Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) (“Monument” or
the “Company”) today announced its annual financial results for the
year ended June 30, 2022. All amounts are in United States dollars
unless otherwise indicated (refer to www.sedar.com for full
financial results).
In fiscal 2022, with the restructured gold
focused portfolio, Monument concentrated on flotation plant
construction at the Selinsing Gold Mine with 69% completion, and
the Phase 1 and Phase 2 drilling programs at the Burnakura project
for new gold which have been completed subsequent to the fiscal
2022. The corporate development is focused on identification of
gold acquisition targets.
Cathy Zhai, the President and CEO commented: “We
are pleased to see in fiscal 2022 Murchison Project progressed
exploration as planned, Phase 1 drilling lead to the discovery of a
high-grade near surface “Junction Target” and the Phase 2 drilling
confirm extensions to known mineralization of existing resources
with high potential to enhance its production scale and
economics.”
Ms. Zhai further commented: “Selinsing flotation
plant construction in general progressed smoothly. The challenges
of the Shanghai COVID-19 lockdown and the worldwide shipping
blockage however caused delay of commissioning from June 30 to late
November 2022. The concentrate market is hot, and we have made good
progress towards an offtake arrangement. Our cash position is
adequate to complete the construction, even though Selinsing gold
production was volatile during fiscal 2022 and not able to fund
development activities.”
Fourth Quarter Highlights:
- Selinsing Sulphide Project
development continued to progress, civil work for flotation plant
foundation was completed and the long lead major items of flotation
cells, agitators, pumps and thickeners were delivered and
installed;
- Selinsing mining rates were volatile primarily due to depletion
of oxide ore transiting to sulphide production:
- 1,942 ounces (“oz”) of gold
produced (Q4 FY2021: 1,838oz);
- 450oz of gold sold for $0.85
million (Q4 FY2021: 3,473oz for $6.08 million);
- Average annual gold price realized
at $1,890/oz (Q4 FY2021: $1,812/oz);
- Cash cost per ounce sold was
$1,282/oz (Q4 FY2021: $1,386/oz);
- Gross margin decreased by 78% to
$0.27 million (Q4 FY2021: $1.27 million);
- All-in sustaining cost (“AISC”)
increased to $2,221/oz (Q4 FY2021: $1,647/oz) (section 15 “Non-IFRS
Performance Measures”).
Fiscal Year 2022
Highlights:
- Murchison Phase 2 drilling
successfully completed subsequent to the year ended June 30, 2022
confirming continuity of gold mineralization at Burnakura;
- Selinsing Sulphide Project
development 69% completion with delay in commissioning due to
Shanghai COVID-19 shutdown and shipping;
- Selinsing mining rates were
volatile primarily due to depletion of oxide ore transiting to
sulphide production:
- 7,091oz of gold produced (FY2021: 10,282oz);
- 8,016oz of gold sold for $14.44 million (FY2021: 12,850oz for
$23.24 million);
- Average annual gold price realized at $1,870/oz (FY2021:
$1,864/oz);
- Cash cost per ounce sold was $1,723/oz (FY2021:
$1,178/oz);
- Gross margin decreased by 92% to $0.63 million (FY2021: $8.10
million);
- All-in sustaining cost increased to
$2,175/oz (FY2021: $1,425/oz) (section 15 “Non-IFRS Performance
Measures”).
