- 314% increase to 2P reserves to Company gross 161.6 BCF for
before tax NPV10 of US$259.7
million
- 551% increase to 3P reserves to Company gross 304.8 BCF for
before tax NPV10 of US$466.8
million
- Company gross unrisked best estimate contingent resources of
195.8 BCF for before-tax NPV10 of US$148.4 million
- Company gross unrisked best estimate prospective resources
of 184.0 BCF for before-tax NPV10 of US$300.5 million
- Production at Maria Conchita has increased to 18 MMcf/d with
100% of gas volumes being sold
TORONTO, Dec. 27,
2023 /CNW/ - NG Energy International Corp.
("NGE" or the "Company") (TSXV: GASX) (OTCQX: GASXF)
is pleased to announce that, with its partners Olympo and Duemav in
the Maria Conchita Block and with Clean Energy and Oleum in the SN9
Block, it has increased reserves at both Maria Conchita and Sinu-9
as part of an updated independent analysis by Sproule International
Limited ("Sproule"). The updated reserves and resources
incorporate the recently drilled Aruchara-3 well at Maria Conchita
which includes the newly encountered section in zone H4 in addition
to zones H1 and H2 and finalized plans for construction of
infrastructure at Sinu-9.
Highlights
Sinu-9 Block:
- Company gross Proved (1P) reserves of 26.7 BCF (37.0 BCF
project gross) of natural gas for before-tax NPV10 of
US$22.0 million;
- Company gross Proved + Probable (2P) reserves of 114.36 BCF
(158.8 BCF project gross) of natural gas for before-tax
NPV10 of US$150.3
million;
- Company gross Proved + Probable + Possible (3P) reserves of
245.3 BCF (340.8 BCF project gross) of natural gas for before-tax
NPV10 of US$331.0
million;
- Company gross unrisked best estimate contingent resources
(development pending) of 130.2 BCF for before-tax NPV10
of US$78.5 million; and
- Company gross unrisked best estimate prospective resources of
131.0 BCF for before-tax NPV10 of US$264.4 million.
Maria Conchita Block:
- Company gross Proved (1P) reserves of 25.0 BCF (31.3 BCF
project gross) of natural gas and 50 MBBL (63 MBBL project gross)
of condensate for before-tax NPV10 of US$75.4 million;
- Company gross Proved + Probable (2P) reserves of 47.2 BCF (59.0
BCF project gross) of natural gas and 75 MBBL (94 MBBL project
gross) of condensate for before-tax NPV10 of
US$34.1 million;
- Company gross Proved + Probable + Possible (3P) reserves of
59.5 BCF (74.3 BCF project gross) of natural gas and 94 MBBL (117
MBBL project gross) of condensate for before-tax NPV10
of US$135.8 million;
- Company gross unrisked best estimate contingent resources
(development pending) of 65.6 BCF for before-tax NPV10
of US$69.9 million; and
- Company gross unrisked best estimate prospective resources
(prospects) of 53.0 BCF for before-tax NPV10 of
US$36.0 million.
Note: All dollar amounts are in US$.
Serafino Iacono, CEO of NGE,
commented: "We are very pleased to have our two greatest
accomplishments of the year reflected in our reserves and resources
report. The report validates the incredible achievements by our
team and our partners after encountering a new naturally fractured
natural gas bearing section in the drilling of Aruchara-3 and
finalizing contracts to build production infrastructure at Sinu-9.
We look forward to continuing to grow these numbers in 2024 as we
aim to achieve significant free cash flow by the end of next
year."
