Orocobre Limited (TSX:ORL)(ASX:ORE) - 

HIGHLIGHTS AND SIGNIFICANT DEVELOPMENTS

Salar de Olaroz Lithium-Potash Project:



--  Construction of the project is proceeding on time and within budget. 
    
--  A total of USD$87m has been spent or committed via executed contracts in
    the construction project to date. 
    
--  A large function involving dignitaries, government, company staff, ten
    local community representatives and members of the business community
    was held on Thursday 14 March at the Salar de Olaroz to celebrate the
    official opening of the Olaroz project construction. Approximately 500
    people attended. 



Corporate



--  The Company announced on 21 January the appointment of Mr Neil Kaplan to
    the position of Chief Financial Officer and Mr David Hall to the
    position of Business Development Manager. 

--  Cash Position of A$12.3 million at the end of the quarter. 



Salar De Olaroz Lithium-Potash Project 

The Olaroz Project is Orocobre's flagship project located in Jujuy province of
Argentina. Together with partners, Toyota Tsusho Corporation ("TTC") and Jujuy
Energia y Mineria Sociedad del Estado ("JEMSE"), Orocobre is building the first
large scale "green fields" lithium brine project in approximately 20 years. The
project has a budgeted construction cost of US$229m and has a design capacity of
17,500tpa of battery grade lithium carbonate. Financing has been completed with
the partners contributing US$82.8m. A low cost debt facility for up to US$192m
has been arranged with Mizuho Corporate Bank. 


The Olaroz Project joint venture is operated through Argentine subsidiary, Sales
de Jujuy S.A. ('SDJ SA"). The effective Olaroz Project equity interest is
Orocobre 66.5%, TTC 25.0% and JEMSE 8.5%. 


Salar de Olaroz Construction Update 

Construction of the Olaroz lithium project officially began on 21 November,
2012. Progress has been swift due in a large part to the preparation and
planning that took place in the preceding year. Sinclair Knight Merz, with the
assistance of INFA, a well-respected Argentine engineering group, completed
detailed engineering for all areas of the operation, including brine extraction,
transport and evaporation, the lithium carbonate plant and key areas of the
re-purification and micronizing circuits. The procurement process was also well
advanced with all main suppliers identified and with many construction and
supply contracts at an advanced stage of negotiation or ready for awarding by
the construction commencement date. 


In addition, prior to official construction start, various aspects of site
preparation had been advanced, including the drilling of fresh water bores and
pumping station and the time consuming removal of scrubby vegetation, "tolar",
from the area of the evaporation ponds prior to earth moving. This includes the
earth moving contracts for the construction of the 4.2 square kilometres of
evaporation ponds and road construction for the bore field access road across
the salt lake (which will allow production bores to be drilled), the drilling
contract for sixteen 200m production bores, purchase of 37km of pipeline for gas
supply, and the establishment of the construction camp, fuel and water supply.
All major contracts awarded and executed to this point have been on or under
budget.


Since the start of official construction significant progress has been made on
site as follows:




--  The establishment of the construction camp at Olaroz, and the renting of
    supplementary accommodation at the nearby town of Susques for first
    stage construction crews 
--  Mobilization of earth moving equipment and commencement of works 
--  The clearing of tolar over the majority of the evaporation pond area
    (4.2 sq km) and the commencement of earth works for evaporation pond
    construction. 
--  Establishment of a long term water supply to be used both for both
    domestic and construction purposes 
--  Establishment of fuel supply/storage and telecommunications 
--  The continuing construction of the access roads on the salar to the bore
    field area. 



