Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or
the "Company") is pleased to report the progress of the flotation
plant at the Selinsing Gold Mine in Malaysia, and to announce that
a ground-breaking ceremony (Figure 1) has been held at the mine
site to herald the return of the principal contractor Seong Henng
Engineering Works Sdn Bhd (“Seong Henng”) to carry out the
construction of the flotation plant.
President and CEO Cathy Zhai commented, “We are
very happy to report the progress of the flotation plant
construction at Selinsing; our on-site team is managing the project
and is overseeing the principal contractor Seong Henng. Together we
are working to complete the construction of the flotation plant to
a high standard, safely, diligently, on time and on budget ready
for dry commissioning at the end of June 2022.”
Figure 1: Ground-breaking Ceremony Ribbon
Cutting at Selinsing Gold Mine is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/2093b803-17fa-495e-9167-279f895ed6c6
Charlie Northfield, General Manager and the
project sponsor at the Selinsing Gold Mine commented: “It is a
great pleasure to see the return of Seong Henng, our long-standing
principal contractor partner, to play a major role in the
construction of the flotation plant. Seong Henng is a local
Malaysia-based manufacturing Company, and had historically
constructed the Selinsing Gold plant and its expansion
successfully.”
The flotation plant construction includes
project management, project validation, flotation design and
engineering, procurement, construction and commissioning. The
flotation plant construction project is 50% complete to date.
Detailed Engineering Design
Mincore Pty Ltd. (“Mincore”) previously
completed the detailed engineering design and has now finalized the
3D model of the new flotation processing plant with provision for
the future addition of the BIOX® plant and ancillary works (Figure
2).
Figure 2: Finalized 3D Model of Sulphide
Flotation Circuit Addition to Selinsing Gold Plant is
available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/af324d08-9757-45c0-8959-aec4cc231596
Procurement
The contract for the supply of flotation cells
was awarded to BGRIMM Machinery and Technology Co Ltd of Beijing,
China. Manufacture of the flotation cells has been completed and
the factory acceptance tests were successfully carried out on
January 25th-26th, 2022. Packing is in progress and the shipment is
due to depart Tianjin on March 15th, 2022.
Metso Outotec Corporation of Finland is
supplying the flotation concentrate and water recovery thickeners.
Fabrication work and parts procurement has commenced. Trial
assembly is scheduled for April 12th, 2022 and the thickeners are
scheduled to be delivered to site in May / June 2022. The
thickeners are of segmented / bolted design to allow for rapid
assembly once received on site, as time will be short to complete
the installation on time.
The flotation concentrate filter press is being
supplied by McLanahan Corporation of Pennsylvania, USA
(“McLanahan”). All equipment parts are on order and fabrication is
underway with expected completion in March 2022. The filter press
assembly is due for completion on April 7th, shipping on April 12th
and delivery to site in May/June 2022.
Other equipment that is contracted out includes
but not limited to: Slurry pumps with 50% complete and shipment is
scheduled for May 9th, 2022, the Afromix agitators have been
completed and are expected to arrive in Port Klang, Malaysia on
March 28th, 2022. The flotation air blowers and
compressor were ordered and are in progress with 30% completion,
with delivery scheduled for May 27th, 2022. The contract to design,
manufacture, deliver and commission the containerized MCC switch
room was awarded with delivery is expected on May 13th, 2022.
Purchase orders were also issued for the concentrate sampler and
the helical rotor reagent pumps; manufacturing was in progress for
both orders. Manufacturing of 11kV / 415V transformer was reported
as 100% complete.
Major Construction Contractor
Engagement
The dedicated project team is complete and
comprises the project manager, assistant project manager, lead
engineer, senior engineer, electrical engineer, procurement
engineer and clerk of works. The project team oversee the
construction work.
Seong Henng has been appointed as the principal
contractor. They previously carried out construction work to build
and expand Selinsing gold processing plant over the past 10 years.
They refurbished and commissioned the CITIC ball mill as part of
the first phase gravity-only process plant in 2009; built and
commissioned the second phase carbon in leach circuit subsequently
in 2010; and constructed/commissioned a new CITIC ball mill and
three new leach tanks in 2012 for the third phase plant expansion.
Seong Henng received the Letter of Award with a commencement date
of January 12th, 2022, a contract period of six months and a
completion date of July 7th, 2022.
R&D Work
The completed pilot plant comprises ball mill
and classifier, rougher / scavenger flotation cells and three
stages of cleaner flotation. (Figure 3). A one tonne sample of
transition ore was crushed in the laboratory fine jaw crusher to
100% passing 2mm to provide feed for the pilot plant ball mill. The
sample was processed using the same reagent regime planned for the
full-scale plant. A total of 50kg of flotation concentrate was
produced and a sample of this was sent to McLanahan for filter
press testwork. Antimony leaching tests were conducted to support
gold concentrates marketing efforts.
Figure 3: Flotation Pilot
Plant is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/9e4e3edb-1d0a-4230-8190-25405da06139
Civil Foundation Work
Seong Henng mobilized to site on January 22nd,
2022 and commenced delivery of reinforcing steel (rebar), bar
bending equipment, formwork, HDPE piping and fusion machine.
Temporary benchmarks were set out for survey tie-in.
Civil foundation work is progressing with the
construction of the retaining wall extension. Final excavations
were completed, rebar and formwork were installed, and the first
concrete pour was carried out on February 17th, 2022 (Figure 4).
The retaining wall extension is 50% complete to date. Work in this
area will continue in parallel with the new reagents mixing
building foundations, followed by civil works for the concentrate
and water recovery thickeners, reagents warehouse and the filter
press building. Fabrication of structural steel and tanks is
ongoing at Seong Henng’s workshop.
Figure 4: First Concrete Pour at Flotation
Foundation is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/db3adc6e-9ec9-46e8-9e99-3b201080fad4
Other contractors working on the construction site have:
rerouted the HV power cables to the primary and secondary ball
mills, connected power and communications cables to the project
office, carried out plate bearing tests over the plant footprint,
and tested soil resistivity for the new transformer.
Transition to Flotation
Dry commissioning of the new flotation plant and
associated equipment is scheduled to start from June 1st, 2022
onwards. The CIL plant will continue operation until June 30th,
2022. Tie-in and wet commissioning of the flotation plant will
commence on July 1st, 2022 and continue to July 14th, 2022. Ore
commissioning is expected to start on July 15th, 2022. The gold
remaining in circuit will be recovered by emptying the leach and
CIL tanks of slurry and bagging the harvested carbon for subsequent
elution. The elution circuit will continue to operate for around a
month after the CIL plant shutdown.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 200
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks; other risks inherent in the mining industry and other risks
described in the management discussion and analysis of the Company
and the technical reports on the Company's projects, all of which
are available under the profile of the Company on SEDAR at
www.sedar.com. Material factors and assumptions used to develop
forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; the expected
timing and results of development and exploration activities; costs
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; exchange
rates; and all of the factors and assumptions described in the
management discussion and analysis of the Company and the technical
reports on the Company's projects, all of which are available under
the profile of the Company on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024