Lithium Americas Corp. (TSX: LAC) (NYSE: LAC)
(“
Lithium Americas”
or the
“
Company”) has reported financial and operating
results for the first quarter ended March 31, 2023 (“
Q1
2023”).
HIGHLIGHTS
Argentina
Caucharí-Olaroz
- Mechanical
construction completed to target first lithium production in June
2023.
- With all key
systems for the production of first lithium completed, the
commissioning team commenced production testing of the
purification, carbonation and SX systems.
- Additional
purification processing equipment necessary to achieve
battery-quality lithium carbonate is expected to be completed in H2
2023, following the start of pre-commercial production.
- Ramp up to
40,000 tonnes per annum (“tpa”) of battery-quality
lithium carbonate is targeted to be complete in Q1 2024.
- As of March 31,
2023, $834 million of the $979 million total expected capex has
been spent (on a 100% basis).
- As of March 31,
2023, the Company expects its remaining funding requirement to be
less than $50 million for capital costs, value added taxes and
working capital to reach positive cash flow.
- Development
planning for Stage 2 expansion of at least 20,000 tpa of lithium
carbonate continues to progress to align with completion of Stage
1.
Pastos Grandes Basin
- The Company
continues to advance the Pastos Grandes’ $30 million development
plan, targeting completion of the plan and a construction decision
in Q4 2023.
- The geophysics
program has been completed. Roads and drilling pads are under
construction.
- On April 20,
2023, the Company completed its acquisition of Arena Minerals and
its 65% ownership interest in the Sal de la Puna project, adjacent
to the Pastos Grandes project in Salta, Argentina.
United States
Thacker Pass
- On March 2,
2023, the Company announced the start of construction activities at
Thacker Pass following receipt of notice to proceed from the Bureau
of Land Management (“BLM”).
- Early works are
progressing, including water pipelines, construction ponds, site
fencing and access roads.
- In April 2023, a
geotechnical report was issued to all engineering contractors to
commence the design of civil foundations.
- Major earthworks
are expected to commence in H2 2023 and support the target to
commence production in the second half of 2026.
- The Company,
Bechtel Corporation (“Bechtel”) (engineering,
procurement and construction management) and the North American
Building Trade Unions have entered into a memorandum of
understanding agreeing to a project labor agreement for major
construction activities for Phase 1 of Thacker Pass.
- On February 22,
2023, the Company announced that it received a Letter of
Substantial Completion from the U.S. Department of Energy
(“DOE”) Loans Program Office for its application
for the DOE’s Advanced Technology Vehicles Manufacturing Loan
Program (“ATVM Loan Program”).
- The Company
expects the DOE ATVM Loan Program conditional approval process to
be completed in 2023 and if approved, to fund up to 75% of the
total capital costs for construction of Phase 1.
- The Company has
approved a construction budget of $125 million through Q3 2023 with
additional capital spend expected following completion of the DOE
ATVM Loan Program process.
- On February 6,
2023, the US District Court, District of Nevada (“Federal
Court”) ruled favorably for the Company in the appeal
filed against the BLM by declining to vacate the Record of Decision
(“ROD”).
Corporate
- As at March 31,
2023, the Company had $604 million in cash and cash equivalents and
short-term bank deposits, with an additional $75 million in
available credit.
- On May 15, 2023,
the Company’s Board of Directors unanimously approved execution of
an arrangement agreement providing for the reorganization of the
Company that will result in the separation of its North American
and Argentine business units into two independent public companies
(the “Separation”).
- In April 2023,
Pablo Mercado joined as Executive Vice President and Chief
Financial Officer following Eduard Epshtein’s retirement.
- On January 30,
2023, Lithium Americas entered into a purchase agreement with
General Motors Holdings LLC (“GM”) whereby GM
agreed to make a $650 million equity investment in the Company and
receive exclusive access to Phase 1 production at Thacker Pass
through a binding supply agreement.
- On February 16,
2023, the initial tranche of $320 million closed with GM’s purchase
of 15 million Lithium Americas’ common shares at $21.34 per share.
GM is now Lithium Americas’ largest shareholder and offtake
partner.
- The second
tranche of $330 million is contemplated to be invested into the
Company’s U.S. business following the Separation and other
conditions being achieved.
TECHNICAL INFORMATION
The Technical Information in this news release
has been reviewed and approved by Rene LeBlanc, PhD, SME, Chief
Technical Officer of Lithium Americas, and a Qualified Person as
defined by National Instrument 43-101.
FINANCIAL RESULTS
Selected consolidated financial information is
presented as follows:
(in US$ million except per share information) |
Quarter ended March 31, |
|
2023 |
|
|
2022 |
|
|
$ |
|
$ |
Expenses |
|
(17.1 |
) |
|
|
(16.0 |
) |
Net loss |
|
(6.4 |
) |
|
|
(46.1 |
) |
Loss per share – basic |
|
(0.04 |
) |
|
|
(0.35 |
) |
(in US$ million) |
As at March 31, 2023 |
|
As at December 31, 2022 |
|
$ |
|
$ |
Cash, cash equivalents and short-term bank deposits |
|
604.1 |
|
|
|
352.1 |
|
Total
assets |
|
1,328.4 |
|
|
|
1,016.5 |
|
Total long-term liabilities |
|
(213.7 |
) |
|
|
(212.9 |
) |
In Q1 2023, net loss decreased primarily due to
gain on change in fair value of the GM agreements derivative
liability as well as gain on change in fair value of the
convertible note derivative versus loss in the comparative
period.
