Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) “Monument” or
the “Company” today announced its production and financial results
for the second quarter of fiscal 2022 and the six months ended
December 31, 2021. All amounts are expressed in United States
dollars (“US$”) unless otherwise indicated (refer to www.sedar.com
for full financial results).
President and CEO Cathy Zhai commented, “I am
glad that the second quarter progressed the Selinsing Flotation
Plant Project to 37% completion and awarded all major equipment
suppliers and construction contractors successfully. Purchase
orders for major long lead items of equipment were issued, and
fabrication of the flotation cell went well, and the civil work has
completed the earth work. We stay on schedule anticipating the dry
commissioning completion by June 2022. At the Murchison Gold
Project, the Phase 1 drill program assays were highly encouraging
and highlighted a new high-grade mineralization at the Junction
Target in an area where there is significant room to extend
mineralization with further drill programs. The Murchison Phase 2
drilling program commenced targeting down dip and down plunge of
known high grade deposits aimed at testing the potential expansion
of the underground resource.”
Second Quarter Highlights:
- Murchison Phase 1
drilling results confirm discovery of new high-grade mineralization
at the Junction Target;
- Murchison Phase 2 drilling started
with 2,918 meters (12 RC holes) drilled;
- Peranggih RC drilling and channel
sampling confirms the extension of oxide mineralization and
potential supplies to the mill;
- Selinsing Flotation Plant Project
is progressing as planned with 37% completion to date;
- Selinsing Gold Mine’s Q2 production
impacted by heavy monsoon rains:
- 1,683oz of gold produced in Q2,
FY2022 (Q2, FY2021: 2,963oz);
- 2,873 ounces (“oz”) of gold sold
for $5.05 million in Q2, FY2022 (Q2, FY2021: 3,754oz for
$6.84million);
- Average quarterly gold price
realized at $1,828/oz in Q2, FY2022 (Q2, FY2021: $1,889/oz);
- Cash cost per ounce sold was
$1,810/oz in Q2, FY2022 (Q2, FY2021: $1,103/oz);
- Gross margin decreased by 106% to
negative $0.15 million in Q2, FY2022 (Q2, FY2021: $2.69
million);
- All-in sustaining cost (“AISC”) increased to $2,146/oz in Q2,
FY2022 (Q2, FY2021: $1,501/oz) (section 15 “Non-IFRS Performance
Measures” of Q2 Management’s Discussion and Analysis
(“MD&A”).
Second Quarter and Six Months Production
and Financial Highlights
|
Three months endedDecember31, |
Six months endedDecember 31, |
|
2021 |
|
2020 |
|
2021 |
|
2020 |
|
Production |
|
|
|
|
Ore mined (t) |
85,209 |
|
112,073 |
|
160,181 |
|
193,649 |
|
Ore processed (t) |
1,770,975 |
|
963,863 |
|
3,713,309 |
|
2,022,019 |
|
Average mill feed grade
(g/t) |
129,000 |
|
152,836 |
|
285,611 |
|
319,268 |
|
Processing recovery rate
(%) |
0.56 |
|
0.89 |
|
0.55 |
|
0.94 |
|
Gold recovery (oz) |
63 |
% |
58 |
% |
64 |
% |
61 |
% |
Gold production (1) (oz) |
1,683 |
|
2,963 |
|
2,726 |
|
6,467 |
|
Gold sold (oz) |
2,873 |
|
3,754 |
|
4,296 |
|
6,854 |
|
|
|
|
|
Three months ended December 31, |
Six months ended December 31, |
|
2021 |
|
2020 |
|
2021 |
|
2020 |
|
Financial (expressed in
thousands of US$) |
$ |
|
$ |
|
$ |
|
$ |
|
Revenue |
5,046 |
|
6,835 |
|
7,429 |
|
12,754 |
|
Gross margin from mining
operations |
(153 |
) |
2,694 |
|
195 |
|
5,753 |
|
Income before other items |
(2,124 |
) |
1,159 |
|
(2,879 |
) |
3,102 |
|
Net loss |
(2,502 |
) |
(649 |
) |
(3,769 |
) |
(511 |
) |
Cash flows (used in) provided
by operations |
(4,023 |
) |
796 |
|
(4,000 |
) |
1,543 |
|
Working capital |
38,605 |
|
20,384 |
|
38,605 |
|
20,384 |
|
|
|
|
|
|
Loss
per share – basic and diluted (US$/share) |
(0.01 |
) |
(0.00 |
) |
(0.01 |
) |
(0.00 |
) |
|
|
|
|
|
Other |
US$/oz |
|
US$/oz |
|
US$/oz |
|
US$/oz |
|
Average realized gold price
per ounce sold (2) |
1,828 |
|
1,889 |
|
1,823 |
|
1,899 |
|
|
|
|
|
|
Cash cost per ounce sold: |
|
|
|
|
Mining |
728 |
|
365 |
|
660 |
|
323 |
|
Processing |
897 |
|
552 |
|
838 |
|
520 |
|
Royalties |
164 |
|
172 |
|
165 |
|
168 |
|
Operations, net of silver
recovery |
21 |
|
14 |
|
20 |
|
10 |
|
Total cash cost per
ounce sold |
1,810 |
|
1,103 |
|
1,683 |
|
1,021 |
|
By-product silver recovery |
0 |
|
1 |
|
0 |
|
1 |
|
Operation expenses |
0 |
|
40 |
|
11 |
|
26 |
|
