Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) “Monument” or
the “Company” today announced its first quarter of fiscal 2023
production and financial results for the three months ended
September 30, 2022. All amounts are expressed in United States
dollars (“US$”) unless otherwise indicated (refer to www.sedar.com
for full financial results).
President and CEO Cathy Zhai commented, “FY 2023
will be a milestone year for Selinsing Gold Mine to initiate the
new life of mine for gold concentrate production. In the first
quarter of fiscal 2023 flotation plant construction progressed in
delivery of major components of long lead items after Shanghai city
lockdown by rescheduling vessel shipment. The new life of mine
production will commence upon completion of the flotation plant
commissioning, which is anticipated in early December 2022. At
Murchison, Phase 2 drill results were announced in the quarter that
confirmed the extension of gold mineralization, including high
grades of up to 17.8g/t gold, for more than 150m vertical depth
below the current Mineral Resource at the North of Alliance (“NOA”)
group of deposits, and exploration work focused on updating
historical data at Gabanintha to potentially improve identifying
drill targets.”
First Quarter Highlights:
- 85% progress of Selinsing Sulphide Project development
targeting completion early December 2022;
- Marketing progressing in reviewing and evaluation of quotations
from potential purchasers of concentrates;
- Selinsing production continued with volatile mining rates and a
breakeven profit margin:
- 2,066 ounces (“oz”) of gold produced (Q1 FY2022: 1,043oz);
- 400 ounces (“oz”) of gold sold for $0.71 million (Q1 FY2022:
1,423oz for $2.38 million);
- Average annual gold price realized at $1,772oz (Q1 FY2022:
$1,829/oz);
- Cash cost per ounce sold was $1,622/oz (Q1 FY2022:
$1,430/oz);
- Gross margin decreased by 83% to $0.06 million (Q1 FY2022:
$0.35 million);
- All-in sustaining cost (“AISC”) increased to $2,677/oz (Q1
FY2022: $2,052/oz)
First Quarter Production and Financial
Highlights
|
Three months ended September 30, |
|
2022 |
2021 |
Production |
|
|
Ore mined (t*) |
107,392 |
74,972 |
Ore processed (t) |
132,447 |
156,611 |
Average mill feed grade
(g/t*) |
1.03 |
0.54 |
Processing recovery rate
(%) |
46% |
65% |
Gold recovery (oz) |
2,032 |
1,777 |
Gold production (1) (oz) |
2,066 |
1,043 |
Gold sold (oz) |
400 |
1,423 |
|
|
|
Financial (expressed in
thousands of US$) |
$ |
$ |
Revenue |
709 |
2,383 |
Gross margin from mining
operations |
60 |
348 |
Loss before other items |
(703) |
(755) |
Net loss |
(289) |
(1,267) |
Cash flows provided from (used
in) operations |
(654) |
23 |
Working capital |
25,705 |
44,532 |
Loss per share - basic and
diluted (US$/share) |
(0.00) |
(0.00) |
*grams/tonne (“g/t”); tonnes (“t”) |
|
|
|
|
|
|
|
Three months ended September 30, |
|
2022 |
2021 |
|
|
|
Other |
US$/oz |
US$/oz |
Average realized gold price
per ounce sold(2) |
1,772 |
1,829 |
|
|
|
Cash cost per ounce (3) |
|
|
Mining |
632 |
522 |
Processing |
770 |
720 |
Royalties |
183 |
168 |
Operations, net of silver
recovery |
37 |
20 |
Total cash cost per
ounce |
1,622 |
1,430 |
All-in sustaining costs per
ounce (4) |
|
|
By-product silver
recovery |
5 |
1 |
Operation expenses |
- |
34 |
Corporate expenses |
65 |
4 |
Accretion of asset retirement
obligation |
115 |
22 |
Exploration and evaluation
expenditures |
442 |
11 |
Sustaining capital
expenditures |
428 |
550 |
Total all-in sustaining costs per ounce |
2,677 |
2,052 |
(1) |
Defined as good delivery gold bullion according to London Bullion
Market Association (“LBMA”), net of gold doŕe in transit and
refinery adjustment. |
(2) |
Monument realized 1,772US$/oz for the three months ended September
30, 2022. |
(3) |
Total cash cost per ounce includes production costs such as mining,
processing, tailing facility maintenance and camp administration,
royalties and operating costs such as storage, temporary mine
production closure, community development cost and property fees,
net of by-product credits. Cash cost excludes amortization,
depletion, accretion expenses, idle production costs, capital
costs, exploration costs and corporate administration costs.
