13 December 2024
Tiris Uranium Project -
Alternative Production Targets provide growth opportunities for
Aura
|
Aura has undertaken an assessment of
the opportunities for future capacity expansion at the Tiris
Uranium Project in Mauritania utilising inputs from the September
2024 Production Target Update[1]
and the recently expanded 91.3Mlbs
U3O8 Mineral Resource[2].
The 11 September 2024 Production
Target Update1 presented an increase in mine life from
17 to 25 years. The Company now presents alternative production
targets ("Production Targets") in this ASX Release based on an
analysis of opportunities to accelerate production in year 3 of
operation, without any other material changes to the underlying
assumptions or levels of confidence.
Options have been analysed to expand
the production capacity commencing in the third year of operations
from the initial development plan of 4.1Mtpa mine rate to produce
~2Mlbspa U3O8 per year by accelerating the
mining rate and increasing production capacity. Production
scenarios have been assessed for mining rates of 6.25Mtpa,
producing ~3Mlbspa U3O8 and 8.2Mtpa,
producing ~4Mlbspa U3O8. The options
presented will not replace the Base Case presented in the September
2024 Production Target Update1, rather they demonstrate
optionality for the Tiris Uranium Project once in
operation.
KEY
POINTS:
§ The ~3Mlbspa U3O8
production rate (6.25Mtpa mining rate) case
(Option 1) returned the highest NPV and improved economics with
results including:
§ NPV8% of approximately
US$544M (A$836M) an increase of 9% on the base
case1
§ IRR of ~45% post tax and payback in the
order of 2.5 years
§ High margin average annual post-tax cash
flows over the life of mine of ~US$86M, an increase of 37% and
average ~US$116M over the first five years of
operations
§ Additional development capital fundable
from cashflow
§ Analysis used only
27% (21Mt) of the total defined Tiris East Inferred Mineral
Resources (79Mt @ 210ppm U3O8 for 36.7Mlbs
U3O8)2, increasing the confidence
that any future increases in Inferred Mineral Resources and
exploration success will have a materially positive impact on this
analysis
§ The next steps in
progressing towards the construction and development of the Tiris
Uranium Project include:
§ Project
funding inclusive of debt, strategic investors and / or
equity
§ Securing
further offtake contracts for future production
§ Confirming
water supply and infrastructure
§ Engagement
with qualified EPCM contractors for project development
§ Update of
Ore Reserve estimate
§ Completion
of Project Execution Plan
§ Final
Investment Decision - March quarter 2025
Information on the future capacity
expansion options is summarised in the table below:
|
Units
|
4.1Mtpa mining (~2Mlbspa
U3O8)
Sept
241
|
Option 1
6.25Mtpa
mining
(~3Mlbspa
U3O8)
|
Option 2
8.2Mtpa
mining
(~4Mlbspa
U3O8)
|
Uranium Price
|
US$/lb
U3O8
|
$80
|
$80
|
$80
|
Valuations and Returns
|
Post-tax NPV8
|
US$M
|
499
|
544
|
521
|
Post-tax IRR
|
%
|
39%
|
45%
|
41%
|
Payback period
|
Years
|
2.25
|
2.5
|
3.25
|
Cashflow Summary
|
Initial Life of Mine
|
Years
|
25
|
18
|
16
|
LOM
Production
|
Mlbspa
U3O8
|
43.5
|
37.9
|
37.9
|
Annual Production
|
Mlbspa
U3O8
|
1.8
|
2.3
|
2.9
|
Gross Revenue (LOM)
|
US$M
|
3,467
|
2,898
|
2,898
|
Free
Cashflow pre-tax (LOM)
|
US$M
|
1,922
|
1,817
|
1,813
|
Free
Cashflow post tax (LOM)
|
US$M
|
1,509
|
1,457
|
1,484
|
Unit
Operating Costs
|
All
in Cost
|
US$/lb
U3O8
|
41.0
|
40.2
|
43.7
|
All-in Sustaining Costs
|
US$/lb
U3O8
|
35.7
|
31.8
|
31.9
|
C1
Cash Cost
|
US$/lb
U3O8
|
31.4
|
27.7
|
27.9
|
Operating Margin
|
US$/lb
U3O8
|
44.3
|
48.8
|
48.1
|
Operating Margin
|
%
|
55%
|
60%
|
60%
|
Capital Cost
|
Development Capital
|
US$M
|
230
|
317
|
445
|
Table
1 - Summary of the future
capacity expansion options results with comparison of the September
2024 Production Target update
Aura Energy Managing Director and CEO, Andrew Grove
said:
"From the development production target update in September,
the Tiris Uranium Project has shown to be a very significant
near-term low-cost high margin uranium project with exceptional
economics2F[3],
a NPV8 of US$499M (A$734M), IRR 39% and producing
2Mlbspa U3O8
over 25 years at
an AISC of US$35.7/lb U3O8 commencing in late
2026/early 2027.
Today's announcement clearly demonstrates the significant
internal growth opportunity at Tiris through a future expansion of
the Project from Stage 1 cash flows, improving the confidence of
the Inferred Mineral resources and further exploration success from
what is a highly prospective and under-explored region with
extensive un-drilled radiometric targets.
The initial near term Tiris Uranium Project development will
be the start of the value creation from the Project. Aura's has
excellent internal growth opportunities beyond the initial planned
Tiris Uranium Project development providing exceptional leverage as
uranium demand is forecast to grow on the back of committed
development of reactors coming on stream."