Corporate expenses |
9 |
|
6 |
|
7 |
|
7 |
|
Accretion of asset retirement obligation |
13 |
|
9 |
|
16 |
|
10 |
|
Exploration and evaluation expenditures |
47 |
|
19 |
|
35 |
|
16 |
|
Sustaining capital expenditures |
267 |
|
323 |
|
361 |
|
219 |
|
Total all-in sustaining costs per ounce sold |
2,146 |
|
1,501 |
|
2,114 |
|
1,300 |
|
(1) Defined as good delivery gold
bullion according to London Bullion Market Association (“LBMA”),
net of gold doŕe in transit and refinery adjustment.(2)
Monument realized US$1,828/oz for the three months ended
December 31, 2021 which excludes gold prepaid delivered of 723oz
for comparison purposes.(3) Total cash cost per ounce
includes production costs such as mining, processing, tailing
facility maintenance and camp administration, royalties and
operating costs such as storage, temporary mine production closure,
community development cost and property fees, net of by-product
credits. Cash cost excludes amortization, depletion, accretion
expenses, idle production costs, capital costs, exploration costs
and corporate administration costs. Readers should refer to section
15 “Non-GAAP Performance Measures” of Q2 MD&A. (4)
All-in sustaining cost per ounce includes total cash costs
and adds sustaining capital expenditures, corporate administrative
expenses for the Selinsing Gold Mine including share-based
compensation, exploration and evaluation costs, and accretion of
asset retirement obligations. Certain other cash expenditures,
including tax payments and acquisition costs, are not included.
Readers should refer to section 15 “Non-GAAP Performance Measures”
of Q2 MD&A.
Q2 FY2022 Production Analysis
- Q2 FY2022 gold
production was 1,683oz, a 43% decrease as compared to 2,963oz for
Q2 FY2021. The decrease resulted from heavy rain and a large
quantity of super low-grade ore being fed into the mill although
gold recovery was slightly higher.
- Q2 FY2022 ore
processed decreased to 129,000t from 152,836t for Q2 FY2021. The
decreased mill feed was mainly due to less oxide ore and old
tailings being fed into plant.
- Average mill
feed grade was 0.56g/t Au in Q2 FY2022 as compared to 0.89g/t Au of
Q2 FY2021. Q2 FY2022 processing recovery rate increased to 63.2%
from 58.4% for Q2 FY2021. The slight increase in processing
recovery rate was mainly due to significant increase in Peranggih
oxide materials being processed.
- Q2 FY2022 cash
cost per ounce increased by 64% to $1,810/oz from $1,103/oz for Q2
FY2021. This increase was primarily due to a significant reduction
in the mill feed grade from 0.89g/t Au to 0.56g/t Au and
significantly more low-grade leachable sulphide ore and low-grade
Peranggih materials being processed.
- Ore stockpile
has reduced mainly as a result of lower mining rate primarily due
to heavy rain in both Selinsing pit and Peranggih pit especially
towards to the end of the quarter.
Q2 FY2022 Financial
Analysis
- Q2 FY2022 gold
sales generated revenue was $5.05 million as compared to $6.84
million from Q2 FY2021. Gold sales revenue was derived from the
sale of 2,150oz (Q2 FY2021: 3,050oz) of gold at an average realized
gold price of $1,828 per ounce (Q2 FY2021: $1,889 per ounce) and
the delivery of 723oz (Q2 FY2021: 704 oz at $1,525 per ounce gold
equivalent) in fulfilling gold prepaid sale obligations.
- Q2 FY2022 total
production costs increased by 26% to $5.20 million as compared to
$4.14 million from Q1 FY2021. Cash cost per ounce increased by 64%
to $1,810/oz as compared to $1,103/oz of the same period last year.
The increase was attributable to a 45% decrease in the mill feed
grade from 0.89g/t to 0.56g/t, heavy rain, offset by an increase in
recovery to 63.2% (Q2 FY2021: 58.4%), as a result of processing
significantly more leachable sulphide ore and other low grade
ores.
- Gross margin for
Q2 FY2022 was negative $0.15 million before operation expenses and
non-cash amortization and accretion. That represented an 106%
decrease as compared to $2.69million from Q2 FY2021. The decrease
in gross margin was attributable to significant lower grade ore
feed, much lower volume of gold sold, and increased cash
costs.
- Net loss for Q2
FY2022 was $2.50 million, or ($0.01) per share as compared to net
loss of $0.65 million or ($0.00) per share from Q2 FY2021. The net
loss was mainly caused by lower operating margins impacted by heavy
rain.