Fourth Quarter and Fiscal Year 2022
Production and Financial Highlights
|
Three months ended June 30, |
Year ended June 30, |
|
2022 |
2021 |
2022 |
2021 |
Production |
|
|
|
|
Ore mined (tonnes) |
91,958 |
72,074 |
355,519 |
427,528 |
Waste removed (tonnes) |
686,423 |
687,255 |
5,593,875 |
3,639,490 |
Ore processed (tonnes) |
119,409 |
94,940 |
544,003 |
579,569 |
Average mill feed grade
(g/t) |
0.95 |
0.72 |
0.69 |
0.84 |
Processing recovery rate
(%) |
55% |
64% |
63% |
61% |
Gold production(1)(oz) |
1,942 |
1,838 |
7,091 |
10,282 |
Gold sold (oz) |
450 |
3,473 |
8,016 |
12,850 |
|
|
|
|
|
Financial (in thousands of US
dollars) |
$ |
$ |
$ |
$ |
Revenue |
851 |
6,085 |
14,440 |
23,236 |
Gross margin from mining
operations |
274 |
1,270 |
629 |
8,103 |
Net income (loss) before other
items |
(342) |
(1,009) |
(5,178) |
1,696 |
Net income (loss) |
112 |
(2,702) |
(6,497) |
(99,318) |
Cash flows generated from
(used in) operations |
(2,722) |
2,208 |
(4,552) |
1,654 |
Working capital |
30,331 |
48,539 |
30,331 |
48,539 |
|
|
|
|
|
Earnings (loss) per share
before other items – basic (US$/share) |
(0.00) |
(0.00) |
(0.02) |
0.01 |
Earnings (loss) per share –
basic (US$/share) |
0.00 |
(0.01) |
(0.02) |
(0.31) |
Other |
US$/oz |
US$/oz |
US$/oz |
US$/oz |
Average realized gold price
per ounce sold(2) |
1,890 |
1,812 |
1,870 |
1,864 |
|
|
|
|
|
Cash cost per ounce(3) |
|
|
|
|
Mining |
397 |
496 |
687 |
397 |
Processing |
623 |
711 |
851 |
602 |
Royalties |
170 |
167 |
166 |
169 |
Operations, net of silver recovery |
92 |
12 |
19 |
10 |
Total cash cost per
ounce |
1,282 |
1,386 |
1,723 |
1,178 |
All-in sustaining costs per
ounce(4) |
|
|
|
|
By-product silver recovery |
7 |
1 |
1 |
1 |
Operation expenses |
0 |
119 |
6 |
46 |
Corporate expenses |
20 |
3 |
8 |
6 |
Accretion of asset retirement obligation |
93 |
9 |
19 |
10 |
Exploration and evaluation expenditures |
256 |
25 |
48 |
22 |
Sustaining capital expenditures |
563 |
104 |
370 |
162 |
Total all-in sustaining cost per ounce |
2,221 |
1,647 |
2,175 |
1,425 |
(1) Defined as good delivery gold bullion
according to London Bullion Market Association (“LBMA”), net of
gold doŕe in transit and refinery adjustment.(2) Exclude gold
prepaid delivery for comparison purposes.(3) Total cash cost
includes production costs such as mining, processing, tailing
facility maintenance and camp administration, royalties, and
operating costs such as storage, temporary mine production closure,
community development cost and property fees, net of by-product
credits. Cash cost excludes amortization, depletion, accretion
expenses, capital costs, exploration costs and corporate
administration costs.(4) All-in sustaining cost per ounce includes
total cash costs, operation expenses, and adds sustaining capital
expenditures, corporate administrative expenses for the Selinsing
Gold Mine including share-based compensation, exploration and
evaluation costs, and accretion of asset retirement obligations.
Certain other cash expenditures, including tax payments and
acquisition costs, are not included.
Fourth Quarter Results
Production Analysis
- Q4 FY2022 gold production of
1,942oz, a 6% increase as compared to 1,838oz for Q4 FY2021. This
increase resulted from a higher feed grade and more ore
processed.
- Q4 FY2022 ore processed increased
to 119,409 tonnes from 94,940 tonnes for Q4 FY2021. The increase is
due to the impact of COVID-19 related closures in Q4 FY2021 and the
operation resuming in FY2022.
- Q4 FY2022 total production costs
were $0.58 million as compared to $4.82 million for Q4 FY2021. Cash
cost per ounce decreased by 7% to $1,282/oz as compared to
$1,386/oz of Q4 FY2021. The decrease was attributable to less waste
removed, higher feed grade, more ore processed, and gold
produced.
Financial Analysis
- Q4 FY2022 gold sales generated
revenue of $0.85 million as compared to $6.08 million from Q4
FY2021. Gold sales revenue was derived from the sale of 450oz (Q4
FY2021: 2,750oz) of gold at an average realized gold price of
$1,890 per ounce (Q4 FY2021: $1,812 per ounce). There was no gold
prepaid delivery for Q4 FY2022 (Q4 FY2021: 723oz at $1,525 per
ounce).