The following tasks have been completed to date:



--  Earthworks and platform construction for the camp, customs yard, lime
    plant and effluent treatment plant 
--  Fencing for the customs yard 
--  Vegetation removal at 5A and 5B evaporation ponds 
--  Aquaduct pipe manufacturing 
--  Dining area and labour bedroom modules 
--  Sewage treatment plant construction 
--  Lime plant conveyor construction 
--  Concrete supplier mobilization 
--  Concrete Plant installation 
--  Contractors camp relocation 
--  Sewage treatment plant construction  



The following tasks are currently in progress:



--  Manufacturing of the worker's accommodation and dining pavilions 
--  Manufacturing of the lime plant conveyor belt 
--  Manufacturing of the ball mill for the lime plant 
--  Installation of the camp effluent plant 
--  Erection of the water pumping station equipment 
--  Construction of evaporation ponds 
--  Road and drilling platform construction on the salar 
--  Manufacturing of lime plant silo and tanks 
--  Equipment and mechanical installation at pumping station and water
    intake 
--  Tola Vegetation Removal and recycling at the pond area 
--  Lime plant silos, tanks and other facilities construction 
--  Road and platform construction on the salar 
--  Evaporation ponds construction 
--  Production wells drilling 
--  Grounding and concrete foundations for Lime Plant 
--  Aqueduct construction 
--  Gas Pipeline construction 
--  Brine pipeline construction 
--  Protection channels construction 
--  Camp modules installation 
--  Warehouse Area fence construction 



Approximately $87m of the US$229m capital budget has been committed or spent and
all major contracts awarded to this point remain on, or under, budget. 


The project implementation is through EPCM (Engineering, Procurement and
Construction Management) with a high proportion of local involvement through
construction and supply contracts and local employment. The unique community and
shared value policy continues as a key success factor, training local people
with supervision by high quality experienced professionals.


Celebration of the Official Opening of Olaroz Construction

A large function involving dignitaries, government, company staff, ten local
community representatives and members of the business community was held on
Thursday 14 March at the Salar de Olaroz to celebrate the official opening of
the Olaroz project construction. Approximately 500 people attended.


The ceremony was attended by dignitaries Amado Bodou, Vice-President of
Argentina; Eduardo Fellner, Governor of the Province of Jujuy; Hector Luzco,
Susques Municipal Commissioner; Misashi Mizukami, Japan's Ambassador to
Argentina and company representatives, James Calaway, Chairman; Richard Seville,
Managing Director; Federico Nicholson, Director; Jose De Castro Alem, Group
General Manager.


Borax Argentina 

Borax Argentina has extensive operations and has a fifty year production history
producing borax chemicals, boric acid and boron minerals. Production currently
comes from three principal mines at Tincalayu, Sijes and Porvenir with
concentrators at the first two locations and a chemicals plant at Campo Quijano
producing refined products.  


There are historical estimates on the mineralisation at these mines and at two
undeveloped deposits. These form the basis for developing plans for the
business. 


Operations 

The Borax Argentina operation performed as planned and expected over the
quarter. At Tincalayu, 6,615 tonnes of tincal mineralisation was mined and
14,430 tonnes of hydroboracite, ulexite and colemanite mineralisation was mined
at Sijes. Porvenir has been in a planned shut down this quarter.  


Approximately 9,182 tonnes of combined products were sold, in line with budget
although prices received were lower than expected due to generally softer market
conditions. 


During the quarter, work progressed in the programmes to convert some of the
historical estimates to JORC compliant resources. Also during the quarter a
number of projects were progressed to improve operations and reduce unit costs.


New developments - Borax Argentina Develops Nuclear Grade Boric Acid 

On 20 March the Company announced the development of a new chemical product by
Borax Argentina. 


In early March Borax Argentina SA made the first shipment of Boric Acid HPN
(High Purity Nuclear) Grade to a customer in Brazil. Boric Acid HPN is a new
refined chemical product developed by Borax Argentina over the last six months
with characteristics of high purity (greater than 99.9%) and low levels of key
impurities such as iron, sodium, chlorine, sulphur. Heavy metal levels are less
than one part per million. The high boric acid content and low impurity levels
makes the product suitable for use in nuclear power plants. Boric acid is used
in nuclear power plants to slow down the rate at which fission is occurring.  


The development of this new product reinforces the inherent flexibility in the
Borax Argentina operation and highlights the ability of the business to produce
new specialist high specification products for high value niche markets. Boric
Acid HPN will form an integral part of the product portfolio as Borax Argentina
becomes more geographically diverse by growing its presence in key international
markets. 


