TSXV: GMIN
OTCQX: GMINF
All amounts are in USD unless stated
otherwise
- Project is 30% complete and remains on track and on budget for
commercial production in H2-2024
- Safety remains a priority with over 1,770,063 man-hours worked
with no Lost Time Incidents
- 1,871 employees and contractors currently employed by the
Project (94% from within Brazil)
- Detailed engineering 81% complete with procurement essentially
finalized at 97%
- Project commitments total $302
million (66% of total) tracking in line with Feasibility
Study
- Andrew Storrie appointed General Manager of
Tocantinzinho
- Updated virtual site tour available through VRIFY
platform
BROSSARD, QC, June 13,
2023 /CNW/ - G Mining Ventures
Corp. ("GMIN" or the "Corporation") (TSXV:
GMIN) (OTCQX: GMINF) is pleased to provide an update on progress
made at GMIN's 100% owned Tocantinzinho Gold Project ("TZ"
or the "Project") currently under construction in the State
of Pará, Brazil. Significant
advancements have been made in all work areas, and the Project
remains on track and on budget for commercial production in
H2-2024. All updates are dated as of May
31st, 2023, unless stated otherwise.
Louis-Pierre Gignac, President
& Chief Executive Officer, commented: "I am proud
of the excellent progress that the GMIN team is making on our TZ
project, through their tireless commitment to the highest level of
safety, quality, and efficiency in execution. Our signature
self-perform approach is once again bearing fruit through
significant advancements in engineering, procurement, delivery,
hiring, training, construction, mining and preparation towards
operational readiness. We are gratified to see the positive impact
we are having on our employees, contractors, community and
stakeholders at large, as we move toward commercial production in
H2-2024."
Tocantinzinho Project
Update
Total Project is currently 30% complete and trending on time
and on budget for commercial production in H2-24.
Detailed Engineering is 81% complete. Notable advancements
to date on the Process Plant include:
- Completion of Hazard and Operability Study;
- Procurement of major mechanical and electrical packages
substantially complete, with bulk material procurement well
advanced;
- Structural steel and concrete drawings issued for construction
at primary crusher, reclaim tunnel, grinding area
and CIL;
- SCADA (Supervisory Control and Data Acquisition) and Automation
Systems have been initiated;
- Laboratory expert onboarded; and
- Formal review of process plant commissioning plan has been
initiated.
Figure 1 – Mine
Infrastructure Area and Process Plant Progress
Notable advancements to date on the items outside the process
plant include:
- Geotechnical work complete for the flotation tailings storage
facility ("FTSF") and CIL tailings storage facility;
- Permanent camp, kitchen and other related services near
completion;
- All piping and instrumentation diagrams issued for
construction;
- Engineering completed for substantially all buildings; and
- Final design of permanent explosive magazine and landfill
facility completed.
Procurement and Delivery
Overall Project procurement is at 97% complete, with 154 (out of
159 total) packages awarded. Commitments to date total $302 million (66% of project total), including
project-to-date expenditures of $198
million (43% of project total). Expenditures and schedule
are tracking in line with the Feasibility Study dated February 09, 2022 (filed under GMIN's profile on
Sedar, entitled "Feasibility Study – NI 43-101 Technical Report,
Tocantinzinho Gold Project.").
The focus of the supply chain team is transitioning away from
procurement towards logistics. Cumulatively, 33,334 tonnes of
material on 3,833 truckloads have been delivered to site since the
start of the Project. May was an exceptional month with 9,361
tonnes of material delivered to site on 797 truckloads (details
below).
The construction and commissioning of the grinding circuit is on
the Project critical path. Recent QA/QC inspections at various
manufacturing facilities for the SAG and ball mill components
indicate that completion and shipping dates are staying on
schedule. Manufacturing of heads, trunnions and shells are expected
by the end of July.
Figure 2 – Tonnes of
Material Delivered to Site
Figure 3 –
Truckloads Delivered to Site
Figure 4 – Delivery to
Site
Construction
Physical construction (excluding services, mine and powerline)
is now 27% complete, with work initiated on almost all Project
areas.
