The Pinos Project Preliminary Economic
Assessment (“PEA”) results indicate a 7 year Life of Mine (“LOM”)
with projected gold equivalent ounce (“GEO”) production of 89,000
with an after-tax IRR of 25%.
Candelaria Mining Corp. (TSXV:CAND, OTC PINK:CDELF) (the
“
Company”) is pleased to provide the following
update on the Company’s Pinos gold project located 140 kilometers
east of the capital Zacatecas in the state of Zacatecas,
Mexico. The project is district scale consisting of
twenty-nine contiguous mining claims and covering 3,816 hectares,
with easy access to infrastructure, labour and supplies.
All currency related figures are in US dollars.
Pinos Project PEA Highlights using $1250/ounce gold and
$17/ounce silver
- Pre-tax Net Present Value (“NPV”) of $19 million using a 5%
discount rate.
- After tax NPV of $12 million using a 5% discount rate.
- After tax Internal Rate of Return (“IRR”) of 25%.
- Low initial capital of $13.5 million and LOM capital of $23
million
- Project has additional upside potential; the PEA only uses the
Cinco Estrellas vein, while multiple other vein targets exist on
the property.
- All permits necessary to commence construction have been
received.
Pinos PEA Results1 |
|
LOM (years) |
7 |
Indicated GEO recovered (000’s)2 |
88.9 |
Direct Cash Cost per GEO |
$666 |
Capital costs: (millions) Initial Sustaining |
$13.5 $ 9.2 |
After tax NPV @ 5% discount rate (millions) 3 |
$12.2 |
After tax Internal Rate of Return (“IRR”)3 |
25% |
1Technical report on the PEA incorporating work by DENM
Engineering, Jose A. Olmedo and Candelaria Mining to be filed
within 45 days of this release. 2Gold equivalent ounces production
was calculated at 73.5:1 conversion using $1,250/oz gold and $17/oz
silver 3NPV and IRR calculations are based on
after tax expectations with a long term gold price of $1,250 and
silver price of $17. The PEA is preliminary in nature, and there is
no certainty that the PEA will be realized. |
Production Specifications
- Total proposed tonnes processed of 790,800 includes Measured
and Indicated resource of 261,500 tonnes at an average grade of 3.0
grams per tonne (“g/t”) gold and 59.1 g/t silver and 529,300 tonnes
of Inferred Resource at an average grade of 3.6 g/t gold and 47.7
g/t silver containing 85,000 ounces of gold and 1.3 million ounces
of silver.
- Total contemplated production of 75,400 ounces of gold and
995,400 ounces of silver from the Indicated and Inferred
Resource.
- Average yearly production of 12,700 gold equivalent ounces
during the initial seven years of the mine life.
- Throughput estimate of an average of 200 tonnes per day (“tpd”)
for the 1st year, 300 tpd for years 2 and 3, and 400 tpd
thereafter.
Production Statistics: |
|
Life of mine (years) |
7 |
Total tonnes processed (000’s) |
791 |
Overall average gold grade (g/t) |
3.34 |
Overall average silver grade (g/t) |
51 |
Overall average gold recovery |
90% |
Overall average silver recovery |
80% |
Gold ounces recovered (000’s) |
75 |
Silver ounces recovered (000’s) |
995 |
Average annual production GEOs (yrs 1-7) |
12,700 |
The proposed potential production mine plan cut-off grade of 2.2
g/t gold.
Modeled Operating Costs |
Cost / Tonne Mineralized Material Mining Processing
MaintenanceG&A |
200
tpd$82.3639.5730.772.0210.00 |
300
tpd$79.8739.4829.521.879.00 |
400 tpd$77.37 39.39
28.26 1.728.00 |
Overall Average Direct Cash Cost Per GEO |
$666 |
Modeled Capital Costs
(millions) |
Mine Development |
$5.9 |
Process |
$5.7 |
Infrastructure |
$1.2 |
Total Capital |
$12.8 |
Working capital, owner & indirect costs |
$0.7 |
Total Initial Capital |
$13.5 |
Sustaining Capital |
$9.2 |
Total Life of Mine Capital |
$22.7 |
The project sensitivities indicate the project is most sensitive
to gold price, followed by operating costs and is less sensitive to
changes in capital costs.
Pinos Sensitivity
Charthttp://www.globenewswire.com/NewsRoom/AttachmentNg/fd6f9d95-ba28-4a66-8532-878828a67263
Curtis Turner, President and CEO of Candelaria Mining
stated:
"I am pleased to announce the results of the
Pinos PEA. The PEA shows that Pinos is a great small scale project
with the ability to grow. We are encouraged, not only by the PEA,
but with the exploration potential on the property. The project is
fully permitted. We have already sourced much of the processing
facility. Therefore, we have limited the much of the risk
associated with the start-up of most projects at a PEA stage.