This follows on from the recent development of a high grade hydroboracite
product for the agriculture market. 


Corporate

New Executive Appointments

On 21 January, 2013 the Company announced the appointment of Mr Neil Kaplan to
the position of Chief Financial Officer and Mr David Hall to the position of
Business Development Manager.


Neil Kaplan brings a wealth of knowledge to the Company with over 20 years of
experience in managerial and finance positions obtained on four different
continents. Neil's experience in the resources sector was obtained working in
executive financial roles for Glencore International and formerly listed
Coalcorp Mining, both based in Colombia.


David Hall has extensive business management, market development, marketing and
logistics experience in domestic and international chemical and industrial
minerals markets across a wide range of products and geographies. David served
for 19 years with ICI Australia and Orica Australia in a number of roles in both
Brisbane and Melbourne and more recently two years with Queensland Magnesia.


Canadian Reporting Update 

Orocobre Limited (the Company) announced on 21 March 2013 that the company is
now a "designated foreign issuer" pursuant to National Instrument 71-102 -
Continuous Disclosure and Other Exemptions Relating to Foreign Issuers ("NI
71-102") and will no longer report under National Instrument 51-102 - Continuous
Disclosure Obligations ("NI 51-102") which would have required the company to
prepare and file continuous disclosure documents in the format as required under
the relevant Canadian regulatory requirements.


As a "designated foreign issuer", the Company will satisfy its Canadian
securities legislation requirements relating to continuous disclosure by
complying with the disclosure requirements of Australia and will do so for the
remainder of the financial year and thereafter. Under the disclosure
requirements of Australia, the Company will file interim six-month and annual
financial results within the time limits prescribed by Australia securities
legislation and the Australian Securities Exchange Listing Rules. The Company
will not prepare and file interim and annual management discussion and analysis
as it is not required to do so under the disclosure requirements of Australia.


As a "designated foreign issuer", the Company will also satisfy its other
Canadian continuous disclosure requirements by complying with the disclosure
requirements of Australia as permitted by NI 71-102. This Press Release was
lodged in Canada by the Company at www sedar.com. The Company is also releasing
the Press Release in Australia for the purpose of facilitating equal
dissemination of information in the Canadian and Australian markets and, to the
extent necessary, to meet its continuous disclosure obligations. 


Cash Position 

At the end of the quarter, the company had a cash position of A$12.3 million. 

The final fund transfer to cover the Jujuy Energia y Minera Sociedad del Estado
(JEMSE) equity component in the Olaroz project will occur in the Apr-Jun 2013
quarter. This is designated as a loan in the cash flow statement and will be
repaid from dividend income. The terms of the agreement with JEMSE are that it
has been granted an 8.5% equity interest in the Olaroz project. JEMSE's share of
the construction financing will be loaned by Orocobre and repayable out of 33.3%
of dividends received by JEMSE.


About Orocobre Limited 

Orocobre Limited is listed on the Australian Securities Exchange and Toronto
Stock Exchange (ASX:ORE)(TSX:ORL), and is building a substantial
Argentinian-based industrial minerals company through the construction and
operation of its portfolio of lithium, potash and boron projects and facilities
in the Puna region of northern Argentina. The Company is building in partnership
with Toyota Tsusho Corporation the first large-scale, de-novo brine based
lithium project in 20 years at its flagship Salar de Olaroz resource, with
projected production of 17,500 tonnes per annum of low-cost battery grade
lithium carbonate scheduled to commence in Q2 2014. The Company also wholly-owns
Borax Argentina, an important regional borate producer. Orocobre has recently
been included in the S&P/ASX 300 Index. For further information, please visit
www.orocobre.com.


Technical Information, Competent Persons' and Qualified Persons Statements 

The information in this report that relates to Exploration Results or Mineral
Resources is based on information prepared by, or under the supervision of Mr.
Richard Seville who is a member of the Australasian Institute of Mining &
Metallurgy. Mr. Seville is an executive director of Orocobre Ltd and has
sufficient experience which is relevant to the style of mineralisation and type
of deposit under consideration and to the activity which they are undertaking to
qualify as Competent Persons as defined in the 2004 Edition of the 'Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'.
Mr. Seville consents to the inclusion in this announcement of the matters based
on his information in the form and context in which it appears. 