The following major milestones have been reached in
construction:
- Dorms, kitchen and all related facilities are nearly completed
with final turnover planned in June;
- Water treatment plant and sewage treatment plant commissioned
and operational;
- SAG mill and ball mill foundations are well advanced;
- CIL area construction started ahead of schedule, with
foundations complete and tank assembly substantially advanced;
- Stage 1 of the 13.8kV overhead line is complete, servicing camp
dorms and its communication tower, welcome center/laundry,
kitchen;
- Permanent kitchen is substantially complete, with full
commissioning anticipated by the end of Q2;
- Construction of the aggregate plant is complete and
commissioning activities initiated; and
- Preparation activities for the main FTSF dam have advanced
including access roads, foundation grubbing activities and coffer
dams. Fill placement for the main dam is to be initiated in
June.
Figure 5 – TZ Site
Construction Overview
Figure 6 – Mill Foundation
and Monument Installation
Figure 7 – Aggregate
Plant
Pre-Production Mining
With night shift operations starting in May, and excellent
mobile equipment availability, pre-production mining has made
significant progress since the start of the dry season. At the end
of May four additional mining trucks (CAT 777) were commissioned,
reaching a total of eight. In June, the last four mining trucks
will be assembled and commissioned along with a second mining
shovel (CAT 6030) to be received at site.
To date, 1.74 Mt of waste material has been excavated from the
starter pit. Since the blasting permit was secured in early April,
150 kt have been blasted. The competent waste material has been
used for construction purposes, for road and coffer dam
construction, as a source of aggregate, and in the future will be
used to construct the FTSF main dam.
Approximately 2.4 Mt of ore will be stockpiled during the
pre-production period prior to mill commissioning, providing
roughly 6 months of mill feed.
Figure 8 – Open Pit
Mining
Power Infrastructure
Since commencing in December 2022,
construction of the 190-km 138 kV power transmission line from Novo
Progresso to TZ is advancing quickly. Powerline progress has
reached 41% and is trending on budget and schedule for completion
in H1-24.
Out of a total of 483 transmission towers:
- 276 foundations have been poured (57%);
- 269 towers have been assembled (56%); and
- 187 towers have been lifted (39%); and
- Stringing activities started with a total of 4.2 km completed
in May.
Figure 9 – Transmission
Line Tower Clamping
The main substation at site achieved significant progress as per
project schedule:
- All purchase orders issued;
- Earthworks completed;
- Main bases poured with transformers positioned on the bases;
and
- Reactor factory acceptance testing ongoing.
Figure 10 – Site Main
Substation Progress
The Novo Progresso substation is progressing on schedule:
- All purchase orders issued;
- All drawings issued for construction; and
- Civil works team mobilized with construction to start on
June 15th.
Human Resources
1,871 employees and contractors are currently employed by the
Project with 94% of the workforce comprised of Brazilians. Of the
total workforce, 52% are from the nearby communities of Itaituba,
Morais Almeida, Mamoal, and Jardim
do Ouro. Of the 95 expatriate employees, 35 are from other South
American countries where G Mining Services previously completed
other mining projects on/below budget and on schedule.
On May 10th,
Andrew Storrie was appointed General
Manager of Tocantinzinho. Mr. Storrie is a seasoned and
accomplished mining professional with a long history of operating
experience in Brazil. Most
recently, Mr. Storrie worked as General Manager of Equinox Gold
Corp.'s Aurizona Mine in Brazil,
where he was responsible for taking the mine from construction into
operation.
As General Manager, Mr. Storrie will be instrumental in the
operational readiness planning and as support to the construction
team during pre-production. As the Project approaches commercial
production, all departments, including the mine, mill, and site
services will report to the General Manager.
Health & Safety
The Corporation continues to deliver on its core value of
prioritizing health and safety. A total of 1,770,063 man-hours have
been worked to date with no Lost Time Incidents.
Figure 11 – Daily Morning
Safety Meeting and Ergonomic Exercises
Project Development
Timeline
The Project remains on track and on budget for commercial
production in H2-2024.
Virtual Site Tour and Feasibility
Study Presentation
Updated satellite imagery and 360 photography showing the site
progress is available through the corporate presentation at:
https://vrify.com/decks/13544. A 3D presentation of the
Project Feasibility Study is available at: Feasibility Study 3D
VRIFY Presentation. Both presentations can be accessed by
visiting GMIN's website at https://www.gminingventures.com.
Timetable and Next Steps
Having made the positive construction decision, the Corporation
will be focused on the following activities:
- Issuance of inaugural ESG report in Q2-23;
- Process plant commissioning commence in Q2-24
- Completion of the powerline construction in Q1-24;
and
- Commercial production in H2-24.