Key
highlights and outcomes of the alternative production target
analysis:
The assessment of the capacity
expansion opportunities identifies revenue can be moved forward by
accelerating the mining schedule with the following observations
for the cases analysed:
§ The open pit mining is a simple, low-risk,
shallow, flexible, free digging operation without the need
for crushing and grinding
§ Initial development
plan provides for a high margin long life business. Future
expansion plans can further enhance the Project value and can be
potentially funded from cash flows
§ Operating costs,
AISC, decrease in the expansion cases analysed and are largely due
to spreading the fixed costs over a larger annual production
base
§ The analysis only
used approximately 26% of Inferred Mineral Resources
currently defined in the Tiris Uranium Project area amounting
in aggregate to 21Mt of the total 79Mt @ 210ppm
U3O8 for 36.7Mlbs
U3O8[4]. Drilling to
increase the confidence of the Inferred resources is anticipated to
have a materially positive impact on this analysis
§ The significant
exploration potential at Tiris also presents an opportunity to add
significant additional value to the future operations and support a
future expansion of the operations
§ The construction and
operation of the Tiris Uranium Project is anticipated to deliver
significant and ongoing benefits to Aura shareholders and the
people of Mauritania
Cautionary Statement: TIRIS URANIUM PROJECT - ALTERNATIVE
PRODUCTION TARGETS
The analysis presented in this ASX
release represents alternative production targets ("Production
Targets") to those presented in the ASX and AIM Release: 11
September 2024 - Updated Production Target Improves Economics at
Tiris. As noted in this release, the updated Production Target was
based upon Front End Engineering Design (FEED) and Definitive
Feasibility Study (DFS) level material assumptions. For more
information, please refer to the ASX and AIM Release: 11 September
2024 - Updated Production Target Improves Economics at Tiris
("Production Target Update").
The 11 September Production Target
Update presented an increase in mine life from 17 to 25 years. The
Company now presents alternative production targets in this ASX
Release as an analysis of opportunities to accelerate production,
without any other material changes to the underlying assumptions or
levels of confidence. The modular nature of the Tiris processing
plant allows for addition of extra modules without significantly
impacting the overall confidence in the capital
estimate.
As the Alternative Production
Targets for Tiris Uranium Project utilise a portion of Inferred
Resources, ASX Listing Rules require a cautionary statement to be
included in this announcement.
The Alternative Production Targets
referred to in this announcement are based on the updated Mineral
Resource Estimate reported in accordance with JORC guidelines 2012
in the ASX announcement entitled Aura increases Tiris Mineral Resources by 55%
to 91.3Mlbs U3O8 (dated 12 June
2024)X.
The Tiris Uranium Project
Alternative Production Targets set out in this announcement use
Measured Resources (34%), Indicated Resources (40%), and Inferred
Resources (26%) for the mining inventory. The removal of the last
1% of Inferred material to achieve a 25% target has less than US$1
million impact on NPV, is not considered material and was
maintained to keep a logical mining sequence.
The percentage of Inferred Resources
in the Alternative Production Target over the first five (5) years
is 8% at a production rate of 6.25Mtpa (~3Mlbspa
U3O8 production) and 7% at a mining rate of
8.2Mtpa (~4Mlbspa U3O8
production).
The percentage of Inferred Resources
in the Alternative Production Target over the first 10 years is 20%
at a production rate of 6.25Mtpa (~3Mlbspa
U3O8 production) and 21% at a mining rate of
8.2Mtpa (~4Mlbspa U3O8 production). The
project remains economically viable with removal of Inferred
Resources from the alternative production targets.
The Company confirms that the use of
Inferred Resources is not a determining factor to the Tiris
Project's economic viability. There is a low level of geological
confidence associated with Inferred Mineral Resources and there is
no certainty that further exploration will result into the
determination of Indicated Mineral Resources, or that the
production targets reported in this announcement will be
realised.
The Company confirms that it is not
aware of any new information materially affecting the information
included in the ASX announcement: Aura increases Tiris Mineral Resources by 55%
to 91.3Mlbs (dated 12 June 2024). All material assumptions
and technical parameters underpinning the Mineral Resources
Estimates continue to apply. The Company confirms that the form and
context in which the Competent Person's findings are presented have
not been materially modified from the original market
announcement.
In accordance with ASX Listing Rules
5.16 and 5.17, and 2012 JORC Code reporting guidelines, a summary
of the information derived from the Tiris Uranium Project
Alternative Production Target is detailed in this report. The
analysis also draws on information from the ASX announcements:
Updated Production Target Improves
Economics at Tiris (dated 11 September 2024), Update to Curzon Offtake Agreement
(dated 16 April 2024), Aura's
Tiris FEED Study returns Excellent Economics (dated 28
February 2024) and Tiris Uranium
Project Enhanced Definitive Feasibility Study (dated 29
March 2023) which are available here:
auraenergy.com.au/investor-centre/asx-announcements.
The Announcement includes
forward-looking statements. These forward-looking statements are
based on the Company's expectations and beliefs concerning future
events. Forward-looking statements are necessarily subject to
risks, uncertainties, and other factors, many of which are outside
the control of Aura Energy, which could cause actual results to
differ materially from such statements. Aura Energy makes no
undertaking to subsequently update or revise the forward-looking
statements made in this announcement, to reflect the circumstances
or events after the date of this announcement.
The Company has concluded that it
has a reasonable basis for providing the forward-looking statements
and production targets included in this announcement. The detailed
reasons for this conclusion are outlined throughout this ASX
announcement and in Updated
Production Target Improves Economics at Tiris (dated 11
September 2024), Update to Curzon
Offtake Agreement (dated 16 April 2024) Aura's Tiris FEED Study returns Excellent
Economics (dated 28 February 2024) and Tiris Uranium Project Enhanced Definitive
Feasibility Study (dated 29 March 2023). The Company
confirms that apart from updates to the Tiris Uranium Project's
production targets outlined in this Tiris Alternative Production
Targets announcement, all the material assumptions underpinning the
aforementioned announcements continue to apply and have not
materially changed.
ENDS
The board of Aura Energy Ltd has
approved this announcement.