Additional Disclosure Regarding
Sinu-9 and Maria Conchita
Sinu-9
The report entitled "Evaluation of the P&NG Reserves and
Resources of NG Energy International in the Sinu-9 Block,
Colombia" (the "Sinu-9
Report") was prepared by Sproule with an effective date of
December 31, 2023 and a preparation
date of December 21, 2023. The
Company's working interest in Sinu-9 is 72%, subject to payment of
ANH sliding scale royalties. Reserves and resources attributed to
the Hechizo, Brujo, Magico, Mago, Hechicero, Encanto, Milagroso,
Porquero, Embrujo, Ensalmo and Sortilegio zones have been included
in the Sinu-9 Report. Contingent resources for Sinu-9 are petroleum
and natural gas classified as "development pending" and are
attributed a chance of development of 80%. The prospective
resources assigned to the Brujo-Porquero, Hechicero-Porquero and
Milagroso fields are subclassified as "prospects" and are
attributed a chance of discovery of 58-60% and a chance of
development of 66%. The prospective resources assigned to the
Embrujo, Ensalmo and Sortilegio fields are subclassified as "lead"
and are attributed a chance of discovery of 25-30% and a chance of
development of 66%.
Total gas is planned to be produced through new and existing
wellbores and a pipeline to a processing facility using established
recovery technology.
The development plan for the reserves area located within Sinu-9
includes the completion of the Brujo-1X, as well as drilling a
total of 12 wells; 5 in the Hechicero field, 4 in the Magico field
and 3 in the Brujo field. Production will be processed through a
dehydration and compression facility as well as a gas pipeline from
Sinu-9 to Jobo station.
The development plan for the contingent resources area located
within Sinu-9 includes the drilling of 5 locations for the low
estimate scenario, 12 locations for the best estimate scenario and
18 locations for the high estimate scenario. Production will be
processed through new facilities to be built by the Company. Due to
the number of reservoirs identified in the area, the number of
wells may change by category according to the uncertainty
identified in the reservoir areas, since they are not completely
concentric with respect to each other.
The development plan for the prospective resources area located
within Sinu-9 includes the drilling of 13 locations. Production
will be processed through new facilities to be built by the
Company. Due to the number of reservoirs identified in the area,
the number of wells may change by category according to the
uncertainty identified in the reservoir areas, since they are not
completely concentric with respect to each other.
The natural gas resources were estimated based on the
technically recoverable volume, budgeted operating and capital
costs and the terms of the fiscal regime. Forecasts of net revenue
were prepared by predicting the annual production from the
resources and product prices. Gas reserves and resources have only
been assigned based on the gas contracts and the gas contract
precedents expected to be in place at production start-up. There is
no certainty it will be commercially viable to produce any portion
of the contingent resources and there is no certainty that any
portion of the prospective resources will be discovered. If
discovered, there is no certainty that it will be commercially
viable to produce any portion of the resources.
In sum, the development forecast presented in the Sinu-9 Report
was based on a complete evaluation of the Company's lands for the
zones identified by the Company to be prospective for economic
development at the time of the Sinú-9 Report. The development
forecast represents full development of the lands for which
reserves and resources could be assigned. Additional potential
could exist within zones which were not identified by the Company,
within the scope of the Sinú-9 Report.
Maria Conchita
The report entitled "Evaluation of the P&NG Reserves and
Resources of NG Energy International in the Maria Conchita Block,
Colombia" (the "Maria Conchita
Report") was prepared by Sproule with an effective date of
December 31, 2023 and a preparation
date of December 20, 2023. The
Company holds an 80% working interest in Maria Conchita. Reserves
and resources attributed to the H1, H1A, H1A1, H1B, H2, H2B, H3, H4
and LM2 zones have been included in the Maria Conchita
Report. Contingent resources for Maria Conchita are petroleum
and natural gas classified as "development pending" and are
attributed a chance of development of 0.73. The prospective
resources for Maria Conchita are subclassified as "prospect" and
are attributed a chance of discovery of 0.41 and chance of
development of 0.73.
Total gas is planned to be produced through new and existing
wellbores and a pipeline to a processing facility using established
recovery technology.
The development plan for the reserves area located within Maria
Conchita includes the production maintenance of Aruchara-1 and
Aruchara-3, as well as the drilling of a total of 5 wells; 2 in the
Aruchara field and 3 in the Tinka field on 425 acres spacing.
Production will be processed through an existing facility.
The development plan for the contingent resources area located
within Maria Conchita includes the drilling of a total of 10 wells;
9 in the Aruchara field and 1 in the Tinka field on 425 acres
spacing. Additionally, expansion of the existing facility is
included to a total capacity of 60 million cubic feet per day for
the best estimate scenario. Due to the number of reservoirs
identified in the area, the number of wells may change by category
according to the uncertainty identified in reservoir areas, since
they are not completely centric with respect to each other.
