Atico Mining Corporation: Scale-Up of El Roble Mine Operations
Advancing on Schedule
VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jan 16, 2014) -
Atico Mining Corporation (TSX-VENTURE:ATY)(PINKSHEETS:ATCMF)
reports that the scale-up and modernization of its recently
acquired El Roble copper-gold mine in Colombia are progressing on
schedule. The company expects to be operating at full capacity by
the fourth quarter of 2014.
"We are very pleased with the execution of the scale-up and
modernization plan at the El Roble mine during this initial phase
of the integration process, perhaps one of the most challenging,"
said Fernando E. Ganoza, CEO. "We are on track to deliver on our
promises thanks to the efforts of our team and contractors on the
ground."
Current operations and integration
The El Roble mine continues to operate at approximately 320
tonnes per day processing ore mined from the higher levels of the
mine. The Company expects to maintain the current throughput while
completing access to and preparation for mining of high-grade ore
from the 1880 level. During the scale-up and modernization phase,
the Company is using existing infrastructure to train personnel,
increase safety and environmental standards and generate cash
flow.
The integration phase at El Roble mine is proceeding as
expected. The Company has retained all of the previous operator's
employees and added a team of staff and technicians, who are on
site supporting and training the local workforce.
Scale-up plans
Scale-up of the El Roble mill to 650 tonnes per day is on
schedule to be completed in the third quarter, prior to the
commencement of mining the new high-grade resources. All major
equipment has been secured with delivery expected during the first
quarter of 2014.
The new 5-meter by 5-meter adit at the 1880 level is advancing
ahead of schedule. The Company now expects to complete the
830-meter adit in the first quarter of this year. Preparation of
the Goliath and Maximus massive sulfide bodies will begin
immediately after and is expected to continue through the second
quarter.
A 60-meter access will be developed from the new adit to
intercept the Goliath massive sulfide body at approximately the
1894 elevation (masl), where the resource estimate suggests mining
activities will begin in a high-grade copper zone. An additional
access of approximately 40 meters in length will be driven to the
southwest to reach the Maximus massive sulfide body at the same
elevation.
Mining of the new resources is expected to commence during the
third quarter, while the ramp-up period to steady-state production
is projected to extend into the fourth quarter.
Construction of the new tailings dam was delayed briefly in late
2013 because of heavy rains. The company has increased construction
activities, taking advantage of the dry season that started in
January, to complete the tailings dam as originally scheduled in
the second quarter of 2014.
El Roble Mine
El Roble is an operating underground copper and gold mine with a
nominal capacity of 400 tonnes per day. Over the past 22 years, the
mine has processed 1.5 million tonnes of ore at an average head
grade of 2.5% copper and an estimated 2.5 g/t gold. Copper and gold
mineralization occurs as volcanogenic massive sulfide ("VMS")
lenses.
Since entering into an option agreement in January 2011 to
acquire 90% of El Roble, Atico has aggressively explored the mine
and surrounding claims. The company has completed 11,740 meters of
diamond drilling and identified numerous prospective targets for
VMS deposits on the 6,679-hectare property. This exploration led to
the discovery of high-grade copper and gold mineralization below
the 2000 level, the lowest production level of the El Roble
mine.
National Instrument 43-101 compliant inferred mineral resource
are 1.58 million tonnes grading 4.45 % copper and 3.17 g/t gold, at
a cut-off grade of 0.72 % copper equivalent. Mineralization is open
at depth and along strike and the company plans to further test the
limits of the resource.
On the larger land package, the company has identified a
prospective stratigraphic contact between volcanic rocks and black
and grey cherts that has been traced by Atico geologists for ten
kilometers. This contact has been determined to be an important
control on VMS mineralization on which Atico has identified 15
prospective target areas for VMS type mineralization occurrence,
which is the focus of the surface drill program at El Roble.
Qualified Person
Dr. Demetrius Pohl, Ph.D., AIPG Certified Geologist, a qualified
person under National Instrument 43-101 standards and independent
of the company, is responsible for ensuring that the information
contained in this news release is an accurate summary of the
original reports and data provided to or developed by Atico.
About Atico Mining Corporation
Atico is a growth-oriented company, focused on exploring,
developing and mining copper and gold projects in Latin America.
The company operates the El Roble mine and is pursuing additional
acquisition opportunities. For more information, please visit
www.aticomining.com.
ON BEHALF OF THE BOARD
Fernando E. Ganoza, CEO
Atico Mining Corporation
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
No securities regulatory authority has either approved or
disapproved of the contents of this news release. The securities
being offered have not been, and will not be, registered under the
United States Securities Act of 1933, as amended (the "U.S.
Securities Act"), or any state securities laws, and may not be
offered or sold in the United States, or to, or for the account or
benefit of, a "U.S. person" (as defined in Regulation S of the U.S.
Securities Act) unless pursuant to an exemption therefrom. This
press release is for information purposes only and does not
constitute an offer to sell or a solicitation of an offer to buy
any securities of the Company in any jurisdiction.
Cautionary
Note Regarding Forward Looking Statements
This announcement includes certain "forward-looking
statements" within the meaning of Canadian securities legislation.
All statements, other than statements of historical fact, included
herein, without limitation the use of net proceeds, are
forward-looking statements. Forward- looking statements involve
various risks and uncertainties and are based on certain factors
and assumptions. There can be no assurance that such statements
will prove to be accurate, and actual results and future events
could differ materially from those anticipated in such statements.
Important factors that could cause actual results to differ
materially from the Company's expectations include uncertainties
relating to interpretation of drill results and the geology,
continuity and grade of mineral deposits; uncertainty of estimates
of capital and operating costs; the need to obtain additional
financing to maintain its interest in and/or explore and develop
the Company's mineral projects; uncertainty of meeting anticipated
program milestones for the Company's mineral projects; and other
risks and uncertainties disclosed under the heading "Risk Factors"
in the prospectus of the Company dated March 2, 2012 filed with the
Canadian securities regulatory authorities on the SEDAR website
at www.sedar.com.
Atico Mining CorporationIgor DutinaInvestor
Relations+1.604.633.9022info@aticomining.comwww.aticomining.com
Atico Mining (TSXV:ATY)
Historical Stock Chart
From Oct 2024 to Nov 2024
Atico Mining (TSXV:ATY)
Historical Stock Chart
From Nov 2023 to Nov 2024