8
July 2024
GOLDSTONE RESOURCES
LIMITED
("GoldStone" or the
"Company")
Homase Mine
Update
GoldStone Resources Limited
(AIM:GRL) is pleased to provide an operational update in respect of
the Homase Gold Project in south-western Ghana
("Homase").
Highlights
ยท
Continuous operations maintained at Homase during
H2 2023 and H1 2024:
o Current operation achieving mining and stacking agglomerated
ore at an average of 5,400 tonnes pcm
o 2024
production to date of 1,350 troy ounces of gold following last gold
pour on 18 June 2024 (Figure 1)
o Significant increase in gold recovery to 68% over the past six
months
o On
track to increase production to deliver the planned 50,000 tonnes
of stacked and agglomerated ore, targeting gold-production of
1,000oz pcm within six months
ยท
Exploration activities continue to demonstrate the
potential to materially expand Homase's current JORC Code Compliant
Resource of 602,000oz gold resource at an
average grade of 1.77 g/t
Emma Priestley, CEO of Goldstone, commented:
"The Company remains focused on delivering
Shareholder value, and this is why the difficult decision was taken
in 2023 to halt production and review the design of the processing
plant. Despite the many challenges associated with the Company's
ordinary shares being suspended from trading for such a long period
of time, the Board and management team have remained committed to
building value for our Shareholders and are now pleased that the
upgraded plant is delivering the improved heap-leaching gold
recoveries we targeted.
"Importantly, the capital-expenditure
requirements to increase gold production are relatively minimal
henceforth, merely requiring completion of leach pads 5, 6, and 7
and construction of an additional pond. These works will allow the
Company to further realise the considerable potential of the Homase
Mine's oxide resource base, with the key objective of increasing
monthly gold production to 1,000 ounces within six months and
achieving [increased operating] cash flow through optimising unit
costs and decreasing G&A exposure.
"I
would like to thank the Board and the Company's advisers for their
support and to the management team in Ghana for maintaining the
mining operations in good order - and especially the Shareholders
for their patience as we focused on improving the gold recoveries
and ensuring a long-life mining operation."
Homase Gold Project - Production
In 2023, the Company elected to
suspend mining in order to evaluate processing options. This was
facilitated by the ยฃ2.4 million investment, announced on 27 January
2023, which enabled engineering improvements and further test work
to be undertaken.
As announced by the Company on 31
May 2023, the Company's process plant on site was extensively
upgraded during 2023, with the acquisition of vibrating screens,
improved cement feed, and the introduction of a radial stacker,
resulting in a significant increase in gold recovery rate to 68%
demonstrated over the past two months (2022 average of 34%). The
Company is now on track to start increasing production to deliver
the planned 50,000 tonnes of stacked and agglomerated ore within
six months, and this level is expected to be maintained on a
monthly basis to ensure that gold-production targets of 1,000oz pcm
can be achieved.
The Company has now hired a 50-tonne
excavator and three 45-tonne ADT trucks (Figure 2), which will
allow a substantial increase in production from Homase's Pit 2,
which is yielding an average grade of 1.1g/t.
On the heap leach pads, the Company
has levelled and compacted Pads 1, 2 and 3 in readiness for the
second lift - superimposition of the next layer of ore for
leaching. Pad 4 is nearing completion, Pad 5 is being constructed,
and civil engineering has begun for Pads 6 and
7.
Another important achievement in
2023 was the commissioning of the on-site laboratory, allowing the
Company to undertake continuous Column Leach test work and Fire
Assays, with the appropriate microbalances and an Atomic Absorption
machine to ensure accurate analysis. This facility now enables
better grade control, critical for both mining and
processing.
Despite limited cash resources
during 2023 and H1 2024, the Company remained focused on resuming
mining and increasing production, and with the equity raise
announced on 24 May 2024, the Company was able to return to trading
and the Board now look forward to progressing
operations.
Figure 1. June 2024 Gold Dorรฉ
Bar - 280 ounces
Figure 2. The 50-tonne
excavator loading one of the three 45-tonne ADTs in Pit 2 at the
Homase Mine
Figure 3. The Company's
Laboratory with the Muffle Furnace and Column Leach Test
Work
Continued Desk Review for Exploration
Throughout 2023 and in H1 2024, the
Company continued to review historical exploration datasets for the
Homase mine and its extended mineralised trend, as described in the
Company's announcement on 20 June 2018, that extends north-east and
south-west of the current Homase Mine and is open at depth. Within
the Homase mining lease, the mineralised zone extends over NNE-SSW
distance of approximately 5km including a substantial deeper gold
resource of c. 600,000 oz underlying and NNE of the Homase pit.
There is also a parallel zone (Adubriem)
around 800m in length within the exploration permit area that has
yet to be systematically explored, as shown in Figure
4.
Historical records show that there
was significant close-spaced drilling undertaken beneath the former
pit mined by Ashanti Goldfields Corporation ("AGC" - now AngloGold Ashanti) between
2002 and 2003, and it is evident that the grade improves markedly
at depth with the transition through 5-10 m of transition ore to
sulphide ore. This former AGC pit is referred to as Pit 4 under the
current mine plan.
Notwithstanding the mineralogical
changes with depth, the oxide cap that is currently being mined
along the Homase trend is some 40-50 metres thick and averages
1.1g/t.
The Company is fortunate to have the
feasibility study and metallurgical testwork data that was
undertaken by AGC in the early 2000s and this shows that the
primary sulphide ore is predominantly non-refractory. Drilling
beneath the AGC pit (now Pit 4), in 2011 and 2012 was made in
sections to 25m intervals along strike. The results from the
drilling programme were announced during the 2011 - 2012 period,
concluding with the JORC Resource in announcement 22 November
2012. Results recorded as announced 5 December 2011, showed
mineralised zones over 10 metres wide on the vertical with a grades
in excess of 6g/t. The Company intends to undertake further
drilling of this section of the Homase trend, including Pits 1-4,
targeting the primary ore.
Figure 4. Plan showing
the target areas for exploration
For
further information, please contact:
GoldStone Resources Limited
|
|
Emma Priestley
|
Tel: +44 (0)1534 487 757
|
Strand Hanson Limited
|
|
James Dance / James
Bellman
|
Tel: +44 (0)20 7409 3494
|
S.
P. Angel Corporate Finance LLP
|
|
Ewan Leggat / Charlie
Bouverat
|
Tel: +44 (0)20 3470
0501
|
St
Brides Partners Ltd
Susie Geliher
|
Tel: +44 (0)20 7236 1177
|
|
|
About GoldStone Resources Limited
GoldStone Resources Limited (AIM:
GRL) is an AIM quoted mining and development company with projects
in Ghana that range from grassroots exploration to
production.
The Company is focused on developing
the Akrokeri-Homase project in south-western Ghana, which hosts a
JORC Code compliant 602,000oz gold resource at an average grade of
1.77 g/t. The existing resource is confined to a 4km zone of the
Homase Trend, including Homase North, Homase Pit and Homase
South.
The project hosts two former mines,
the Akrokerri Ashanti Mine Ltd, which produced 75,000 oz gold at 24
g/t recovered grade in the early 1900s, and the Homase Pit which
AngloGold Ashanti developed in 2002/03 producing 52,000 oz gold at
2.5 g/t recovered. Production is currently focussed on the Homase
Mine however it is the Company's intention to build a portfolio of
high-quality gold projects in Ghana, with a particular focus on the
highly prospective Ashanti Gold Belt.