The development plan for the prospective resources area located
within Maria Conchita include the drilling of 10 wells on 425 acres
spacing across the intervals of interest H2, H2B and H3.
The natural gas and condensate reserves and resources were
estimated based on the technically recoverable volume, operating
and capital costs and the terms of the fiscal regime. Forecasts of
net revenue were prepared by predicting the annual production from
the reserves, resources and product prices. Gas reserves and
resources have only been assigned based on the gas contracts and
the gas contract precedents in effect as of date of the Maria
Conchita Report. There is no certainty it will be commercially
viable to produce any portion of the contingent resources and there
is no certainty that any portion of the prospective resources will
be discovered. If discovered, there is no certainty that it will be
commercially viable to produce any portion of the resources.
In sum, the development forecast presented in the Maria Conchita
Report was based on a complete evaluation of the Company's lands
for the zones identified by the Company to be prospective for
economic development at the time of the Maria Conchita Report. The
development forecast represents full development of the lands for
which reserves and resources could be assigned. Additional
potential could exist within zones which were not identified by the
Company, within the scope of the Maria Conchita Report.
With regard to the costs associated with achieving additional
commercial production at Maria Conchita and Sinú-9, and the general
timeline of the projects, please see the Company's Annual
Information Form dated June 30, 2023
and its most recent Management's Discussion & Analysis, both of
which can be found at www.sedarplus.ca.
Sproule International Limited, an independent qualified reserves
and resources evaluator, has conducted the reserves and resource
evaluation for Maria Conchita and Sinú-9 in accordance with the
Canadian Oil and Gas Evaluation Handbook (the "COGE
Handbook"). It adheres in all material aspects to the
principles and definitions established by the Calgary Chapter of
the Society of Petroleum Evaluation Engineers regarding annual
reserve and resource reports that are being released in the public
domain. The COGE Handbook is incorporated by reference in National
Instrument 51-101 - Standards of Disclosure for Oil and Gas
Activities ("NI 51-101").
About NG Energy International
Corp.
NG Energy International Corp. is a natural gas exploration and
production company with operations in Colombia. The Company is on a mission to
discover, delineate and develop meaningful natural gas fields in
developing counties to support energy transition and economic
growth. In Colombia, the Company
is executing on this mission with a rapidly growing production base
that is being delivered to the premium priced Colombian market.
NGE's team has extensive technical expertise and a proven track
record of building companies and creating value in South America. For more information, please
visit SEDAR+ (www.sedarplus.ca) and the Company's website
(www.ngenergyintl.com).
Cautionary Statement Regarding
Forward-Looking Information
This news release contains "forward-looking information" and
"forward-looking statements" (collectively, "forward-looking
statements") within the meaning of the applicable Canadian
securities legislation. All statements, other than statements of
historical fact, are forward-looking statements and are based on
expectations, estimates and projections as at the date of this news
release, including, without limitation, the information contained
in this news release regarding any development forecast and any
information concerning the intentions, plans and future actions of
the Company. Any statement that involves discussions with respect
to predictions, expectations, beliefs, plans, projections,
objectives, assumptions, future events or performance (often but
not always using phrases such as "expects", or "does not expect",
"is expected", "anticipates" or "does not anticipate", "plans",
"budget", "scheduled", "forecasts", "estimates", "believes" or
"intends" or variations of such words and phrases or stating that
certain actions, events or results "may" or "could", "would",
"might" or "will" be taken to occur or be achieved) are not
statements of historical fact and may be forward-looking
statements.