This Announcement contains inside
information for the purposes of the UK version of the market abuse
regulation (EU No. 596/2014) as it forms part of United Kingdom
domestic law by virtue of the European Union (Withdrawal) Act 2018
('UK MAR').
For
further information, please contact:
Andrew Grove
Managing Director and CEO
Aura Energy Limited
agrove@auraee.com
+61 414 011 383
|
|
SP
Angel Corporate Finance LLP
Nominated Advisor and
Broker
David Hignell
Adam Cowl
Devik Mehta
+44 203 470 0470
|
About Aura Energy (ASX: AEE, AIM:
AURA)
Aura Energy is an Australian-based
mineral company with major uranium and polymetallic projects in
Africa and Europe.
The Company is focused on developing
a uranium mine at the Tiris Uranium Project, a major greenfield
uranium discovery in Mauritania. 2024 FEED Study[5] and Updated Production Target[6] demonstrated Tiris to be a near-term low-cost
2Mlbspa U3O8 future uranium mine with a
25-year mine life with excellent economics and optionality to
expand to accommodate future resource growth.
Aura plans to transition from a
uranium explorer to a uranium producer to capitalise on the rapidly
growing demand for nuclear power as the world shifts towards a
decarbonised energy sector.
Disclaimer Regarding Forward-Looking
Statements
This ASX announcement (Announcement)
contains various forward-looking statements. All statements other
than statements of historical fact are forward-looking statements.
Forward-looking statements are inherently subject to uncertainties
in that they may be affected by a variety of known and unknown
risks, variables and factors which could cause actual values or
results, performance or achievements to differ materially
from the expectations described in such forward-looking
statements. The Company does not give any assurance or
guarantee that the anticipated results, performance or
achievements expressed or implied in those forward-looking
statements will be achieved.
The Company has concluded that it
has a reasonable basis for providing the forward-looking statements
and production targets included in this announcement and that
material assumptions remain unchanged. The detailed reasons for
this conclusion are outlined throughout this announcement, and in
the ASX Releases; "Aura's Tiris FEED Study returns Excellent
Economics", dated 28 February 2024, "Tiris Uranium Project Enhanced
Definitive Feasibility Study", dated 29 March 2023 and "Updated
Production Target improves economics at Tiris Uranium Project",
dated 11 September 2024.
ASX and JORC Related
Disclosures
Mineral Resources
The information on Mineral Resources
for the Tiris Uranium Project in this report is extracted from the
ASX release "Aura increases Tiris Mineral Resources by 55% to
91.3Mlbs", dated June 2024.
These reports can be viewed
at https://auraenergy.com.au/investor-centre/asx-announcements.
The estimated mineral resources
underpinning the alternative production targets have been prepared
by a Competent Person or persons in accordance with the
requirements in Appendix 5A (JORC Code). The Competent Person
for the 2024 Tiris Mineral Resource Estimates for all deposits
underpinning the Production Targets is Mr Arnold van der Heyden of
H&S Consulting Pty Limited[7].
The company confirms that it is not
aware of any new information or data that materially affects the
information included in the original market announcement and, in
the case of estimates of Mineral Resources or Ore Reserves, that
all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and
have not materially changed. The company confirms that the form and
context in which the Competent Person's findings are presented have
not been materially modified from the original market
announcement.
Production Targets
The information on Production Targets for the Tiris Uranium
Project in this report is extracted from the ASX release "Updated
Production Target Improves Economics at Tiris", dated 11 Sept
2024. This report can be viewed at
https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that all
material assumptions on which the Alternative Production Targets
are based have been disclosed in this release.
The company confirms that it is not
aware of any new information or data that materially affects the
information included in the original market announcement and that
all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and
have not materially changed.
Ore
Reserve Estimates
There are no Ore Reserves reported
from this work.
This mine schedule optimisation
study has not been undertaken to a suitable level for Ore Reserve
Reporting. There is outstanding work required before an Ore Reserve
can be estimated based on the June 2024 Mineral Resource. That work
is currently in progress.
An Ore Reserve Estimate has
previously been published with the ASX and AIM Release: 28 March
2023 - Tiris Uranium Project Enhanced Definitive Feasibility
Study. Since that publication an updated production target,
outlined in ASX release "Updated Production Target Improves
Economics at Tiris", dated 11 Sept 2024 has been released and work
remains ongoing to estimate an Ore Reserve from this
target.
Competent Person
The Competent Person for the
Financial Analysis of expansion options for the Tiris Uranium
project is Dr Will Goodall. Dr Goodall is Chief Development Officer
with Aura Energy Ltd. The financial analysis in the report to which
this statement is attached and related material assumptions
arebased on information compiled and reviewed by Dr Will Goodall.
Dr Goodall has sufficient experience that is relevant to the
project and to the activity which he is undertaking. This qualifies
Dr Goodall as a Competent Person as defined in the 2012 edition of
the 'Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves'. Dr Goodall is a Member of The
Australasian Institute of Mining and Metallurgy (AusIMM). Dr
Goodall consents to the inclusion in the analysis of the matters
based on his information in the form and context in which it
appears
Tiris Uranium Project Base Case Summary
The Tiris Uranium Project is a
greenfield calcrete uranium project located in Mauritania that was
first discovered by Aura Energy in 2008. It represents the first
planned development in a significant new global uranium province in
Mauritania with an updated Mineral Resource Estimate of 91.3Mlbs
U3O88[8] and with
very considerable exploration upside and project growth
opportunities. The mineralisation is naturally suited to low
capital cost development and low operating cost extraction of
uranium, presenting an opportunity for near term development of the
Project.
The FEED Study[9] was completed in February 2024 with focus on
improving engineering definition for each of the three modular
circuit components of the Tiris Uranium Project, including the
beneficiation, concentrate processing and precipitation and
packaging circuits. The scope was defined in this manner to provide
scalability to fully utilise additional Mineral Resources as they
were defined.