- Q4 FY2022 mining operations before
non-cash amortization and depreciation generated a gross margin of
$0.27 million, a decrease of 78% from $1.27 million in Q4 FY2021.
The decrease in gross margin was attributable to the decrease in
gold sold offset by a higher average realized gold price.
- Cash outflow from investing
activities for Q4 FY2022 was $2.25 million (Q4 FY2021: inflow of
$28.44 million, which was mainly from the sale of the Mengapur
project of $29.16 million and the sale of 80% interest in
Tuckanarra project of $2.66 million).
Fiscal Year 2022 Results
2022 Gold Production
Production Analysis
- Gold production of 7,091oz, a 31%
decrease as compared to 10,282oz of the previous year. Gold
production for the year ended June 30, 2022 was mainly from
transitional leachable sulphide ore from Selinsing Pit 4, oxide
mineralized materials from Peranggih and old tailings materials.
This resulted in lower mill feed grades but slightly higher
recovery rates.
- 2022 mining activities delivered
355,519 tonnes of ore from Selinsing (198,689 tonnes), Buffalo Reef
(4,205 tonnes), and Peranggih (152,625 tonnes). Mining costs for
Peranggih were recorded against inventories for 152,625 tonnes
during the year, of which 147,598 tonnes were fed into the
mill.
- Ore processed decreased to 544,003
tonnes from 579,569 tonnes last year. The decrease was due to the
lack of availability of stockpiled ore. Ore stockpile has
significantly reduced mainly due to the adverse impact of the oxide
materials are being depleted and in transition to flotation
production, which is under construction. COVID-19 pandemic has not
helped in achieving the target. The Company has devoted its effort
to improve the stockpile balance.
- Total production costs were $13.81
million as compared to $15.13 million of last year. Cash cost per
ounce increased by 46% to $1,723/oz as compared to $1,178/oz of
last year. The increase was attributable to a 18% decrease in the
mill feed grade from 0.69g/t to 0.84g/t as a result of processing
significantly more leachable sulphide ore and other low recovery
ores, heavy rainfall in the mine pits, partially offset by an
increase in recovery to 62.7% (2021: 60.8%).
Financial Analysis
- Gold sales generated revenue of
$14.44 million for the year as compared to $23.24 million from last
year. Gold sales revenue was derived from the sale of 6,329oz
(2021: 10,700oz) of gold at an average realized gold price of
$1,870 per ounce (2021: $1,864 per ounce) and the delivery of
1,687oz (2021: 2,150oz) in fulfilling gold prepaid obligations at
an average London Fix PM gold price of $1,545 per ounce (2021:
$1,525 per ounce).
- Mining operations before non-cash
amortization and depreciation generated a gross margin of $0.63
million, a decrease of 92% from $8.10 million from the previous
year. The decrease in gross margin was attributable to the decrease
in gold sold offset by a higher average realized gold price.
- Cash and cash equivalents balance
as at June 30, 2022 was $21.04 million, a decrease of $17.58
million from the balance at June 30, 2021 of $38.62 million. As at
June 30, 2022, the Company had positive working capital $30.33
million (June 30, 2021: $48.54 million). The decrease in working
capital was mainly due to the capital expenditures spent on
flotation construction project and Murchison drilling
programs.
- Cash outflow from investing
activities for the year was $12.99 million (2021: inflow of $26.87
million, which was mainly from the sale of the Mengapur project of
$29.16 million and the sale of 80% interest in Tuckanarra project
of $2.66 million).
Development
Selinsing Gold Mine
At Selinsing, development work focused on
completion of the Phase 1 Sulphide Project development that
includes flotation plant construction and mine development, aimed
to produce saleable sulphide gold concentrates. The flotation plant
construction includes project management, project validation,
flotation design and engineering, procurement, construction and
commissioning. Mine development includes upgrading of tailing
storage facilities, pit push backs, river diversion, and
pre-stripping.
Procurement at Selinsing construction has
delivered and installed the flotation cells, agitators, pumps,
thickeners. A major delay was encountered from several long lead
components which were held up at the factory and at the Shanghai
international port due to Shanghai COVID-19 shutdown. Of which the
gear box and bridge assemble work have been complete and shipped to
the Selinsing site subsequent to the year end in September 2022.