Forward-looking statements involve known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of the Company to be materially
different from any future results, performance or achievements
expressed or implied by the forward-looking statements. Factors
that could cause actual results to differ materially from those
anticipated in these forward-looking statements are described under
the caption "Risk Factors" in the Company's most recent Management
Discussion and Analysis and its Annual Information Form dated
June 30, 2023, which are available
for view on SEDAR+ at www.sedarplus.ca. These risks include but are
not limited to, the risks associated with the oil and natural gas
industry, such as exploration, production and general operational
risks, volatility of pricing for oil and natural gas, changing
investor sentiment about the oil and natural gas industry,
competition in the markets where the Company operates, any delays
in production, marketing and transportation of natural gas,
drilling costs and availability of equipment, regulatory approval
risks and environmental risks. Forward-looking statements contained
herein, including but not limited to the Company's
statements related to anticipated business plans or strategies,
including the Company's plans to complete infrastructure
construction required for commercial production from Sinu-9;
completion of the transactions contemplated by the pipeline
agreement; and the completion of any updated resource
assessment and reclassification of contingent resources to
reserves. The Company disclaims, other than as required by
law, any obligation to update any forward-looking statements
whether as a result of new information, results, future events,
circumstances, or if management's estimates or opinions should
change, or otherwise. There can be no assurance that
forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Accordingly, the reader is
cautioned not to place undue reliance on forward-looking
statements.
Neither the TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Abbreviations
The abbreviations set forth below have the following
meanings:
Oil
and Natural Gas Liquids
|
|
Natural Gas
|
Mbbls
|
thousand barrels
|
|
MMcf/d
|
million cubic feet per
day
|
NGLs
|
natural gas liquids
|
|
Bcf
|
billion cubic
feet
|
|
|
|
|
|
Other
|
|
|
|
|
NPV10
|
Net present value using
a 10% forward
discount rate
|
|
|
|
|
|
Caution Respecting Reserves
Information
The determination of oil and gas reserves involves the
preparation of estimates that have an inherent degree of associated
uncertainty. Categories of proved, probable and possible reserves
have been established to reflect the level of these uncertainties
and to provide an indication of the probability of recovery. The
estimation and classification of reserves requires the application
of professional judgement combined with geological and engineering
knowledge to assess whether or not specific reserves classification
criteria have been satisfied. Knowledge of concepts including
uncertainty and risk, probability and statistics, and deterministic
and probabilistic estimation methods is required to properly use
and apply reserves definitions.
The recovery and reserve estimates of NGLs and gas
reserves provided herein are estimates only. Actual reserves may be
greater than or less than the estimates provided herein. The
estimated future net revenue from the production of the disclosed
gas reserves does not represent the fair market value of these
reserves.
Information Regarding
Reserves
Reserves are estimated remaining quantities of commercially
recoverable oil, gas and related substances anticipated to be
recoverable from known accumulations, as of a given date, based on
the analysis of drilling, geological, geophysical and engineering
data; the use of established technology; and specified economic
conditions, which are generally accepted as being reasonable.
Reserves are further classified according to the level of certainty
associated with the estimates and may be subclassified based on
development and production status.
"Proved reserves" are those reserves that can be
estimated with a high degree of certainty to be recoverable. It is
likely that the actual remaining quantities recovered will exceed
the estimated Proved reserves.
"Probable reserves" are those additional
reserves that are less certain to be recovered than Proved
reserves. It is equally likely that the actual remaining quantities
recovered will be greater or less than the sum of the estimated
Proved plus Probable reserves.
"Possible reserves" are those additional
reserves that are less certain to be recovered than Probable
reserves. It is unlikely that the actual remaining quantities
recovered will exceed the sum of the estimated Proved plus Probable
plus Possible reserves. There is a 10% probability that the
quantities actually recovered will equal or exceed the sum of
Proved plus Probable plus Possible reserves.
The qualitative certainty levels referred to in the
definitions above are applicable to "individual reserves entities"
(which refers to the lowest level at which reserves calculations
are performed) and to "reported reserves" (which refers to the
highest-level sum of individual entity estimates for which reserves
estimates are presented). Reported reserves should target the
following levels of certainty under a specific set of economic
conditions:
- at least a 90% probability that the quantities actually
recovered will equal or exceed the estimated Proved reserves;
and
- at least a 50% probability that the quantities actually
recovered will equal or exceed the sum of estimated Proved plus
Probable reserves.