In Q1 2023, total assets increased primarily due
to cash proceeds from the first tranche investment by GM of $320
million and commencement of construction of the Thacker Pass
project and, as a result, capitalization of the related project
construction costs.
This news release
should be read in conjunction with Lithium Americas’ condensed
consolidated interim financial statements and management's
discussion and analysis for the quarter ended March 31, 2023, which
are available on SEDAR. All amounts are in U.S. dollars unless
otherwise indicated.
ABOUT LITHIUM AMERICAS
Lithium Americas is focused on advancing lithium
projects in Argentina and the United States to production. In
Argentina, Caucharí-Olaroz is advancing towards first production
and Pastos Grandes represents regional growth. In the United
States, Thacker Pass has received its Record of Decision and
commenced construction. The Company trades on both the Toronto
Stock Exchange and on the New York Stock Exchange, under the ticker
symbol “LAC”.
For further information contact:Investor
RelationsTelephone: 778-656-5820mail:
ir@lithiumamericas.comWebsite: www.lithiumamericas.com
FORWARD-LOOKING
STATEMENTS
This news release contains “forward-looking
information” within the meaning of applicable Canadian securities
legislation and “forward-looking statements” within the meaning of
the United States Private Securities Litigation Reform Act of 1995
(collectively referred to herein as “forward-looking information”).
These statements relate to future events or the Company’s future
performance. All statements, other than statements of historical
fact, may be forward-looking information. Information concerning
Mineral Resource and Mineral Reserve estimates also may be deemed
to be forward-looking information in that it reflects a prediction
of mineralization that would be encountered if a mineral deposit
were developed and mined. Forward-looking information generally can
be identified by the use of words such as “seek,” “anticipate,”
“plan,” “continue,” “estimate,” “expect,” “may,” “will,” “project,”
“predict,” “propose,” “potential,” “targeting,” “intend,” “could,”
“might,” “should,” “believe” and similar expressions. These
statements involve known and unknown risks, uncertainties and other
factors that may cause actual results or events to differ
materially from those anticipated in such forward-looking
information.
In particular, this news release contains
forward-looking information, including, without limitation, with
respect to the following matters or the Company’s expectations
relating to such matters: development of the Caucharí-Olaroz
Project and the Thacker Pass Project, including timing, progress,
approach, continuity or change in plans, construction,
commissioning, milestones, anticipated production and results
thereof and expansion plans; plans at the Caucharí-Olaroz Project
to prioritize commissioning and the expected timing to complete
deferred construction items such as the purification process as a
result of such prioritization; expected timing of first production
and full capacity production; expectations regarding accessing
funding from the ATVM Loan Program, including the expected amount,
timing and outcome of the loan application; expectations and
anticipated impact of the COVID-19 pandemic; anticipated timing to
resolve, and the expected outcome of, any complaints or claims made
or that could be made concerning the environmental permitting
process in the United States for the Thacker Pass Project,
including current lawsuits involving the Record of Decision for the
project, and the transfer application for certain water rights for
the project; capital expenditures and programs; estimates, and any
change in estimates, of the Mineral Resources and Mineral Reserves
at the Company’s properties; development of Mineral Resources and
Mineral Reserves; government regulation of mining operations and
treatment under governmental and taxation regimes; the future price
of commodities, including lithium; the realization of Mineral
Resources and Mineral Reserves estimates, including whether Mineral
Resources that are not included in Mineral Reserves will ever be
developed into Mineral Reserves, and information and underlying
assumptions related thereto; the timing and amount of future
production; currency exchange and interest rates; the Company’s
ability to raise capital and the sufficiency of currently available
funding; expected expenditures to be made by the Company on its
properties; the timing, cost, quantity, capacity and product
quality of production of the Caucharí-Olaroz Project, which is held
and operated through an entity in Argentina that is 44.8% owned by
the Company, 46.7% owned by Ganfeng and 8.5% owned by JEMSE;
successful operation of the Caucharí-Olaroz Project under its
co-ownership structure; ability to produce battery grade lithium
products; settlement of agreements related to the operation and
sale of mineral production as well as contracts in respect of
operations and inputs required in the course of production; the
timing, cost, quantity, capacity and product quality of production
at the Thacker Pass Project; successful development of the Thacker
Pass Project; capital costs, operating costs, sustaining capital
requirements, after tax net present value and internal rate of
return, payback period, sensitivity analyses, and net cash flows of
the Caucharí-Olaroz Project and the Thacker Pass Project; the
Company’s share of the expected capital expenditures for the
construction of the Caucharí-Olaroz Project and the expected
capital expenditures for the construction of the Thacker Pass
Project; expecting timing to complete development planning and
reach a construction decision for the Pastos Grandes and Sal de la
Puna projects; ability to achieve capital cost efficiencies;
stability and inflation related to the Argentine peso, matters
relating to the agreement reached by the Argentine government with
the International Monetary Fund in respect of Argentina’s external
debt, whether the Argentine government implements additional
foreign exchange and capital controls, and the effect of current or
any additional regulations on the Company’s operations; the GM