- Cash and cash
equivalents balance as at December 31, 2021 was $27.79 million, a
decrease of $10.83 million from the balance at June 30, 2021 of
$38.62 million due to $4 million used in operation activities, $5.5
million development cost in Selinsing including $3.8 million spent
in sulphide project development, and $1.3 million spent in
Murchison exploration and maintenance activities . As at December
31, 2021, the Company had positive working capital of $38.61
million as compared to that at June 30, 2021 of $48.54
million.
Development
Selinsing Gold Mine
The Sulphide project development comprises the
Stage 1 Flotation plant project and Stage 2 BIOX® leaching plant.
The flotation plant construction includes project management,
project validation, flotation design and engineering, procurement,
construction and commissioning. Mine development included upgrading
of tailing storage facilities, pit push backs, and river diversion.
The flotation plant is expected to be completed by June 2022 with
an estimated cost of up to $20 million. As of December 31, 2021,
37% of overall project has been completed.
During Q2 FY2022 Mincore Pty Ltd. (“Mincore”)
completed the detailed engineering design of the flotation plant.
Equipment specifications and data sheets were completed, and
material take-offs and bills of material were issued for concrete,
structural steel, piping, valves and electric cables
instrumentation. All civil and structural, mechanical and piping
drawings were issued for construction. Purchase orders for major
long lead items of equipment were sent to the selected
manufacturers. During the quarter the construction contract has
been awarded to Seong Henng Engineering Works Sdn Bhd, an
experienced Malaysian contractor which carried out the Selinsing
Oxide Plant construction over 10 years ago.
During Q2 FY2022, R&D work produced the
sample of flotation concentrate for pressure filtration testwork by
the filter press supplier McLanahan. It is also achieved a key
milestone that the pilot plant was successfully commissioned into
operation, comprised ball mill and classifier, rougher / scavenger
flotation cells and three stages of cleaner flotation. Samples of
flotation concentrate was produced and a sample of this was sent to
McLanahan for filter press testwork. Antimony leaching tests was
carried out to support gold concentrates marketing effort.
The Tail Storage Facility expansion progressed
91.9% as of December 31, 2021, reached the 537m RL, which provides
adequate capacity till May 2023.
Murchison Gold Project
No mine development was planned during the
second quarter of fiscal year 2022, with the focus on exploration
at Murchison. Murchison Project development is put on hold. The
processing plant and other facilities are under care and
maintenance and in good condition. Site accommodations and catering
are fully functional to host administrative, exploration and mining
activities.
Exploration Progress
Malaysia
Peranggih is currently the focus for identifying
additional mineable material to extend production from the oxide
plant at Selinsing. In the Phase 1 and 2 Reverse Circulation (“RC”)
drilling programs at Peranggih approximately 70% of holes have hit
gold mineralization above an oxide cut-off (>0.35g/t Au) at less
than 50m below the surface, defining a mineralized zone 830m long
and 60m wide. Exploration in the second quarter of FY2022 comprised
of 396 channel samples, which tested extensions to known
mineralization at Peranggih, where follow-up RC drilling is planned
in Q3 FY2022, and a new prospect at Mentique, where further mapping
and sampling are to be undertaken.
Western Australia
At the Murchison Gold Project, the Phase 1 RC
and Air Core (“AC”) drill program completion was announced and
comprised 3,465m in 46 RC holes and 10,484m in 349 AC holes, which
were designed to test new targets away from known resources. All
assays from the Phase 1 drilling were received in January 2022,
subsequent to the end of the second quarter, and significant
intercepts include 5m at 1.53 g/t Au from 31m (21BNRC037), 2m at
0.81 g/t Au from 111m and 3m at 1.91 g/t Au from 119m (21BNRC038)
and 2m at 1.56 g/t Au from 60m and 2m at 3.70g/t Au from 106m
(21BNRC039) at Munro Bore, 8m at 0.97g/t Au from 5m (21BNRC008) and
7m at 0.82g/t Au from 18m (21BNRC026) at FLC2, and 3m at 10.2g/t Au
from 22m (21BNAC213) at the newly discovered Junction Target.
A Phase 2 RC and diamond drilling (DD) program
commenced in November 2021, and a total of 2,918m in 12 RC holes
were completed during the second quarter of FY2022, testing for
extensions to known mineralization and resources at the NOA1, NOA2,
NOA78 and Alliance target areas. 1,406 RC samples from the Phase 2
drilling were dispatched to ALS Geochemistry in Perth during the
quarter. DD drilling was rearranged and postponed to March 2022 due
to availability of the drill rigs. The Phase 2 drilling program is
expected to be completed by the end of March 2022.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE: D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 200
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks; other risks inherent in the mining industry and other risks
described in the management discussion and analysis of the Company
and the technical reports on the Company's projects, all of which
are available under the profile of the Company on SEDAR at
www.sedar.com. Material factors and assumptions used to develop
forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; the expected
timing and results of development and exploration activities; costs
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; exchange
rates; and all of the factors and assumptions described in the
management discussion and analysis of the Company and the technical
reports on the Company's projects, all of which are available under
the profile of the Company on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024