A qualitative measure of the certainty levels pertaining to
estimates prepared for the various reserves categories is desirable
to provide a clearer understanding of the associated risks and
uncertainties. However, the majority of reserves estimates will be
prepared using deterministic methods that do not provide a
mathematically derived quantitative measure of probability. In
principle, there should be no difference between estimates prepared
using probabilistic or deterministic methods.
Each of the reserve categories (Proved and Probable) may be
divided into developed and undeveloped categories as
follows:
"Developed Producing reserves" are those
reserves that are expected to be recovered from completion
intervals open at the time of the estimate. These reserves may be
currently producing or, if shut-in, they must have previously been
on production, and the date of resumption of production must be
known with reasonable certainty.
"Developed Non-Producing reserves" are those
reserves that either have not been on production, or have
previously been on production, but are shut-in, and the date of
resumption of production is unknown.
"Undeveloped reserves" are those reserves
expected to be recovered from known accumulations where a
significant expenditure (e.g., when compared to the cost of
drilling a well) is required to render them capable of production.
They must fully meet the requirements of the reserves
classification (Proved, Probable and Possible) to which they are
assigned and expected to be developed within a limited
time.
In multi-well pools it may be appropriate to allocate total
pool reserves between the developed and undeveloped subclasses or
to subdivide the developed reserves for the pool between developed
producing and developed nonproducing. This allocation should be
based on the estimator's assessment as to the reserves that will be
recovered from specific wells, facilities and completion intervals
in the pool and their respective development and production
status.
Information Regarding
Contingent Resources
"Contingent resources" are those
quantities of oil or gas estimated, as of a given date, to be
potentially recoverable from known accumulations using established
technology or technology under development but which are not
currently considered to be commercially recoverable due to one or
more contingencies. Contingencies are conditions that must be
satisfied for a portion of contingent resources to be classified as
reserves that are: (a) specific to the project being evaluated; and
(b) expected to be resolved within a reasonable timeframe.
The contingencies that apply to the contingent resources
in Sinu-9 are as follows:
(1) Timing of Production and Development: The Company has not
prepared a detailed development and the overall timing of
production is unknown. It is anticipated that as the development
plan is refined the Company would be able to make a final
investment decision, at which point this contingency would be
lifted;
(2) Infrastructure and Market Considerations: Current
infrastructure in the contingent resources area does not allow
access to pipelines or existing facilities, although there are two
third party facilities nearby and the Company has begun discussions
with the relevant third parties. Once this has been completed or is
contracted to be completed in the near term, this contingency would
be lifted;
(3) Corporate Commitment: The Company is committed to move
forward with the commercial development of the assets assigned as
contingent resources, but currently there is no final investment
decision. Therefore, the risk factor is low; and
(4) Regulatory Approval: The Company has not submitted a
regulatory application for the development of the total contingent
area, but its virtually certain that they will obtain regulatory
approval. Therefore, the risk is low. Once the application has been
submitted this contingency would be lifted.
The contingencies that apply to the contingent resources in
Maria Conchita are as follows:
(1) Regulatory Approval: The Company has not submitted a
regulatory application for the development of the contingent
resource area. The absence of the submission of an application to
expand the development has resulted in the contingency. Once the
application has been submitted this contingency would be
lifted;
(2) Timing of Production and Development: The development
plan (which has not been submitted in accordance with the
regulations) includes a high concentration of wells to be drilled
per year. A small risk factor has been applied to account for the
risk of development proceeding at a slower pace. Once the Company
demonstrates this level of development is sustainable this
contingency would be lifted; and
(3) Infrastructure and Market Considerations: Current
infrastructure in the contingent resources area does not allow
access to pipelines or existing facilities. This has restricted the
volumes of produced hydrocarbon from the contingent resources area
that can access viable markets. Therefore, pipelines need to be
built to allow for the product to reach markets. Once this has been
completed or is contracted to be completed in the near term, this
contingency would be lifted.
