Southstone Reports Continued Recovery of High-Quality Diamonds from Oena
October 31 2019 - 12:12PM
Southstone Minerals Limited (“Southstone” or the
“Company”) (TSX.V – SML) is pleased to provide an
operational and production update for the Oena Diamond Mine
(“Oena”). During the production period, 8 August to 16 October
2019, a total of 742 carats were produced, placed on tender and
sold with an average price of US1,495 per carat (USD $1,110,164 in
sales).
Southstone maintains its strategic focus on its
diamond operations, in particular the Company’s flagship asset the
Oena Diamond Mine, located in the Northern Cape, South Africa,
which produces very high-quality diamonds. There are currently two
mining contractors on site operating eight (8) pan plants which
process both run of mine (“ROM”) and pan tailings and bantam
material (“Tailings”) and one Bourevestnik (“BVX”) unit is used for
diamond recovery.
The two mining contractors continue their
activities at Oena as per a Contract Mining and Diamond Recovery
Agreement (see news releases dated 2 May 2018, 10 October 2018 and
16 November 2017) and a Joint Operating Agreement (see news release
date 17 June 2019).
ON BEHALF OF THE BOARD OF DIRECTORS
OFSOUTHSTONE MINERALS LIMITED
Mr. Samer Khalaf Chief Executive
OfficerSouthstone Minerals Limitedinfo@southastoneminerals.com
Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Forward-Looking Statement
Certain information set forth in this news
release contains “forward-looking statements” and “forward-looking
information” under applicable securities laws. Except for
statements of historical fact, certain information contained herein
constitutes forward-looking statements, which include management’s
assessment of future plans and operations and are based on current
internal expectations, estimates, projections, assumptions and
beliefs, which may prove to be incorrect. Some of the
forward-looking statements may be identified by words such as
“forecasts”, estimates”, “expects” “anticipates”, “believes”,
“projects”, “plans”, “outlook”, “capacity” and similar expressions.
These statements are not guarantees of future performance and undue
reliance should not be placed on them.
Such forward-looking statements necessarily
involve known and unknown risks and uncertainties, which may cause
the Company’s actual performance and financial results in future
periods to differ materially from any projections of future
performance or results expressed or implied by such forward-looking
statements. These risks and uncertainties include, but are not
limited to statements with respect to the estimation of mineral
resources; the realization of mineral resource estimates;
anticipated future production, capital and operating costs; cash
flows and mine life; potential size of a mineralized zone;
potential expansion of mineralization; potential types of mining
operations; permitting timelines; government regulation of
exploration and mining operations; risks that the presence of
diamond deposits mentioned nearby the Company’s property are not
indicative of the diamond mineralization on the Company’s property,
the supply and demand for, deliveries of and the level and
volatility of prices of rough diamonds, risks that the actual
revenues will be less than projected; risks that the target
production for the existing mining contracts will be less than
projected or expected; risks that production will not commence as
projected due to delay or inability to receive governmental
approval of the Company’s acquisition or the timely completion of
an NI43-101 report; technical problems; inability of management to
secure sales or third party purchase contracts; currency and
interest rate fluctuations; foreign exchange fluctuations and
foreign operations; various events which could disrupt operations,
including labor stoppages and severe weather conditions; and
management’s ability to anticipate and manage the foregoing factors
and risks.
The forward-looking statements and information
contained in this news release are based on certain assumptions
regarding, among other things, future prices for coal and diamonds;
future currency and exchange rates; the Company’s ability to
generate sufficient cash flow from operations and access capital
markets to meet its future obligations; coal consumption levels;
and the Company’s ability to retain qualified staff and equipment
in a cost-efficient manner to meet its demand. There can be no
assurance that forward-looking statements will prove to be
accurate, as actual results and future events could differ
materially from those anticipated in such statements. The reader is
cautioned not to place undue reliance on forward-looking
statements. The Company does not undertake to update any of the
forward-looking statements contained in this news release unless
required by law. The statements as to the Company’s capacity to
achieve revenue are no assurance that it will achieve these levels
of revenue.