However, the delivery of the fabricated concentrate filter was
further delivered for shipment and an arrival is expected in mid of
November 2022. Completion of commissioning is anticipated in late
November 2022.
At year end, 69% of the overall project had been
completed with costs incurred of $10.46 million. Construction for
project included: civil foundation work at the: flotation area,
reagent area and concentrate thickener area. Structure steel work
has been initiated and continues for the filter, water recovery
thickener, water services facilities, screening and conditioning
tower, flocculants plant, and the concentrate thickener areas are
75% completed. The 60% of the piping work has been completed and
continues to progress. The equipment installation work for
flotation cell is nearly completed, while the reagent agitator and
tank installation has been completed.
The tailing storage facility (“TSF”) upgrade
continued with the current capacity being adequate for production
until May 2023.
Murchison Gold Project
At Murchison development work focused on
identifying and testing both regional exploration targets away from
known mineralization, and extensions to existing resources, while
continuing to assess early production opportunities.
The Company continues to ensure that the plant
and other facilities are operationally ready through its care and
maintenance program to ensure efficient commissioning in the
future. Site accommodations and catering are fully functional in
readiness for the Company’s personnel and mining contractors when a
restart is approved.
Exploration
Malaysia
No significant exploration activities were
conducted at Selinsing and Buffalo Reef during the fiscal year
except for geological mapping exercise and grab sampling
collection.
During fiscal 2022, the Company continued to
place grade control drilling at Peranggih, intended to locate
mineable material to provide additional Selinsing mill feed.
Drilling at Peranggih included 1,200m over 25 holes to a maximum
depth of 70m, at 20m by 20m spacing, targeting a steeply dipping
high-grade mineralized structure. Approximately 70% of holes have
hit gold mineralization above an oxide cut-off (>0.35g/t Au) at
less than 50m below the surface, defining a mineralized zone 830m
long and 60m wide. 66 channel samples and 131 grab/float samples
were compiled, which tested extensions to known mineralization at
Peranggih and 76 grab/float samples at Selinsing.
Western Australia
In fiscal 2022, as part of a two-year
exploration program to test the potential for additional gold
discovery, the Company completed Phase 1 and Phase 2 drilling
programs. The Company tested greenfield targets and extensions to
known mineralized structures, and successfully achieved initial
objectives with the Phase 1 Junction target discovery and the Phase
2 drilling confirmation of gold mineralization extensions at depth
at the NOA group of deposits, highlighting the opportunity to grow
the Murchison Project organically.
Phase 1 drilling program included a total of 46
RC holes for 3,465m and a total of 349 AC holes were completed for
10,484m. Phase 2 drilling program included a combined 18 RC and DD
holes for a total of 5,595m. The drill programs covered the Munro
Bore Extension target, FLC2 and FLC3 prospects, newly discovered
Junction Target and NOA group.
The results from the programs continue to
support the Company’s strategy that potentially could lead to
extend the economic mineralization beyond the existing Mineral
Resource and to new discoveries within the Burnakura Project
area.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 200
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY VancouverT: +1-604-638-1661
x102rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans (“forward-looking statements”). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company’s plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks, including risks related to changes in mining license rights,
tax rates and government royalty requirements; other risks inherent
in the mining industry and other risks described in the management
discussion and analysis of the Company and the technical reports on
the Company’s projects, all of which are available under the
profile of the Company on SEDAR at www.sedar.com. Material factors
and assumptions used to develop forward-looking statements in this
news release include: expectations regarding the estimated cash
cost per ounce of gold production and the estimated cash flows
which may be generated from the operations, general economic
factors and other factors that may be beyond the control of
Monument; assumptions and expectations regarding the results of
exploration on the Company’s projects; assumptions regarding the
future price of gold of other minerals; the timing and amount of
estimated future production; the expected timing and results of
development and exploration activities; costs of future activities;
capital and operating expenditures; success of exploration
activities; mining or processing issues; exchange rates; expected
mining rights, tax rates, and government royalty requirements in
the jurisdictions in which the Company operates; and all of the
factors and assumptions described in the management discussion and
analysis of the Company and the technical reports on the Company’s
projects, all of which are available under the profile of the
Company on SEDAR at www.sedar.com. Although the Company has
attempted to identify important factors that could cause actual
results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024