Additional information relating to the Company's projects is available in
"Technical Report - Salar de Olaroz Lithium-Potash Project, Argentina" dated May
30, 2011, (the Olaroz Report), the "Technical Report - Salinas Grandes Project"
dated April 30, 2010 and the "Technical Report - Salar de Cauchari Project,
Argentina" dated April 30, 2010, respectively, which have each been prepared by
John Houston, Consulting Hydrogeologist, together with, in the case of the
Olaroz Report, Mike Gunn, Consulting Processing Engineer, in accordance with NI
43-101. 


Caution Regarding Forward-Looking Information 

This news release contains "forward-looking information" within the meaning of
applicable securities legislation. Forward-looking information contained in this
release includes, but is not limited to, construction at the Olaroz Project and
the timing thereof, the commencement of commercial production at the Olaroz
Project and the timing thereof, the projected production of lithium carbonate at
the Olaroz Project and the expected brine cost and grade at the Olaroz Project. 


Such forward-looking information is subject to known and unknown risks,
uncertainties and other factors that may cause actual results to be materially
different from those expressed or implied by such forward looking information,
including but not limited to the risk of further changes in government
regulations, policies or legislation; the possibility that required concessions
may not be obtained, or may be obtained only on terms and conditions that are
materially worse than anticipated; the risk that the conditions precedent to
draw down the project financing with Mizuho Corporate Bank will not be met; that
further funding may be required, but unavailable, for the ongoing development of
the Company's projects; fluctuations or decreases in commodity prices;
uncertainty in the estimation, economic viability, recoverability and processing
of mineral resources; risks associated with weather patterns and impact on
production rate; risks associated with construction and development of the
Olaroz Project; unexpected capital or operating cost increases; uncertainty of
meeting anticipated program milestones at the Olaroz Project; general risks
associated with the feasibility and development of the Olaroz Project; as well
as those factors disclosed in the Company's Annual Information Form for the year
ended June 30, 2012 filed at www.sedar.com. 


The Company believes that the assumptions and expectations reflected in such
forward-looking information are reasonable. Assumptions have been made
regarding, among other things: the timely receipt of required approvals and
completion of agreements on reasonable terms and conditions; the ability of the
Company to obtain financing as and when required and on reasonable terms and
conditions; the prices of lithium and potash; and the ability of the Company to
operate in a safe, efficient and effective manner. Readers are cautioned that
the foregoing list is not exhaustive of all factors and assumptions which may
have been used. There can be no assurance that forward-looking information will
prove to be accurate, as actual results and future events could differ
materially from those anticipated in such information. Accordingly, readers
should not place undue reliance on forward-looking information. The Company does
not undertake to update any forward-looking information, except in accordance
with applicable securities laws.


Not For Release in US

This announcement has been prepared for publication in Australia and may not be
released in the U.S. This announcement does not constitute an offer of
securities for sale in any jurisdiction, including the United States, and any
securities described in this announcement may not be offered or sold in the
United States absent registration or an exemption from registration under the
United States Securities Act of 1933, as amended. Any public offering of
securities to be made in the United States will be made by means of a prospectus
that may be obtained from the issuer and that will contain detailed information
about the company and management, as well as financial statements.


ABN 31 112 589 910

FOR FURTHER INFORMATION PLEASE CONTACT: 
Orocobre Limited
David Hall
Business Development Manager
M: + 61 407 845 052
dhall@orocobre.com


Orocobre Limited
James Calaway
Chairman
M: + 1 (713) 818 1457
jcalaway@orocobre.com
www.orocobre.com

Tathacus Resources Ltd (TSXV:TTC)
Historical Stock Chart
From Oct 2024 to Nov 2024 Click Here for more Tathacus Resources Ltd Charts.
Tathacus Resources Ltd (TSXV:TTC)
Historical Stock Chart
From Nov 2023 to Nov 2024 Click Here for more Tathacus Resources Ltd Charts.