Contingent resources are further categorised according to the
level of certainty associated with the estimates and may be
sub-classified based on a project maturity and characterised by
their economic status. There are three classifications of
contingent resources: low estimate, best estimate and high
estimate. Best estimate is a classification of estimated resources
described in the COGE Handbook as the best estimate of the quantity
that will be actually recovered; it is equally likely that the
actual remaining quantities recovered will be greater or less than
the best estimate. If probabilistic methods are used, there should
be at least a 50% probability that the quantities actually
recovered will equal or exceed the best estimate.
The project maturity subclasses include development pending,
development on hold, development unclarified and development not
viable. All of the contingent resources disclosed in this news
release are classified as development pending. Development pending
is defined as a contingent resource where resolution of the final
conditions of development is being actively pursued. Chance of
development is the likelihood that an accumulation will be
commercially developed.
Conversion of the development pending contingent resources to
reserves is dependent upon a final investment decision for the
natural gas development of Maria Conchita and
Sinu-9.
For Sinu-9 the major positive factors relevant to the
estimate of the development pending contingent resources are
production has already been tested for three fields (Brujo, Magico
and Hechizo), analogs and test results show high potential for
economically recoverable volumes, reclassification of Brujo, Magico
and Hechizo will assist to get access to future infrastructure for
gas transportation and treatment and the proximity to existing
infrastructure for gas gathering and compression. The major
negative factors are the long-term sustainability of the gas price
is unknown and there is insufficient infrastructure capacity to
handle large volumes of gas.
For Maria Conchita the major positive factors relevant to the
estimate of the development pending contingent resources are
production tests performed in wells drilled in the area are showing
gas presence and wells logged favourable reservoir quality
formations. The major negative factors are the non-concentricity
between target formations, which could cause an increase in the
number of wells, long-term water production since some formations
produced water and caused water loading up problems during well
testing and insufficient infrastructure capacity to handle large
volumes of gas.
There is no certainty that any portion of the resources will
be discovered. If discovered, there is no certainty that it will be
commercially viable to produce any portion of the
resources.
Information Regarding
Prospective Resources
This news release discloses estimates of the Company's
prospective resources. There is no certainty that it will be
commercially viable to produce any portion of such prospective
resources. Estimates of prospective resources involve additional
risks over estimates of reserves. The accuracy of any resources
estimate is a function of the quality and quantity of available
data and of engineering interpretation and judgment. While
resources presented herein are considered reasonable, the estimates
should be accepted with the understanding that reservoir
performance subsequent to the date of the estimate may justify
revision, either upward or downward.
"Prospective Resources" are defined in the COGE
Handbook as those quantities of petroleum estimated, as of a given
date, to be potentially recoverable from undiscovered accumulations
by application of future development projects. Prospective
resources have both an associated chance of discovery and a chance
of development. The chance that an exploration project
will result in the discovery of petroleum is referred to as the
chance of discovery. The chance that an accumulation will be
commercially developed is referred to as the chance of
development.
Prospective Resources are further subdivided in accordance
with the level of certainty associated with recoverable estimates
assuming their discovery:
- Low Estimate: This is considered to be a conservative
estimate of the quantity that will actually be recovered. It is
likely that the actual remaining quantities recovered will exceed
the low estimate. If probabilistic methods are used, there should
be at least a 90 percent probability (P90) that the quantities
actually recovered will equal or exceed the low estimate.
- Best Estimate: This is considered to be the best estimate of
the quantity that will actually be recovered. It is equally likely
that the actual remaining quantities recovered will be greater or
less than the best estimate. If probabilistic methods are used,
there should be at least a 50 percent probability (P50) that the
quantities actually recovered will equal or exceed the best
estimate.
- High Estimate: This is considered to be an optimistic
estimate of the quantity that will actually be recovered. It is
unlikely that the actual remaining quantities recovered will exceed
the high estimate. If probabilistic methods are used, there should
be at least a 10 percent probability (P10) that the quantities
actually recovered will equal or exceed the high estimate.
Prospective resources are not, and should not be confused
with, reserves or contingent resources. "Prospective Resources" are
those quantities of petroleum estimated, as of a given date, to be
potentially recoverable from undiscovered accumulations by
application of future development projects. Prospective Resources
have both an associated chance of discovery and a chance of
development.
