Centamin PLC Q1 Preliminary Production Results (3704E)
April 09 2014 - 2:00AM
UK Regulatory
TIDMCEY
RNS Number : 3704E
Centamin PLC
09 April 2014
For immediate 09 April 2014
release
Centamin plc ("Centamin" or "the Company")
(LSE:CEY, TSX:CEE)
Q1 Preliminary Production Results
Centamin is pleased to announce preliminary production results
from its Sukari Gold Mine ("Sukari") in Egypt for the quarter ended
31 March 2014. Total gold production for the quarter was 74,241
ounces, a 14% decrease on the corresponding quarter in 2013 and 19%
lower than Q4 2013. Although gold production was affected by a
temporary reduction in the underground average grade, the first
quarter demonstrated record levels of material movement from the
underground mine and process plant throughput and all areas of the
operation have provided a solid foundation for the year ahead.
Production guidance for 2014 remains unchanged at 420,000 ounces
gold.
Open pit total material movement continued well from the
previous quarter with a small increase of 1% to 9,749kt. A decrease
in open pit ore production of 26% on Q4 2013 to 2,325kt reflected a
focus on waste stripping activities in line with the mine plan. The
run of mine ore stockpile balance decreased by 216kt to 1,540kt at
the end of the period.
Record quarterly throughput at the process plant was 1,486kt, a
6% increase on the prior year period and a 6% increase on Q4 2013,
exceeding the nameplate annualised rate of 5 million tonnes for the
fifth successive quarter with continued high levels of productivity
and availability. The Stage 4 commissioning process will
progressively lift overall plant throughput and hence gold
production levels through the remainder of the year.
The primary challenge faced during the quarter was from poor
mining fleet availability within the high grade stoping areas of
the underground mine. Whilst the operation delivered a record 206kt
of ore, up 18% on Q4 2013, this limited ability to remotely mine
the high-grade stopes reduced the average mined grade to below
planned levels and thus restricted the contribution to overall
production. These problems with equipment availability were
rectified late in the quarter.
Q1 2014 Q4 2013 Q1 2013
(estimate)
---------------------------- ------------ -------- --------
Total Material Movement
- Open Pit (kt) 9,749 9,642 10,550
---------------------------- ------------ -------- --------
Open Pit Ore Production
(kt) 2,325 3,161 2,133
---------------------------- ------------ -------- --------
Underground Ore Production
(kt) 206 174 119
---------------------------- ------------ -------- --------
Process Plant Throughput
(kt) 1,486 1,400 1,402
---------------------------- ------------ -------- --------
Process Plant Productivity
(tph) 745 698 689
---------------------------- ------------ -------- --------
Gold Produced (oz) 74,241 91,546 87,016
---------------------------- ------------ -------- --------
Josef El-Raghy, Chairman of Centamin, commented:
"Consistently high levels of productivity have again been
achieved with the process plant at Sukari, with minimal impact from
the Stage 4 commissioning activities. Although underground
performance has impacted Q1 we are pleased to confirm commissioning
of Stage 4 is proceeding as planned, with Sukari achieving a major
milestone towards the end of Q1 as first ore was fed through the
new circuit. We expect plant throughput, and hence quarterly
production rates, to increase through the rest of the year as
commissioning continues. Our forecast 2014 production and the
continued ramp up towards Sukari's long-term target of
450,000-500,000 ounces per annum remain on track."
For more information please contact:
Centamin plc Buchanan
Josef El-Raghy, Chairman Bobby Morse, Gordon
Andy Davidson, Head of Business Poole,
Development and Investor Relations Gabriella Clinkard
(andy.davidson@centamin.je) +44 + 44 (0) 20 7466
(0) 1534 828708 5000
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCQVLFBZZFFBBX
Centamin (LSE:CEY)
Historical Stock Chart
From Dec 2024 to Jan 2025
Centamin (LSE:CEY)
Historical Stock Chart
From Jan 2024 to Jan 2025