Readers should refer to section 15 “Non-GAAP Performance
Measures”. |
(4) |
All-in sustaining cost per ounce includes total cash costs and adds
sustaining capital expenditures, corporate administrative expenses
for the Selinsing Gold Mine including share-based compensation,
exploration and evaluation costs, and accretion of asset retirement
obligations. Certain other cash expenditures, including tax
payments and acquisition costs, are not included. Readers should
refer to section 15 “Non-GAAP Performance Measures”. |
Q1 FY2023 Production
Analysis
- Q1 FY2023 gold
production was 2,066oz, a 98% increase as compared to 1,043oz for
Q1 FY2022. The increase mainly was from higher feed grade.
- Q1 FY2023 ore
processed decreased to 132,447t from 156,611t for Q1 FY2022. The
decreased mill feed was mainly due to less oxide ore and old
tailings being fed into plant.
- Average mill
feed grade was higher this quarter (1.03g/t Au for Q1FY2023) as
compared to the same period last year (0.54g/t Au for Q1 FY2022)
due to higher grade ore from Selinsing and Buffalo Reef than
Peranggih mineralized materials. The processing recovery rate
decreased to 46.2% for Q1FY2023 as compared to 65.0% in Q1 FY2022
was mainly due to the lower gold recovery from Selinsing leachable
sulphide ore processed.
- Q1 FY2023 cash
cost per ounce increased by 13% to $1,622/oz from $1,430/oz for Q1
FY2022. This increase was primarily due to harder and lower
recovery sulphide materials processed offset by a significant
increase in the mill feed grade from 0.54g/t Au to 1.03g/t Au.
Q1 FY2023 Financial Analysis
- Q1 FY2023 gold
sales generated revenue was $0.71 million as compared to $2.38
million from Q1 FY2022. Gold sales revenue was derived from the
sale of 400oz (Q1 FY2022: 1,423oz) of gold at an average realized
gold price of $1,772 per ounce (Q1 FY2022: $1,829 per ounce) and
the delivery of nil (Q1 FY2022: 723 oz at $1,525 per ounce gold
equivalent) in fulfilling gold prepaid obligations.
- Q1 FY2023 total
production costs decreased by 68% to $0.65 million as compared to
$2.04 million from Q1 FY2022. Cash cost per ounce increased by 13%
to $1,622/oz as compared to $1,430/oz of the same period last year.
The increase was attributable to a 29% decrease in the gold
recovery from 65.0% to 46.2% but an increase in mill feed grade to
1.03g/t (Q1 FY2022: 0.54g/t) as a result of processing harder
leachable sulphide material.
- Gross margin for
Q1 FY2023 was $0.06 million before operation expenses and non-cash
amortization and accretion. That represented an 83% decrease as
compared to $0.35 million from Q1 FY2022. The decrease in gross
margin was attributable to lower recovery ore processed, much lower
volume of gold sold, and increased cash costs.
- Net loss for Q1
FY2023 was $0.29 million, or ($0.00) per share as compared to net
loss of $1.27 million or ($0.00) per share from Q1 FY2022. The net
loss was mainly caused by lower operating margins.
- Cash and cash
equivalents balance as at September 30, 2022 was $16.15 million, a
decrease of $4.89 million from the balance at June 30, 2022 of
$21.04 million. As at September 30, 2022, the Company had positive
working capital of $25.71 million as compared to that at June 30,
2022 of $30.33 million.
Development
Selinsing Gold Mine
At Selinsing, development work included the
continuing of the flotation plant construction, mine development,
and flotation testwork on stockpiled transition ore samples.
Overall, Selinsing Sulphide Project Development was 85% completed
as of September 30, 2022 including: project management, project
validation, flotation design and engineering, procurement,
construction and commissioning. Mine development includes upgrading
of tailing storage facilities, pit push backs, river diversion, and
pre-stripping.
The flotation plant detail engineering design
work has been completed and shop detailing design of earthing and
lightning conductor work for power supply upgrade is underway.
Procurement of all major and long lead equipment has been
completed, with the delivery of the fabricated concentrate filter
press arriving in mid-November, after the end of the quarter.
As of September 30, 2022, the plant construction
work has been largely completed with completion of foundation work
at flotation area, reagents area, concentrate thickener area and
pipe rack. Other foundation work at filter press building, water
recovery thickener and flocculants plant area were completed. After
the delivery of concentrate filter press, assembly work progressed
immediately. Cabling and piping work and mechanical equipment
installation were in progress during the quarter.
