions outlined
in the Decision Statement and Approval Order along with the
required federal and provincial permits needed to advance the
Project. The Company will continue to work expeditiously to satisfy
any pre-construction conditions and ensure compliance with all of
the conditions needed to advance construction and operations in a
timely manner, with the intention of beginning construction in
2023, subject to final permitting and financing arrangements.
Gen Mining continues to work on de-risking and optimizing the
Marathon Project, making significant progress on detailed
engineering and financing. The progress of development at the
Marathon Project, including progress of project expenditures and
contracting processes, is contingent on the continued availability
of capital and financing, permitting timelines, and the Company's
decisions with respect to capital allocation.
About the Company
Gen Mining’s focus is the development of the Marathon Project, a
large undeveloped palladium-copper deposit in Northwestern Ontario.
The Company released the results of the Project Feasibility Study
on March 3, 2021 and published the NI43-101 Technical Report dated
March 25, 2021. The Marathon Property covers a land package of
approximately 22,000 hectares, or 220 square kilometers. Gen Mining
owns a 100% interest in the Marathon Project and once constructed,
it is expected to have a low carbon footprint. For more
information, please review the detailed Feasibility Study dated
March 25, 2021, filed under the Company’s profile at SEDAR.com.
Forward-Looking Information
This news release contains certain forward-looking information
and forward-looking statements, as defined in applicable securities
laws (collectively referred to herein as "forward-looking
statements"). Forward-looking statements reflect current
expectations or beliefs regarding future events or the Company’s
future performance. All statements other than statements of
historical fact are forward-looking statements. Often, but not
always, forward-looking statements can be identified by the use of
words such as "plans", "expects", "is expected", "budget",
"scheduled", "estimates", "continues", "forecasts", "Projects",
"predicts", "intends", "anticipates", "targets" or "believes", or
variations of, or the negatives of, such words and phrases or state
that certain actions, events or results "may", "could", "would",
"should", "might" or "will" be taken, occur or be achieved,
including statements related to the anticipated timing for
commencement of construction of the Marathon Project; and the
timing and amount of funding required to execute the Company’s
development and business plans related to the Marathon Project. All
forward-looking statements, including those herein, are qualified
by this cautionary statement.
Although the Company believes that the expectations expressed in
such statements are based on reasonable assumptions, such
statements are not guarantees of future performance and actual
results or developments may differ materially from those in the
statements. There are certain factors that could cause actual
results to differ materially from those in the forward-looking
information. These include the timing for a construction decision;
the progress of development at the Marathon Project, including
progress of project expenditures and contracting processes, the
Company's plans and expectations with respect to liquidity
management, continued availability of capital and financing, the
future price of palladium and other commodities, permitting
timelines, exchange rates and currency fluctuations, increases in
costs, requirements for additional capital, and the Company's
decisions with respect to capital allocation, and the impact of
COVID-19, inflation, global supply chain disruptions and the war in
Ukraine on the Company, the project schedule for the Marathon
Project, key inputs, staffing and contractors, commodity price
volatility, continued availability of capital and financing,
uncertainties involved in interpreting geological data, increases
in costs, environmental compliance and changes in environmental
legislation and regulation, the Company’s relationships with First
Nations communities, exploration successes, and general economic,
market or business conditions, as well as those risk factors set
out in the Company’s annual information form for the year ended
December 31, 2021, and in the continuous disclosure documents filed
by the Company on SEDAR at www.sedar.com. Readers are cautioned
that the foregoing list of factors is not exhaustive of the factors
that may affect forward-looking statements. Accordingly, readers
should not place undue reliance on forward-looking statements. The
forward-looking statements in this news release speak only as of
the date of this news release or as of the date or dates specified
in such statements.
Forward-looking statements are based on a number of assumptions
which may prove to be incorrect, including, but not limited to,
assumptions relating to: the availability of financing for the
Company’s operations; operating and capital costs; results of
operations; the mine development and production schedule and
related costs; the supply and demand for, and the level and
volatility of commodity prices; timing of the receipt of regulatory
and governmental approvals for development Projects and other
operations; the accuracy of Mineral Reserve and Mineral Resource
Estimates, production estimates and capital and operating cost
estimates; and general business and economic conditions.
Investors are cautioned that any such statements are not
guarantees of future performance and actual results or developments
may differ materially from those projected in the forward-looking
information. For more information on the Company, investors are
encouraged to review the Company’s public filings on SEDAR at
www.sedar.com. The Company disclaims any intention or obligation to
update or revise any forward- looking information, whether as a
result of new information, future events or otherwise, other than
as required by law.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20230110005462/en/
Jamie Levy President and Chief Executive Officer (416) 640-2934
(O) (416) 567-2440 (M) jlevy@genmining.com Ann Wilkinson Vice
President, Investor Relations (416) 640-2954 (O) (416) 357-5511 (M)
awilkinson@genmining.com
Generation Mining (TSX:GENM)
Historical Stock Chart
From Nov 2024 to Dec 2024
Generation Mining (TSX:GENM)
Historical Stock Chart
From Dec 2023 to Dec 2024