The FEED10 study which
defined the project configuration is outlined in
Table 2. The production
target11 for the Tiris Uranium Project was updated in
September 2024 and the base case economics are presented in
Table 2. The production
target information from September 2024 is the data used in the
scenario analysis.
Parameter
|
Unit
|
FEED
parameters
Feb 2024
4.1Mtpa
mining
(~2Mlbspa
U3O8)
|
Production
target
Sep 2024
4.1Mtpa
mining
(~2Mlbspa
U3O8)
|
Beneficiation modules
|
#
|
4
|
|
Processing modules
|
#
|
2
|
|
Precipitation and packaging modules
|
#
|
1
|
|
Beneficiation design capacity
|
Mtpa
|
5
|
|
Processing design capacity
|
Mtpa
|
0.5
|
|
Total ore mined
|
Mt
|
63.7
|
|
Avg
Strip ratio
|
W:O
|
0.7
|
|
Avg
mined grade
|
U3O8 ppm
|
255
|
|
Contained U3O8
|
U3O8 Mlbs
|
35.8
|
|
Avg
concentrate grade
|
U3O8 ppm
|
1,743
|
|
Total Product U3O8
|
U3O8 Mlbs
|
30.1
|
|
Life
of Mine
|
years
|
17
|
|
Resource utilisation
|
%
|
75%
|
|
Table
2 - FEED configuration
parameters with comparison of variations between FEED production
target and updated production target
Evaluation of alternative
Production Targets for expansion opportunities
The updated Production Target for
the Tiris Project[10] demonstrated a
substantial increase in mine life, from 17 years to 25 years. Based on this
Production Target the Company has examined alternative Production
Targets to expand future mining rates and production capacity of
the Tiris Uranium Project after the Project has been put into
production and cashflow is available to fund the expansion
opportunity. The basis for evaluation of expansion opportunities
included:
§
Project start up unchanged from Tiris
FEED12
study configuration and updated Production
Target13
§ Capital
expansion of the beneficiation and processing plants in year three
of operation
§ Capital
and operating cost estimates expanded on modular basis, as defined
in the FEED study[11]
The material assumptions for the
FEED study15, including capital and operating cost
estimates, remained unchanged in the development of an updated
production target utilising the updated June 2024 Mineral Resource
Estimate ('MRE')[12], for project start up.
Estimation of expansion capital and operating costs was completed
by adding process modules. All updates relating to the material
assumptions for inputs to the updated Production Targets for each
option analysed are outlined in the following sections.
Tiris Uranium Project
background
The Tiris Uranium Project is 100%
owned by Tiris Ressources SA, which is 85% owned by Aura Energy Ltd
and 15% by the Mauritanian Government's Agence Nationale de
Recherches Géologiques et du Patrimoine Minier
('ANARPAM').
A Scoping Study was completed in
2014. This was updated into a Feasibility Study ('FS') document in
May 2017, to support an application for exploitation licences. The
FS and an extensive Environmental and Social Impact Assessment
('ESIA') were submitted on 24 May 2017 to the Mauritanian Ministry
of Petroleum, Energy and Mines, and formally approved by the
Mauritanian Government on 5 October 2017.
A Definitive Feasibility Study
('DFS') for a 1.25Mtpa mine and 230ktpa process plant was completed
in 201913F[13]. The process plant was designed
to take full advantage of the characteristics of the material which
responds well to concentration of uranium by scrubbing and
screening, whilst providing a low capital cost and rapid project
development and construction.
The capital estimate for the DFS was
updated in August 2021[14]. In March 2023
an Enhanced Definitive Feasibility Study[15] ('EFS') was published including additional Ore
Reserves and Mineral ResourcesF[16]. The EFS
presented a staged development approach, including a 2-year ramp up
at 1.25Mtpa mined ore, expanding to 4.1Mtpa mined ore in year three
to produce an average of 2Mlbspa
U3O8.
In February 2024 the results of a
FEED study14
updated capital and operating cost assumptions and
accelerated production to a base case capacity of 2Mlbspa
U3O8 from the beginning of the
Project.
Exploitation licences (2491C4 and
2492C4) for the Ain Sder and Oued El Foude permits, were granted on
8 February 2019[17]. Mining Conventions for
these permits were signed in January 2023[18] and the final permits for mining and processing
uranium were granted in July 2024[19].
The Mineral Resource Estimate for
the Tiris Uranium Project was updated in the ASX and AIM release:
"Aura increases Tiris Mineral Resources by 55% to 91.3Mlbs", dated
12 June 2024. The global resource has been summarised
in Table 3.
The Tiris Production Target update presented in September 2024
included material from the Tiris East resources and excluded
material from Oum Ferkik Resources.
Tiris Mineral Resource June
2024
|
Deposit
|
Class
|
Ore
|
U3O8
|
U3O8
|
V2O5
|
V2O5
|
Mt
|
ppm
|
Mlbs
|
ppm
|
Mlbs
|
All Tiris
East
|
Measured
|
34
|
230
|
17.3
|
75
|
5.6
|
Indicated
|
48
|
212
|
22.6
|
69
|
7.3
|
Inferred
|
79
|
210
|
36.7
|
68
|
11.9
|
Sub-total
|
162
|
215
|
76.6
|
69
|
24.9
|
Oum
Ferkik
|
Inferred
|
22
|
294
|
14.6
|
95
|
4.7
|
All
Deposits
|
Measured
|
34
|
230
|
17.3
|
74
|
5.6
|
Indicated
|
48
|
212
|
22.6
|
69
|
7.3
|
Inferred
|
102
|
229
|
51.4
|
74
|
16.6
|
Grand Total
|
All
|
184
|
225
|
91.3
|
73
|
29.6
|
Table
3 - Tiris Uranium project
Mineral Resource Estimate updated June 2024
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability
The information on Mineral Resources
for the Tiris Uranium Project in this report is extracted from the
ASX release "Aura increases Tiris Mineral Resources by 55% to
91.3Mlbs", dated June 2024.