A revised environmental management plan that
includes the sulphide processing was submitted to the Department of
Environment (“DOE”) in fiscal year 2022 and was approved on
September 23, 2022.
The production of flotation concentrate is
expected to commence after completion of commissioning, anticipated
in early December 2022.
Mine development was completed, with pre-stripping work finished
during the quarter. The Tailing Storage Facility (“TSF”) expansion
development to 540m RL level will continue after commencement of
production.
Flotation tests were carried out on samples of
old stockpiles of transition ore that will be processed during
commissioning and early ramp-up. The flotation tailings of
transition ore will be stored for future Carbon-in-Leach (“CIL”)
processing. Several flotation pilot test runs were conducted which
further supports the previous observation and test result; a mill
feed flotation test was carried out during this quarter which
indicated the good flotation performance of above 90% of rougher
recoveries.
Murchison Gold Project
At Murchison, no drilling was carried out during
the first quarter of fiscal year 2023 in order to dedicate
resources to complete the Selinsing flotation construction and
commence production, the Company focused on updating Gabanintha
data that might improve identifying drill targets. The Company
continued to maintain the plant and other facilities, so they are
operationally ready for efficient commissioning when production is
restarted. Site accommodation and catering facilities are fully
functional for administrative, exploration and mining
activities.
Gross Revenue Royalty from Fortress
During the first quarter of FY2023, the Company
has begun earning royalties from Fortress Minerals Limited
(“Fortress”) on the Mengapur Project. Pursuant to the terms of the
Royalty Agreement entered January 2021 with Fortress, the Company
earned the first royalty of 1.25% against $1.2 million declared by
Fortress.
Exploration Progress
Malaysia
During the first quarter of FY2023, to sustain
the continuity of the oxide plant production, a total of 270m RC
drilling over six holes was drilled at Selinsing Pit 4 and Pit 6. A
total of 10 batches of RC samples comprising 317 samples including
QAQC control samples were dispatched to the assay laboratory. All
samples received the assay results. The drilling results at
Selinsing Pit 6 confirmed the continuation of the mineralization to
the down dip direction and the drilling results at Pit 4 confirmed
that the high-grade zone is extended to the south direction,
Carbon-in-Leach (“CIL”) recoveries were generally low, but the
laboratory flotation response was highly satisfactory with over 90%
recovery reported. The additional ore mined at Selinsing Pit 4 and
Pit 6 will be processed in the flotation plant that is planned for
commissioning in December 2022.
During the first quarter of FY2023, to explore
near surface oxide mineralisation, a total of 37 and 134 channel
samples were collected at Buffalo Reef C3 pit and the south wall of
C2 pit respectively. Assay results were received, and no
significant result was reported. Further a total of 20 grab samples
of the alluvial material was collected at a diverted Buffalo Reef
C3 creek, near the known high-grade mineralisation. Assay results
reported highest Au value of 0.89g/t and 12 samples were reported
with Au above 0.20g/t with an average grade of 0.45g/t.
The areas where the materials were considered
economically mineable through the above drilling were considered in
the mining plan
Western Australia
During the first quarter of FY2023, the Company
received and analyzed the diamond drilling results of Phase 2 that
confirmed the extension of gold mineralization, including high
grades of up to 17.8g/t gold, for more than 150m
vertical depth below the current Mineral Resource at the NOA group
of deposits. Fiscal 2023 started with a focus on updating
Gabanintha historical data to improve identifying drill targets. A
full review of all historical maps with reports is ongoing for the
Gabanintha project.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE: D7Q1)
is an established Canadian gold producer that owns and operates the
Selinsing Gold Mine in Malaysia. Its experienced management team is
committed to growth and is also advancing the Murchison Gold
Projects comprising Burnakura, Gabanintha and Tuckanarra JV (20%
interest) in the Murchison area of Western Australia. The Company
employs approximately 200 people in both regions and is committed
to the highest standards of environmental management, social
responsibility, and health and safety for its employees and
neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks; other risks inherent in the mining industry and other risks
described in the management discussion and analysis of the Company
and the technical reports on the Company's projects, all of which
are available under the profile of the Company on SEDAR at
www.sedar.com. Material factors and assumptions used to develop
forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; the expected
timing and results of development and exploration activities; costs
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; exchange
rates; and all of the factors and assumptions described in the
management discussion and analysis of the Company and the technical
reports on the Company's projects, all of which are available under
the profile of the Company on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024