Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or
the "Company") is pleased to update the progress at the Selinsing
Sulphide Project. With the completion of the flotation plant
construction at the Selinsing Gold Mine in Malaysia, the sulphide
treatment plant has been placed into commissioning after the oxide
plant production ceased in mid-November 2022. The first gold
concentrate was filtered on December 27, 2022 and the ramp up
period commenced in January 2023.
President and CEO Cathy Zhai commented, “During
commissioning we have identified some bottlenecks and are working
with Mincore to fix them. Up to date the flotation plant has
delivered saleable concentrate of approximately 1,707 dry tonnes at
35.12 g/t Au with gold content of 1,928 troy ounces. In the
meantime, with unexpected heavy rainfall in the dry season, we also
are focused on acceleration of the mining rates to fulfill
commercial production requirement.”
Figure 1. Flotation
Plant
Figure 2. Plant Inspection
Flotation Commissioning
Progress
The commissioning stages include: (1)
preparation - to confirm the completeness of construction and
deliver the commissioning plan for test work, (2) dry commissioning
- to test if mechanical, electrical and electronic equipment and
components in the circuit are installed correctly and completely
according to designed protocols and their availability, (3) wet
commissioning - to test circulation of water through the flotation
circuit and the plant as a whole ensure the water and pumping
system up running for the designed purpose;(4) ore commissioning -
to start-up with first fill to verify flotation performance and
tune it to meet the designed performance in connection with front
end circuit, this includes but not limited to the control level,
the flows in relation to each components in the circuit and to
overall treatment process, the water balance and mass balance.
During the commissioning process the bottlenecks will be identified
and corrected.
After the start-up ore commissioning, a ramp up
period will tune the plant under increased mill feed and required
conditions until commercial production is reached. The management
and board would consider the commercial production is reached when
the flotation plant is running for 30 days continuously with
production at 85% to 90% designed capacity.
Progress Highlights
- Construction of the flotation plant
completed except weighbridge and the concentrate storage shed.
- Dry and wet commissioning completed
on flotation cells, concentrate and water recovery thickeners,
reagents mixing and storage, blowers, compressor and filter press
plant.
- Ore commissioning started on
December 15th,2022 with assistance from various consulting
engineers: Mincore (engineering design), Metso-Outotec
(thickeners), BGRIMM (flotation cells), Powerwell (MCC), Enertech
(PLC and SCADA control system), McLanahan (filter press) and ISI
Control (instrumentation control).
- Ongoing improvements to flotation
circuit, correcting shortfalls identified during ore commissioning
period.
- Flotation plant currently operating
at 90% capacity and expected ramp-up to design capacity of 119 tph
in March 2023.
- As of February 22nd, 2023, a total
of 1,707 dry metric tonnes of gold concentrate have been produced
with an average gold grade of 35.12 g/t Au (1,928 troy
ounces).
Figure 3: Operating Scada
System
Figure 4: Concentrate Filter Cake Stockpile
Commissioning Technical Findings and
Ramp up
As of February 22, 2023, a total of 1,707 tonnes
of flotation concentrate have been produced at an average grade of
35.12 g/t Au. The flotation plant is currently operating at a mill
feed rate of around 120 wet tonnes / 107 dry tonnes per hour or
around 90% of design capacity. The mill feed rate will be increased
over the next month with the aim of achieving and maintaining the
design capacity of 119 tph by the end of March
2023.
Some bottlenecks were identified during ore
commissioning period that took longer time than expected, mainly
caused by design deficiencies. While temporary solutions are in
place to tune the plant to reach designed protocols and production
level, actions have been undertaken to receive and review redesign
from Mincore.
Both the flotation concentrate and the water
recovery (flotation tailings) thickeners were successfully
commissioned. The performance was compromised however by design
deficiencies in relation to flotation tailings management; a
stilling well was installed that stabilized the tailings pump
operation as a temporary solution; the revised design for a
tailings hopper sent by Mincore is currently under review.
The flotation concentrate pipeline and launder
were found to be undersized; a new pipeline will be installed and
new launder fabricated once the design is received. The concentrate
thickener underflow pump has at times struggled to deliver
concentrate to the filter press surge tank and modifications to
both the pump suction and delivery lines are planned. The
concentrate thickener overflow delivery line was undersized; an
additional bigger diameter pipeline was installed as an interim
solution; bigger pumps and pipelines will be installed.
The concentrate filter press has been
successfully commissioned and initial filter cake containing around
20% moisture has been produced. Filter press commissioning was
assisted by the manufacturer McLanahan who had direct on-line
access to the control screen. Minor adjustments have been made to
the automatic control system in an effort to lower the moisture
level, this has been helped to some extent by coarsening the grind
size and reducing the slimes content of the flotation
concentrate.
In addition to the flotation plant construction,
most ancillary buildings have been completed apart from the final
concentrate shed, due to start in March 2023. Mechanical
installation has been completed except for the weighbridge, which
is ongoing, and the bagging system that has yet to be delivered.
Power and instrumentation cabling have all been installed apart
from that for the concentrate shed, the weighbridge and the bagging
system.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 200
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks; other risks inherent in the mining industry and other risks
described in the management discussion and analysis of the Company
and the technical reports on the Company's projects, all of which
are available under the profile of the Company on SEDAR at
www.sedar.com. Material factors and assumptions used to develop
forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; the expected
timing and results of development and exploration activities; costs
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; exchange
rates; and all of the factors and assumptions described in the
management discussion and analysis of the Company and the technical
reports on the Company's projects, all of which are available under
the profile of the Company on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/4ee45702-71d1-4432-af3d-ad12b70ff62f
https://www.globenewswire.com/NewsRoom/AttachmentNg/32add158-50a1-4dc0-8823-c8fbef7afea2
https://www.globenewswire.com/NewsRoom/AttachmentNg/78a97e38-02f1-46fc-ade2-66466fc9ad93
https://www.globenewswire.com/NewsRoom/AttachmentNg/c8c740c4-fd3e-4aa5-a23f-81c4ca72cfb4
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024