These reports can be viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The estimated mineral resources underpinning
the alternative production targets have been prepared by a
Competent Person or persons in accordance with the requirements in
Appendix 5A (JORC Code). The Competent Person for the 2024
Tiris Mineral Resource Estimates for all deposits underpinning the
Production Targets is Mr Arnold van der Heyden of H&S
Consulting Pty Limited[20].
The company confirms that it is not
aware of any new information or data that materially affects the
information included in the original market announcement and, in
the case of estimates of Mineral Resources or Ore Reserves, that
all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and
have not materially changed. The company confirms that the form and
context in which the Competent Person's findings are presented have
not been materially modified from the original market
announcement.
Expansion opportunity
assessment
The Tiris Production Target update
presented in September 2024[21]
demonstrated an increased mine life from 17
to 25 years. The modular design of the Tiris process flow
sheet, Figure 1,
allows for easy expansion of capacity through the addition of
further beneficiation and processing modules. Consequently, the
Company has assessed opportunities to optimise the life of mine
through assessment of several expansion scenarios, summarised
in Table 4.
Figure
1 - Tiris Uranium Project key
operational parameters and systems
Scenario
|
Target expansion
year
|
Mining rate
|
Production target
capacity
|
Base case
|
N/A
|
4.1
Mtpa
|
~2 Mlbspa
U3O8
|
Option 1
|
3
|
6.25
Mtpa
|
3 Mlbspa
U3O8
|
Option 2
|
3
|
8.2
Mtpa
|
4 Mlbspa
U3O8
|
Table
4 - Expansion scenario
configurations and alternative Production Target
capacity
Expansion mining
assumptions
Introduction
An updated mine planning
study[22] was
undertaken on the updated Mineral Resource Estimate
for the Tiris Uranium Project of 184Mt @ 225ppm
U3O8 for 91.3Mlbs
U3O8[23]. The tasks
completed included open pit optimisations, mine layouts and
production scheduling.
The mining method remains the same
as proposed in previous studies and is a small-scale open pit
"strip" mine which will commence with the excavation of numerous
discrete pits, with the waste placed in surface landforms. As
mining continues, the resulting pit voids are available to take the
waste from the next mining area, beneficiation plant rejects and
leach plant tailings, which allows progressive backfilling and
rehabilitation. This mining method will result in "real-time
continuous rehabilitation" including a smaller environmental
footprint at any given time and significant savings in waste
movement and rehabilitation costs. Mining has been costed using an
owner mining model, the same as reported in the FEED
Study[24].
Details of the material assumptions
applied to define the mining inventory can be found in ASX
Release: "Updated production target
improves economics at Tiris", dated 11 September
2024.
Expansion schedule cases -
Alternative Production Targets
The alternative production targets were established utilising the
same mining inventory as reported with the September Production
Target update, with mine scheduling completed at higher mining
rates, to assess the value of accelerating production from the
third year of operation. The scheduling objectives for each
option schedule, in order of priority applied, were:
§ Limit the
proportion of Inferred Mineral Resources mined to less than 10% of
feed in first four years and less than 20% in the first ten years
and 25% over the Life of Mine ('LOM')
§ Maximise
cashflow by targeting high value mining areas early in the
LOM
§ Maximise
utilisation of leach plant modules - 260,000t concentrate per annum
per module
§ Maximise
utilisation of each precipitation plant module - 3.0Mlbs.
U3O8 per annum per module
§ Maximise
utilisation of each beneficiation plant module - each 1.2Mt plant
feed per plant per annum
§ Minimise
the number beneficiation plant locations during the first 3 years
of the project to reduce project complexity at startup
§ Minimise
the number of beneficiation plant relocations - estimated to
require three months downtime per relocation
§ Minimise
mining cost by reducing haulage distance from pits to the
beneficiation plant
§ Minimise
mining cost by levelling activity rates
§ The
analysis demonstrated that for production rates of over 4Mlbspa the
constraints limiting the percentage of Inferred material could not
be met and would require additional Inferred Resources to be
upgraded to Measured and Indicated Resources
The total processing modules for
each scenario has been summarised in Table
5.
Cases
|
Expansion
Year
|
Production
|
Modules
|
Mining rate
Mtpa
|
Beneficiation
Plant
Modules
#
|
Processing Plant
Modules
#
|
Packing Plant
Modules
#
|
Base
case
|
N/A
|
4.1
|
4
|
2
|
1
|
Option
1
|
3
|
6.25
|
5
|
3
|
1
|
Option
2
|
3
|
8.2
|
7
|
4
|
2
|
Table
5 - Expansion scenario module
configurations
The site layout for each scenario
can be seen in Figure 2 to
3.
Figure
2 - Site layout for Option 1 -
6.25Mtpa mining to produce ~3Mlbspa U3O8
Production Target schedule over mine
life
Figure 3 - Site layout for Option 2 -
8.2Mtpa mining to produce ~4Mlbspa U3O8 Production Target schedule
over mine life
The physicals by Mineral Resource
area for the alternative Production Targets for expansion options
are shown in Table 6 and the physicals charts by mining area by year for each
option is shown in Figure 4
to Figure
5. The
physicals were maintained from the September 2024 production target
update, with alternative production targets only representing an
acceleration of mining and processing rates.