Developing the property as outlined in the PEA will allow us to
commence with a low-capex project which will generate cash flows
and to allow us to expand the operations, conduct further
exploration work and continue to advance the other projects in our
portfolio.”
National Instrument 43-101 (“NI 43-101”) Preliminary
Economic Assessment Report
This PEA is based on the Canadian NI 43-101
Mineral Resource Estimate and Economic Analysis generated by Jose
A. Olmedo with Metallurgical work, Process Design Criteria, and
Process Plant Details prepared by DENM Engineering Ltd., and
presented in a National Instrument 43-101 Technical Report which
will be filed within 45 days of the date of the publishing of this
press release.
Mineral Resource Summary of the Pinos Project as of
September 13, 2018.
Resource Class |
Tonnes of Material |
Gold Equivalent Grade (g/t)1,2,3,4 |
Gold Grade (g/t)4 |
Silver Grade (g/t)4 |
Gold Ounces Contained |
Silver Ounces Contained |
Measured (Dumps) |
85,847 |
2.7 |
1.6 |
82.9 |
4,444 |
228,892 |
Indicated |
175,697 |
4.3 |
3.6 |
47.4 |
20,586 |
267,745 |
Measured and Indicated |
261,544 |
3.8 |
3.0 |
59.1 |
25,029 |
496,637 |
Inferred |
529,267 |
4.2 |
3.6 |
47.7 |
60,671 |
811,082 |
1 g/t refers to grams per tonne 2 Resource based on
a 2.2 g/t gold equivalent cut-off grade 3 The gold equivalent
grade for the conceptual pit uses a 73.5:1 gold equivalent ounce
ratio ($1,250/oz Gold and $17/oz Silver).4 The mine grades are
diluted, using a 10% mine dilution factor Notes to Accompany
Mineral Resource Table:
- Mineral resources are not mineral reserves and do not
have demonstrated economic viability.
- Inferred mineral resources have a high degree of uncertainty as
to their existence, and great uncertainty as to their economic and
legal feasibility.
- Mineral resources are reported with 10% dilution.
- The resources calculated using a cut-off of 2.2 g/t gold based
on $1,250/oz gold price, $17/oz silver price, mining cost of $39.57
per tonne ("/t") of material mined, process and general and
administrative expense cost of $42.80/t (at 200 tpd processing
rate) with gold recoveries of 90% and silver recoveries of
80%.
- Specific gravity: 2.69 g/cm3
- Tonnes, grade values, and contained metal quantities may differ
due to rounding.
|
The stated Mineral Resources have been prepared
in accordance with the CIM classifications of Canada's NI 43-101
Standards of Disclosure for Mineral Projects.
Path forward:
At Pinos project, Candelaria is in the process
of obtaining financing and will be reviewing all project aspects in
order to make a construction decision based on obtaining favorable
financing terms, as well as advancing engineering and design plans
to be ready to commence development of the project.
Technical Information
Mineral resources referenced herein are not
mineral reserves and do not have demonstrated economic viability.
Mineral resource estimates do not account for mineability,
selectivity, and mining loss but do include a dilution factor of
10%. The mineral resource estimates include inferred mineral
resources that are normally considered too speculative geologically
to have economic considerations applied to them that would enable
them to be categorized as mineral reserves. There is also no
certainty that these inferred mineral resources will be converted
to measured and indicated categories through further drilling, or
into mineral reserves, once economic considerations are
applied.
The Company cautions that a PEA is preliminary
in nature and that it relies upon mineral resource estimates which
have the considerations noted above applied to them. There is
no certainty that the PEA will be realized or that any of the
resources will ever be upgraded to reserves.
Mr. Jose Antonio Olmedo, Eng. Geol. MSc. Is an
Independent Consultant, located in Mexico City, Mexico, who is an
“Independent Qualified Person” as defined by NI 43-101 and the lead
person responsible for completing the Pinos resource has reviewed
this press release as it relates to the Pinos project.
Mr. David Salari, P.Eng. of DENM Engineering
Ltd. located in Oakville , Ontario, Canada who is an “Independent
Qualified Person” as defined by NI 43-101 and the lead person
responsible for reviewing the metallurgical work for the Pinos
resource has reviewed this press release as it relates to the Pinos
project and has overseen the metallurgical and recovery methods and
infrastructure.
