IMPLATS FIRST QUARTER PRODUCTION REPORT FOR PERIOD 01 JULY TO 30 SEPTEMBER 2010 
 
   Operational information                   Unaudited           Unaudited 
 
                                           Quarter ended       Quarter ended 
 
                                          30 September 10     30 September 09 
 
Implats Gross Refined 
Production 
 
Platinum                          000oz                 441                 413 
 
Palladium                         000oz                 285                 266 
 
Rhodium                           000oz                  57                  63 
 
Nickel                         000tonne                3.76                3.48 
 
Impala 
 
Tonnes Milled                       000               3 979               2 997 
 
Grade (6E)                          g/t                4.66                4.61 
 
% Merensky (Ex underground)                             42%                 41% 
 
Refined Platinum Production       000oz                 251                 180 
 
Marula 
 
Tonnes Milled                       000                 437                 393 
 
Grade (6E)                          g/t                4.32                4.41 
 
Platinum in Concentrate           000oz                  20                  19 
 
Zimplats 
 
Tonnes Milled                       000               1 043                 869 
 
Grade (6E)                          g/t                3.56                3.52 
 
Platinum in Matte                 000oz                  44                  36 
 
Mimosa 
 
Tonnes Milled                       000                 594                 577 
 
Grade (6E)                          g/t                3.91                3.86 
 
Platinum in Concentrate           000oz                  27                  26 
 
IRS 
 
Refined Platinum Production       000oz                 190                 233 
 
Prices Achieved 
 
Platinum                           $/oz               1 528               1 211 
 
Palladium                          $/oz                 470                 260 
 
Rhodium                            $/oz               2 286               1 509 
 
Nickel                          $/tonne              19 100              16 330 
 
Average exchange rate               R/$                7.41                7.82 
 
SAFETY 
 
Regrettably, three of our employees lost their lives at work during the first 
quarter of FY2011. Two of these incidents occurred at Impala Rustenburg, one 
due to a fall-of-ground, the other the result of material handling. The third 
followed an explosives incident at Mimosa in which one of our contractor 
employees was injured and who later passed away in hospital. The Board and 
management team extend their sincere sympathies to the families, friends and 
colleagues of these employees. 
 
The challenge the group continues to face is changing the safety behaviour of 
all employees. Du Pont Sustainable Solutions have been contracted to assist our 
Rustenburg and Marula operations with the introduction of a new Behaviour Based 
Safety System. Key to this is zero tolerance for unlawful behaviour and 
violations of the safety rules by all levels within the company and the 
empowerment of employees to stop unsafe work places and practices. 
 
PRODUCTION 
 
Gross platinum production rose by 7% compared to the first quarter a year ago 
to 441 000 ounces due to increased production from Impala and Zimplats. 
Palladium production increased in line with platinum, but rhodium fell by 10% 
as the pipeline in both the BMR and PMR were restocked during the period. 
 
Impala 
 
At Impala Rustenburg tonnes milled improved by 33% and platinum production 
improved by 39% to 251 000 ounces. In the previous comparable quarter 70 000 
ounces were lost due to the strike action and the major safety incident at 14 
Shaft. The amount of Merensky ore milled continues to be impacted by limited 
face availability at the major shafts. However, improvements in both headgrade 
and yield have benefited production. 
 
The focus at the operation remains on on-reef development at current shafts and 
main development at the project shafts. Number 20 Shaft is on track for first 
reef production early in the new year. The start of equipping at 16 Shaft and 
first level development at 17 Shaft are scheduled to commence in the first half 
of 2011. Impala is on track to produce 940 000 ounces of platinum for the full 
year. 
 
Marula 
 
Production at Marula continues to be hampered by constrained mining 
flexibility. While tonnes milled rose by 11%, a marginal decline in headgrade 
as a result of increased on-reef development coupled with lower recoveries 
resulted in platinum production only rising by 5% to 20 000 ounces of platinum 
in concentrate. 
 
Zimplats 
 
Zimplats' platinum production in matte was up 22% in line with a 20% increase 
in tonnes milled. This is reflective of the ramp up of the Phase 1 expansion 
and the commissioning of the new concentrator which occurred in September 2009. 
The Phase 2 expansion project has commenced with the earthworks for the Portal 
3 boxcut scheduled for completion in the second quarter of FY2011. This project 
will take production to 270 000 ounces of platinum by 2013. 
 
Mimosa 
 
Mimosa achieved a marginal improvement in tonnes milled which resulted in 
record quarterly platinum in concentrate production of 27 000 ounces. The 
operation is running at steady-state production of 100 000 ounces of platinum 
in concentrate per annum. 
 
IRS 
 
IRS' refined platinum production declined by 19% quarter on quarter due to the 
timing of a portion of deliveries. These deliveries will be processed in the 
second quarter. 
 
17 November 2010 
 
Johannesburg 
 
Issued by sponsor: Deutsche Securities (SA) (Proprietary) Limited 
 
 
 
END 
 

Impala Platinum (LSE:IPLA)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Impala Platinum Charts.
Impala Platinum (LSE:IPLA)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Impala Platinum Charts.