Mineral Resource
Area
|
Total
Movement
|
Strip Ratio
|
Beneficiation Plant
Feed
|
Process Plant
Feed
|
Recovered
Metal
|
Rock
|
Waste
|
Feed
|
U308
|
U3O8
|
Feed
|
U308
|
U3O8
|
U3O8
|
MT
|
MT
|
MT
|
ppm
|
Mlbs
|
MT
|
ppm
|
Mlbs
|
Mlbs
|
Lazare North
|
31
|
18
|
1.4
|
13
|
287
|
8.1
|
2
|
2,208
|
7.4
|
6.8
|
Lazare South
|
30
|
13
|
0.8
|
17
|
246
|
9.1
|
2
|
2,191
|
8.7
|
8.0
|
Sadi
|
63
|
28
|
0.8
|
35
|
216
|
16.6
|
4
|
1,889
|
15.9
|
14.7
|
Hippolyte North
|
28
|
12
|
0.7
|
16
|
292
|
10.5
|
3
|
1,479
|
9.0
|
8.3
|
Hippolyte South
|
0
|
0
|
0.0
|
0
|
234
|
0.0
|
0
|
0
|
0.0
|
0.0
|
Total
|
152
|
71
|
0.9
|
81
|
250
|
44.3
|
11
|
1,880
|
41.0
|
37.9
|
Table
6 - Summary physicals by
Mineral Resource area
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability.
Figure 4 - Mining physicals
by location for Option 1 - 3Mlbspa Production Target
schedule
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability.
The mining physicals at a mining
rate of 6.25Mtpa for target production rate of ~3Mlbspa
U3O8 (Option 1), remain similar to the base
case[25], with mining predominantly
from the Lazare North, Lazare South and Sadi areas for the first 10
years. During this period a single beneficiation module will be
located in the Hippolyte North location to target high value
blocks.
Figure 5 - Mining physicals by location for Option 2 - 4Mlbspa
Production Target schedule
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability.
The mining
physicals for Option 2, with a mining rate
of 8.2Mtpa targeting production of ~4Mlbspa
U3O8 show that a second beneficiation module
can be located at Hippolyte North to maintain throughput at target
grades.
Mining cost estimation
Mining has been costed using an
owner mining model, the same as was used in the February 2024 FEED
study[26]. The mining
costs were estimated using the project cost and financial models
which can be found in the FEED study release.
Ore Reserve estimate
There are no Ore Reserves reported
from the expansion analysis. The mine schedule optimisation study
has not been undertaken to a suitable level for Ore Reserve
Reporting. There is still work required which is currently in
progress before an Ore Reserve can be estimated based on the June
2024 Mineral Resource.
Production schedule
options
An updated production schedule was
developed for each option based on pit optimisation from the
updated production target. The production targets were constrained
by maintaining full utilisation of the leaching circuits, with
mining rate and uranium oxide concentrate production rate allowed
to vary to maintain this condition as defined under scheduling
objectives.
The updated production schedule, for
the base case and each expansion scenario has been summarised
in Figure 6.
Figure 6: - Comparison of mined ore production schedule
between FEED production targetF[27] and the alternative Production Target
schedules
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability.
A focus was maintained on
minimisation the proportion of Inferred material in the first 10
years of operation. The updated mining schedule only includes
between 7% (Option 1) and 8% (Option 2) Inferred Resources in the
first five years and between 20% (Option 1) and 21% (Option 2) in
the first ten years of operation. Over the LOM, the proportion of
Inferred Resources material was 26%. The Project remains strongly
viable with removal of Inferred Resources material.
The Company confirms that the use of
Inferred Resources is not a determining factor to the Tiris
Project's economic viability. Therefore, the forecast financial
information of not including the Inferred Resources in the
Production Target is not considered material in this
release.
The very shallow mine depth and low
stripping ratio gives the Company a very flexible mine schedule if
any of the early inferred mine plan does not come in. As such, if a
portion of the mine plan Inferred Resource does not convert then
other resources can be bought forward in the schedule.
Other Inferred Resources can be
brought into the back end of the plan if early Inferred Resources
aren't proven up, due to the flexibility around shallow depths and
very low stripping ratios.
In addition, only 50% of the total
Tiris Uranium Project and 26% of the defined Inferred Resources are
being used in the production targets. Other Inferred Resources can
be upgraded and brought into the back end of the mine plan if early
Inferred Resources aren't proven up, due to the flexibility around
shallow depths and very low stripping ratios. The existence of
these other Inferred Resources and the flexibility to utilise them
if required, increases confidence in the life of mine plan,
production targets and forecast financial information.
The production target profile by
resource category for each scenario can be seen in
Figure 7 and
Figure 8.
Figure 7: 6.25Mtpa mining rate, with target production of
~3Mlbspa U3O8 mine schedule ore profile
(Option 1) by area
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability.
Figure 8: 8.2Mtpa mining rate, with target production of
~4Mlbspa U3O8 mine schedule ore profile
(Option 2) by area
Note:
There is a low
level of geological confidence associated with Inferred Resources
and there is no certainty that further exploration or evaluation
work will result in the determination of Indicated Resources or
that the production targets reported in this announcement will be
realised. The Company confirms that the use of Inferred Resources
is not a determining factor to the Tiris Uranium Project's economic
viability.
The updated Base Case concentrate
grade profile for U3O8 compared to the
expansion cases has been presented in Figure 9, demonstrating an average
concentrate grade to leaching of 1,756ppm
U3O8 life of mine, this increases to 1,880ppm
U3O8 for the expansion scenarios. A full
description of concentration of uranium through the beneficiation
circuit by scrubbing and screening, including recovery assumptions,
can be found in the ASX and AIM Release, 'Tiris Uranium Project
Enhanced Definitive Feasibility Study', 29 March 2023.