ON BEHALF OF THE BOARD,
Curtis TurnerChief Executive Officer
For further information, please contact:
Investor RelationsEmail:
info@candelariamining.comPhone: 604-349-5992
Quality Assurance and Quality Control
(QA/QC)
Preparation and assaying of samples from
Candelaria's Pinos project are done with strict adherence to a
Quality Assurance/Quality Control (QA/QC) protocol. The custody of
the samples are in charge of ALS Minerals from project to the ALS
Minerals' preparation facility in Zacatecas, Zacatecas, Mexico.
Quality-control (QC) samples are inserted in the sample stream
every 20 samples. QC samples include standards and blanks. Sampling
analysis certificates, halved drill cores, chip samples
and rejects are stored for future checking and control
purposes.
About Candelaria Mining
Candelaria Mining is a Canadian-based gold
development and exploration company with a portfolio of highly
prospective projects in Mexico, one of the world’s best mining
jurisdictions. Candelaria’s 100% owned Caballo Blanco Project hosts
NI 43-101 Indicated Resources of 521,000 ounces of gold and
2,170,000 ounces of silver (31,220,000 tonnes grading 0.52 g/t gold
and 2.16 g/t silver) and Inferred Resources of 95,000 ounces of
gold and 590,000 of ounces silver (8,630,000 tonnes grading 0.34
g/t gold and 2.14 g/t silver). Potential exists to increase these
estimated resources through continued drilling and exploration. For
more information on resource estimates, please see the Company’s
website, www.candelariamining.com.
Cautionary Note Regarding
Forward-looking Statements
This press release contains certain
“forward-looking statements” and “forward-looking information”
under applicable Canadian securities laws concerning the business,
operations and financial performance and condition of Candelaria
Mining Corp. (“Candelaria” or “Candelaria Mining”). Forward-looking
statements and forward-looking information include, but are not
limited to, statements with respect to estimation of mineral
resources at mineral projects of Candelaria; ; the realization of
mineral reserve estimates; the timing and amount of estimated
future production; economics of production; success of exploration
activities; estimated production and mine life of the various
mineral projects of Candelaria; the future price of gold and
silver; synergies and financial impact of completed acquisitions;
the benefits of the development potential of the properties of
Candelaria and currency exchange rate fluctuations. Except for
statements of historical fact relating to Candelaria, certain
information contained herein constitutes forward-looking
statements. Forward-looking statements are frequently characterized
by words such as “plan,” “expect,” “project,” “intend,” “believe,”
“anticipate”, “estimate” and other similar words, or statements
that certain events or conditions “may” or “will” occur.
Forward-looking statements are based on the opinions and estimates
of management at the date the statements are made, and are based on
a number of assumptions and subject to a variety of risks and
uncertainties and other factors that could cause actual events or
results to differ materially from those projected in the
forward-looking statements. Many of these assumptions are based on
factors and events that are not within the control of Candelaria
and there is no assurance they will prove to be correct.
Factors that could cause actual results to vary
materially from results anticipated by such forward-looking
statements include variations in metal grades, changes in market
conditions, variations in recovery rates, risks relating to
international operations, fluctuating metal prices and currency
exchange rates, changes in project parameters, the possibility of
project cost overruns or unanticipated costs and expenses, labor
disputes and other risks of the mining industry, failure of plant,
equipment or processes to operate as anticipated.
These factors are discussed in greater detail in
Candelaria's most recent Management Discussion and Analysis filed
on SEDAR, which also provide additional general assumptions in
connection with these statements. Candelaria cautions that the
foregoing list of important factors is not exhaustive. Investors
and others who base themselves on forward-looking statements should
carefully consider the above factors as well as the uncertainties
they represent and the risk they entail. Candelaria believes that
the expectations reflected in those forward-looking statements are
reasonable, but no assurance can be given that these expectations
will prove to be correct and such forward-looking statements
included in this press release should not be unduly relied upon.
These statements speak only as of the date of this press release.
Candelaria undertakes no obligation to update forward-looking
statements if circumstances or management’s estimates or opinions
should change except as required by applicable securities laws.
Although Candelaria has attempted to identify
important factors that could cause actual actions, events or
results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be anticipated, estimated or
intended. Statements concerning mineral resource estimates may also
be deemed to constitute forward-looking statements to the extent
they involve estimates of the mineralization that will be
encountered if the property is developed.
Candelaria Mining (TSXV:CAND)
Historical Stock Chart
From Feb 2025 to Mar 2025
Candelaria Mining (TSXV:CAND)
Historical Stock Chart
From Mar 2024 to Mar 2025