Qualified Person
Louis-Pierre Gignac, President
& Chief Executive Officer of GMIN, a QP as defined in NI
43-101, has reviewed the press release on behalf of the Corporation
and has approved the technical disclosure contained in this press
release.
About G Mining Ventures
Corp.
G Mining Ventures Corp. (TSXV: GMIN) (OTCQX: GMINF) is a mining
company engaged in the acquisition, exploration and development of
precious metal projects, to capitalize on the value uplift from
successful mine development. GMIN is well-positioned to grow into
the next mid-tier precious metals producer by leveraging strong
access to capital and proven development expertise. GMIN is
currently anchored by its flagship Tocantinzinho Gold Project in
mining friendly and prospective State of Pará, Brazil.
Additional Information
For further information on GMIN, please visit the website at
www.gminingventures.com.
Neither the TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this press release.
Cautionary Statement on
Forward-Looking Information
All statements, other than statements of historical fact,
contained in this press release constitute "forward-looking
information" and "forward-looking statements" within the meaning of
certain securities laws and are based on expectations and
projections as of the date of this press release. Forward-looking
statements contained in this press release include, without
limitation, those related to (i) the Project remaining on track and
on budget for commercial production in H2-2024; (ii) the Project
commitments to track in line with the Feasibility Study; (iii) the
future use of waste material for construction; (iv) the
commissioning of equipment for pre-production mining; and
(v) more generally, the horizontal bar chart entitled
"Project Development Timeline" as well as the sections entitled
"Timetable and Next Steps" and "About G Mining Ventures
Corp.".
Forward-looking statements are based on expectations,
estimates and projections as of the time of this press release.
Forward-looking statements are necessarily based upon a number of
estimates and assumptions that, while considered reasonable by the
Corporation as of the time of such statements, are inherently
subject to significant business, economic and competitive
uncertainties and contingencies. These estimates and assumptions
may prove to be incorrect. Such assumptions include,
without limitation, those relating to the price of gold and
currency exchange rates, those outlined in the Feasibility Study
and those underlying the items listed on the above section entitled
"About G Mining Ventures Corp.".
Many of these uncertainties and contingencies can directly or
indirectly affect, and could cause, actual results to differ
materially from those expressed or implied in any forward-looking
statements. There can be no assurance that, notably but without
limitation, the Corporation will (i) continue to progress on all
fronts at the Project, to carry the self-perform approach with
similar success as proven in the past and to continue taking care
of the health and safety of all its stakeholders (with no Lost Time
Incidents), (ii) keep its expenditures and schedule in line with
the Feasibility Study, (iii) carry its next steps as per the above
timetable and effect the transition to commercial production as
contemplated, (iv) complete the transmission line in H1-2024 and
bring the Project into commercial production in the H2-2024, or at
all, (v) advance TZ into one of the largest operating gold
mines in Brazil, or (vi) use TZ to
grow GMIN into the next intermediate producer, as future events
could differ materially from what is currently anticipated by the
Corporation. There is also no assurance that the State of
Pará, in Brazil, will remain a
mining friendly and prospective jurisdiction.
By their very nature, forward-looking statements involve
inherent risks and uncertainties, both general and specific, and
risks exist that estimates, forecasts, projections and other
forward-looking statements will not be achieved or that assumptions
do not reflect future experience. Forward-looking statements are
provided for the purpose of providing information about
management's expectations and plans relating to the future. Readers
are cautioned not to place undue reliance on these forward-looking
statements as a number of important risk factors and future events
could cause the actual outcomes to differ materially from the
beliefs, plans, objectives, expectations, anticipations, estimates,
assumptions and intentions expressed in such forward-looking
statements. All of the forward-looking statements made in this
press release are qualified by these cautionary statements and
those made in the Corporation's other filings with the securities
regulators of Canada including,
but not limited to, the cautionary statements made in the relevant
sections of the Corporation's (i) Annual Information Form dated
April 28, 2023, for the financial
year ended December 31, 2022, and
(ii) Management Discussion & Analysis. The Corporation cautions
that the foregoing list of factors that may affect future results
is not exhaustive, and new, unforeseeable risks may arise from time
to time. The Corporation disclaims any intention or obligation to
update or revise any forward-looking statements or to explain any
material difference between subsequent actual events and such
forward-looking statements, except to the extent required by
applicable law.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/g-mining-ventures-provides-update-on-site-activities-at-tocantinzinho-gold-project-301849064.html
SOURCE G Mining Ventures Corp