Figure 9: Concentrate grade profile for
alternative
Production Target schedules highlighting higher leach
feed grade profile in early years
The alternative Production Target
profiles for each option analysed can be seen in
Figure 10. This demonstrates that
although production was targeted to achieve ~3 and ~4 Mlbspa
U3O8 production at mining rates of 6.25Mtpa
and 8.2Mtpa respectively, these were difficult to achieve
consistently over the life of the Project. This was mainly
attributed to depletion of higher-grade mining blocks and the need
to keep the beneficiation modules at resource areas to complete
mining lower grade blocks before the module could be moved. The
Company believes that with further exploration success adding to
the mineral resource inventory that the production targets will be
able to be sustained for longer periods as well as extending the
currently defined mine life.
Figure 10: Uranium oxide production
profile for base case scenario and each alternative Production
Target schedule
Capital cost estimate
The FEED Capital Cost Estimate
('CAPEX') for the development of Tiris has been applied for the
production capacity scenarios used in the analysis and using a
design based on a single modular processing train. The estimate is
shown in Table 7.
Area
|
Base Case
4.1Mtpa
mining
~2Mlbspa
U3O8
|
Option 1
6.25Mtpa
mining
(~3Mlbspa
U3O8)
|
Option 2
8.2Mtpa
mining
(~4Mlbspa
U3O8)
|
US$M
|
US$M
|
US$M
|
Mining
|
4.3
|
8.0
|
11.2
|
Beneficiation
|
25.6
|
31.9
|
44.7
|
Processing
|
84.2
|
122.0
|
168.3
|
Infrastructure
|
54.1
|
71.9
|
101.0
|
EPCM
|
22.5
|
29.5
|
43.2
|
Owner's cost
|
19.3
|
25.6
|
37.2
|
Contingency
|
20.1
|
28.0
|
39.7
|
Total CAPEX
|
230.0
|
316.9
|
445.2
|
Table
7: - Project CAPEX -
FEED 202427F[28]
Operating cost estimate
The operating cost estimate inputs
were maintained from the FEED study29, with no changes
made to unit input costs. The updated schedule did result in some
changes to the mining fleet requirements and a higher strip ratio
than the FEED production schedule, which resulted in a modest
increase in unit operating cost. This also resulted in modest
reductions in fixed costs (labour, power, maintenance) with
increased production rates.
The operating cost estimate has been
summarised in Table 8. The average LOM C1 cash cost will range from US$27.7/lb
U3O8 for the base case to US$28/lb
U3O8 at 8.2Mtpa mining rate (~4Mlbspa
U3O8 capacity). LOM AISC, inclusive of
royalties, LOM sustaining capital, insurances and product transport
will be US$35.7/lb U3O8 for the base case to
US$31.9/lb U3O8 for the 8.2Mtpa mining rate
(~4Mlbspa U3O8 capacity) case. These costs
have been estimated as an average of annualised
expenditure.
Area
|
Base Case
4.1Mtpa
mining
~2Mlbspa
U3O8
|
Option 1
6.25Mtpa
mining
(~3Mlbspa
U3O8)
|
Option 2
8.2Mtpa
mining
(~4Mlbspa
U3O8)
|
Sept 2024
|
Dec 2024
|
Dec 2024
|
US$/lb U3O8
|
US$/lb
U3O8
|
US$/lb
U3O8
|
Owner
Mining
|
9.2
|
8.8
|
8.8
|
Labour
|
2.0
|
1.5
|
1.3
|
Reagents
|
7.0
|
6.8
|
6.8
|
Power
|
8.2
|
7.1
|
7.4
|
Maintenance
|
1.8
|
1.2
|
1.2
|
Environment
|
0.6
|
0.6
|
0.6
|
Site
G&A
|
2.5
|
1.7
|
1.7
|
CASH COST
|
31.4
|
27.7
|
28.0
|
Transport &
Marketing
|
0.5
|
0.5
|
0.5
|
Royalties
|
2.8
|
2.8
|
2.8
|
Communities
|
0.8
|
0.8
|
0.8
|
Sustaining
Capital
|
0.2
|
0.2
|
0.2
|
ALL-IN-SUSTAINING
COST
|
35.7
|
31.8
|
31.9
|
Table
8: - Operating cost estimates
of each scenario compared to the FEED update
Market analysis
Aura has maintained the uranium
market assumptions outlined in the 2024 FEED study[29], with a long-term price assumption of US$80/lb
U3O8. These assumptions remain valid with no
material changes.
Financial analysis
Financial analysis of the Tiris
Project is inclusive of Mauritanian government royalties and
commitments relating to the offtake agreement with Curzon
Resources[30]. This is outlined in the ASX
announcement 'Update to Curzon Offtake Agreement', dated 16 April
2024.
Results are on an after-tax basis in
$USD, unless otherwise stated. Financial modelling is inclusive of
all capital items, including mining mobilisation, process plant,
project infrastructure and LOM sustaining capital.
Table 9 shows the variance in NPV8, IRR, payback period and
net cashflows between the production target update and the options
analysed. Applying a base case uranium price of US$80/lb U3O8,
the September 2024 production target update gave a post-tax
NPV8 of the Tiris Project of US$499M, post-tax IRR of 39%, and project payback of
2.25 years from
commencement of production. At this price the project generates
average annual free cashflows
post-tax of US$89M per annum for the first five years and US$60M
per annum over average over the entire mine life.
The best expansion opportunity
analysed was considered to be the 6.25Mtpa mining rate (3Mlbspa
U3O8 capacity) case - Option 1. For this
scenario an NPV8 of approximately US$544M was estimated with IRR of ~45% and payback of 2.5 years. At this mining rate the
project generates average approximate annual free cashflows post-tax of US$116M per
annum for the first five years after expansion and US$86M per annum
over the entire mine life. This case will not replace the
current base case, however it provides an assessment of potential
growth once the Tiris base case has entered production.
It should be noted that for cases
with production rates greater than 4Mlbs per annum
U3O8, the project economics are strongly
influenced by the expansion capital required and short mine life
based on the current Mineral Resource base. There is considerable
opportunity to optimise the capital requirements through
consolidation of modules with higher throughput. The Company will
continue to assess the opportunities for capital reduction at
higher throughputs.