Transaction and the potential for additional financing scenarios
for the Thacker Pass Project; the expected timetable for completing
Tranche 2 of the GM Transaction; the ability of the Company to
complete Tranche 2 of the GM Transaction on the terms and timeline
anticipated, or at all; the receipt of shareholder and required
stock exchange and regulatory approvals, authorizations and court
rulings, and the securing of sufficient funding to complete the
development of Phase 1 of the Thacker Pass Project, required for
Tranche 2 of the GM Transaction; the expected benefits of the GM
Transaction; the expected timetable for completing the Separation
(including timing of advance tax rulings from the CRA and the IRS
in connection with same); the ability of the Company to complete
the Separation on the terms and timeline anticipated, or at all;
the receipt of Board of Directors, shareholder and required third
party, court, tax, stock exchange and regulatory approvals required
for the Separation (including obtaining a CRA and an IRS advance
income tax ruling in respect thereof); the expected holdings and
assets of the entities resulting from the Separation; the expected
benefits of the Separation for each business and to the Company’s
shareholders and other stakeholders; the strategic advantages,
future opportunities and focus of each business resulting from the
Separation; and the successful integration and expected benefits of
the acquisition of Arena Minerals Inc., including opportunities for
regional growth and development of the Pastos Grandes basin
expected from the acquisition.
Forward-looking information does not take into
account the effect of transactions or other items announced or
occurring after the statements are made. Forward-looking
information is based upon a number of expectations and assumptions
and is subject to a number of risks and uncertainties, many of
which are beyond the Company’s control, that could cause actual
results to differ materially from those that are disclosed in or
implied by such forward-looking information. With respect to
forward-looking information listed above, the Company has made
assumptions regarding, among other things: current technological
trends; a cordial business relationship between the Company and
third party strategic and contractual partners, including the
co-owners of the Caucharí-Olaroz Project; ability of the Company to
fund, advance and develop the Caucharí-Olaroz Project and the
Thacker Pass Project, and the respective impacts of the projects
when production commences; the Company’s ability to operate in a
safe and effective manner; uncertainties relating to receiving and
maintaining mining, exploration, environmental and other permits or
approvals in Nevada and Argentina; demand for lithium, including
that such demand is supported by growth in the electric vehicle
market; the impact of increasing competition in the lithium
business, and the Company’s competitive position in the industry;
general economic conditions; the stable and supportive legislative,
regulatory and community environment in the jurisdictions where the
Company operates; stability and inflation of the Argentine peso,
including any foreign exchange or capital controls which may be
enacted in respect thereof, and the effect of current or any
additional regulations on the Company’s operations; the impact of
unknown financial contingencies, including litigation costs, on the
Company’s operations; gains or losses, in each case, if any, from
short-term investments in Argentine bonds and equities; estimates
of and unpredictable changes to the market prices for lithium
products; development and construction costs for the
Caucharí-Olaroz Project and the Thacker Pass Project, and costs for
any additional exploration work at the projects; estimates of
Mineral Resources and Mineral Reserves, including whether Mineral
Resources not included in Mineral Reserves will be further
developed into Mineral Reserves; reliability of technical data;
anticipated timing and results of exploration, development and
construction activities, including the impact of COVID-19 on such
timing; timely responses from governmental agencies responsible for
reviewing and considering the Company’s permitting activities at
the Thacker Pass Project; the Company’s ability to obtain
additional financing on satisfactory terms or at all; the ability
to develop and achieve production at any of the Company’s mineral
exploration and development properties; the impact of inflationary
and other conditions flowing from COVID-19 on the Company’s
business and global mark; and accuracy of development budget and
construction estimates.
Although the Company believes that the
assumptions and expectations reflected in such forward-looking
information are reasonable, the Company can give no assurance that
these assumptions and expectations will prove to be correct. Since
forward-looking information inherently involves risks and
uncertainties, undue reliance should not be placed on such
information. The Company’s actual results could differ materially
from those anticipated in any forward-looking information as a
result of the risk factors set out herein and in the Company’s
latest annual information form (“AIF”) available
on SEDAR.
All forward-looking information contained in
this news release is expressly qualified by the risk factors set
out in the Company’s latest AIF and management discussion analysis.
Such risk factors are not exhaustive. The Company does not
undertake any obligation to update or revise any forward-looking
information, whether as a result of new information, future events
or otherwise, except as required by law. All forward-looking
information contained in this news release is expressly qualified
in its entirety by this cautionary statement. Additional
information about the above-noted assumptions, risks and
uncertainties is contained in the Company’s filings with securities
regulators, including our latest AIF, which are available on SEDAR
at www.sedar.com.
Lithium Americas (TSX:LAC)
Historical Stock Chart
From Nov 2024 to Dec 2024
Lithium Americas (TSX:LAC)
Historical Stock Chart
From Dec 2023 to Dec 2024