There is no certainty that any portion of the prospective
resources will be discovered. If discovered, there is no certainty
that it will be commercially viable to produce any portion of the
prospective resources or that the Company will produce any portion
of the volumes currently classified as prospective resources. The
estimates of prospective resources involve implied assessment,
based on certain estimates and assumptions, that the resources
described exists in the quantities predicted or estimated, as at a
given date, and that the resources can be profitably produced in
the future. Actual prospective resources (and any volumes that may
be reclassified as reserves) and future production therefrom may be
greater than or less than the estimates provided herein.
The contingencies that apply to the prospective resources
in Sinu-9 are as follows:
(1) Evaluation Drilling: There is a requirement for more
evaluation drilling to confirm the geological continuity of the
reservoir and reduce the distance from proven productivity. It is
anticipated that as the Company continues to pursue primary
development of the reservoir, commercial productivity will be
established closer to and within the primary production prospective
resources areas, at which time this contingency would be
removed;
(2) Regulatory Approval: The Company has not submitted a
regulatory application for the development of the prospective
resources area. The absence of the submission of an application to
expand the development has resulted in the contingency. Once the
application has been submitted this contingency would be
lifted;
(3) Infrastructure and Market Considerations: Current
infrastructure in the prospective resources area does not allow
access to pipelines or existing facilities. This has restricted the
volumes of produced hydrocarbon from the prospective resources area
that can access viable markets. Therefore, pipelines and facilities
need to be built to allow for the product to reach markets. Once
this has been completed or is contracted to be completed in the
near term, this contingency would be lifted;
(4) Timing of Production and Development: The Company has not
prepared a detailed development and the overall timing of
production is unknown. It is anticipated that as the development
plan is refined the Company would be able to make a final
investment decision, at which point this contingency would be
lifted; and
(5) Corporate Commitment: There has been no final investment
decision and endorsement from the Company to move forward with
commercial development of the assets assigned as prospective
resources. It is likely that a final investment decision to approve
this project will not occur for several years. Additionally, a
detailed development plan has not been created and further work
needs to be completed to confirm how the resources will be
developed. It is anticipated that as the development plan is
refined the Company would be able to make a final investment
decision, at which point this contingency would be lifted.
The contingencies that apply to the prospective resources
in Maria Conchita are as follows:
(1) Regulatory Approval: The Company has not submitted a
regulatory application for the development of the prospective
resources area. The absence of the submission of an application to
expand the development has resulted in the contingency. Once the
application has been submitted this contingency would be
lifted;
(2) Timing of Production and Development: The development
plan (which has not been submitted in accordance with the
regulations) includes a high concentration of wells to be drilled
per year. A small risk factor has been applied to account for the
risk of development proceeding at a slower pace. Once the Company
demonstrates this level of development is sustainable this
contingency would be lifted; and
(3) Infrastructure and Market Considerations: Current
infrastructure in the Prospective Resources Area does not allow
access to pipelines or existing facilities. This has restricted the
volumes of produced hydrocarbon from the Prospective Resources Area
that can access viable markets. Therefore, pipelines and facilities
need to be built to allow for the product to reach markets. Once
this has been completed or is contracted to be completed in the
near term, this contingency would be lifted.
For Sinu-9 the major positive factors relevant to the
estimate of the prospective resources are the proximity of the
Milagroso prospect to the existing gas gathering and compression
infrastructure could speed gas access to the market if discovered
and exploration wells have been successfully drilled in Sinu-9, so
the prospects uncertainty is decreasing. The major negative factors
are the long-term sustainability of the gas price is unknown,
prospects and leads are quite far away in some instances from the
gathering and compression facilities, so additional CAPEX should be
required to construct new facilities and due to the high
uncertainty associated with Cabala and Conjuro, these couldn't be
classified as prospective resources, further studies should be
performed to classify them as that.
For Maria Conchita the major positive factors relevant to the
estimate of the prospective resources are as large amplitudes are
seen in seismic for prospective resources, the areas could be
larger than expected. The major negative factors are the
uncertainty in lateral variation of thickness and reservoir quality
and insufficient infrastructure capacity to handle large volumes of
gas.
SOURCE NG Energy International Corp.