The Tiris area is highly
prospective, and the Company strongly believes there will be
significant future growth in the Mineral Resource inventory through
exploration and this would further support the economics of a
future expansion of the Project. Very significant areas of
undrilled radiometric anomalies exist with the Tiris East area
within Aura's tenements and within the adjacent tenement
applications, Figure 11.
|
Units
|
Base Case
4.1Mtpa
mining
(2Mlbspa
U3O8)
Sept
241
|
Option 1
6.25Mtpa
mining
(~3Mlbspa
U3O8)
|
Option 2
8.2Mtpa
mining
(~4Mlbspa
U3O8)
|
Uranium Price
|
US$/lb
U3O8
|
$80
|
$80
|
$80
|
Valuations and Returns
|
Post-tax NPV8
|
US$M
|
499
|
544
|
521
|
Post-tax IRR
|
%
|
39%
|
45%
|
41%
|
Payback period
|
Years
|
2.25
|
2.5
|
3.25
|
Cashflow Summary
|
Initial Life of Mine
|
Years
|
25
|
18
|
16
|
LOM
Production
|
Mlbspa
U3O8
|
43.5
|
37.9
|
37.9
|
Annual Production
|
Mlbspa
U3O8
|
1.8
|
2.3
|
2.9
|
Gross Revenue (LOM)
|
US$M
|
3,467
|
2,898
|
2,898
|
Free
Cashflow pre-tax (LOM)
|
US$M
|
1,922
|
1,817
|
1,813
|
Free
Cashflow post tax (LOM)
|
US$M
|
1,509
|
1,457
|
1,484
|
Unit
Operating Costs
|
All
in Cost
|
US$/lb
U3O8
|
41.0
|
40.2
|
43.7
|
All-in Sustaining Costs
|
US$/lb
U3O8
|
35.7
|
31.8
|
31.9
|
C1
Cash Cost
|
US$/lb
U3O8
|
31.4
|
27.7
|
27.9
|
Operating Margin
|
US$/lb
U3O8
|
44.3
|
48.8
|
48.1
|
Operating Margin
|
%
|
55%
|
60%
|
60%
|
Capital Cost
|
Development Capital
|
US$M
|
230
|
317
|
445
|
Table
9: -
Summary of outputs recommended for presentation of Production
Target updates and the scenarios analysed
Figure 11: Radiometrics, tenement boundaries, prospect
locations, Mineral Resource boundaries reported in 2024 and 2023,
along with drilling completed during the current and prior
programs
Sensitivity Analysis
The sensitivity of the project to
key variables was examined in Figure
12 for Option 1 expansion to 6.25Mtpa
throughput and Figure 13
for Option 2 for 8.2Mtpa throughput. This showed
that the Project was most sensitive to revenue drivers, including
mined grade and U3O8 spot price. The Project
was least sensitive to operating cost inputs.
Figure 12 - Sensitivity
analysis for alternative Production Target, Option 1 expanding from
4.1Mtpa mining rate to 6.25Mtpa mining rate in year 3 of
operation
Figure 13 - Sensitivity
analysis for alternative Production Target, Option 2 expanding from
4.1Mtpa mining rate to 8.2Mtpa mining rate in year 3 of
operation
Project risk
The key risks with their
mitigations, are identified as follows:
§ Uranium price:
The Project's success is dependent on the price of
uranium exceeding the operating cost of the project for the life of
the project. Aura is in the process of seeking additional offtake
agreements with suitable long-term pricing, to minimise the risk of
the market price being outside of Aura's control
§ Capital costs:
The estimated capital costs for the project could
prove optimistic, requiring additional funding. The Capex estimate
was composed of 85% external pricing[31],
so has a strong basis for its pricing, subject to any subsequent
inflation. The project will rely on competent Project cost control
by the EPC company overviewing the project
§ Health and safety
risk: Occupational health and safety
(OHS) management risk of radioactive dust in the mining and
production areas. Aura will ensure operators are in dust sealed
cabins, use radiation monitoring badges and will rotate personnel
as necessary. There are also risks from terror groups in the Sahel
region. Aura has provisionally arranged for military supported
security to be permanently based close to the site. Aura will
continue with its very close coordination with
police/gendarmes/military guarding the area
§ Government
approvals: There are potential risks
in obtaining Mauritanian statutory permit approvals, in the time
required. Aura is continuing on high-level relationships between
Government authorities and its senior management, to assist the
usual project interfaces between Aura's local permitting supervisor
and Government authorities. It is expected given Aura's focus on
maximising local employment, that the Mauritanian Government will
continue to be supportive
§ Water supply:
A risk remains of insufficient water being
available for the project. A program designed to mitigate the risk
that includes the drilling and test work of the Taoudeni Basin is
currently underway with significant water quantities having been
identified by drilling and it is expected that there will be more
than sufficient quantities of water available for the
Project
§ Power supply:
Aura's hybrid diesel and solar generation plant
will be the only power source for the Project. Aura shall undertake
rigorous engineering selection of the power generation supply and
hire experienced and competent electrical support personnel to
maintain the power plant
Future activities
The next steps in progressing
towards the construction and development of the Project planned for
2024 and early 2025 include:
§ Project
funding inclusive of debt, strategic investors and
equity
§ Securing
offtake contracts for future production
§ Water
drill hole and aquifer testing to demonstrate that sufficient water
resources will be available for the Project. Drilling has been
completed with significant water flows having been intersected both
at the Taoudeni Basin, ~120km south of the Project and the more
proximal C22 target
§ Engagement
with qualified EPCM contractors for project development
§ Additional
engineering and design work to support development
activities
§ Update of
Ore Reserve estimate
§ Completion
of Project Execution Plan
§ Final
Investment Decision - March quarter 2025