TIDMKDNC

RNS Number : 4059L

Cadence Minerals PLC

03 January 2023

Cadence Minerals Plc

("Cadence Minerals", "Cadence", or "the Company")

Pre-Feasibility Study Delivers Robust Economics for the Amapá Iron Ore Project, Brazil

Post-Tax Project NPV US$949 million, Internal Rate of Return of 34% and a Project Maiden Ore Reserve Estimate of 195.8 Mt (Cadence attributable of 58.74 Mt) at 39.34% Fe Declared

Cadence Minerals (AIM/NEX: KDNC; OTC: KDNCY) is pleased to announce the completion of the Pre-Feasibility Study ("PFS") on the Amapá Iron Ore Project, Brazil ("Amapá" or the "Project").

The PFS confirms the potential for the Amapá Iron Ore Project to produce a high-grade iron ore concentrate and generate strong returns over its life of mine. Completing the PFS is a significant milestone in the Project's development, laying the foundations to advance Amapá to eventual production.

Cadence holds a 30% interest in Pedra Branca and, consequently, a 30% interest in the Amapá Project and has a first right of refusal to increase its interest to 49%.

The PFS was managed by Pedra Branca Alliance Pte. Ltd. ("PBA"), Cadence and Indo Sino Pte. Ltd. ("Indo Sino") and has been compiled by Wardell Armstrong International ("WAI"). WAI is a leading, globally recognised mining consultancy with a track record of conducting all levels of technical study required on projects that have successfully been financed and developed into mining operations.

PFS Highlights:

Ø Annual average production after ramp-up of 5.28 million dry metric tonnes per annum ("Mtpa") of Fe concentrate, consisting of 4.36 Mtpa at 65.4% Fe and 0.92 Mtpa at 62% Fe concentrate.

Ø Post-tax Net Present Value ("NPV") of US$949 million ("M") at a discount rate of 10%, with profit after tax of US$2.96 billion ("B") over Life of Mine ("LOM") gross revenues of US$9.39 B over LOM.

Ø Post-tax Internal Rate of Return of 34%, with an average annual LOM EBITDA of US$235 M per annum.

Ø Maiden Ore Reserve of 195.8 million tonnes ("Mt") at 39.34% Fe, demonstrating an 85% mineral resource conversion.

Ø Free on Board ("FOB") C1 Cash Costs of US$35.53/dmt at the port of Santana. Cost and Freight ("CFR") C1 Cash Costs US$64.23/dmt in China.

Ø After applying tax rebates, a pre-production capital cost estimate of US$399 M, including the improvement and rehabilitation of the processing facility and the restoration of the railway and the wholly owned port export facility, cost estimations have a PFS level of accuracy at +/- 25%.

Ø Key assumptions: Long-term average price for 62% iron ore concentrate of US$95/dmt and US$23.8/dmt premium for 65.4% iron ore concentrate, both quoted on a Cost and Freight ("CFR") basis.

Ø Opportunities: exploration target at the Tucano Mine to further extend initial mine life and potential capital savings at port loading facilities.

Based on the positive outcome of the PFS, the owner of the Project DEV Mineração S/A ("DEV") intends to advance the Project. The initial works will include optimising the capital expenditure, optimising processing plant availability and efficiency and developing the adjacent exploration targets to increase the mine life, after which work on a Feasibility Study can begin.

Cadence CEO Kiran Morzaria commented: "On behalf of the Cadence Board, we are pleased and proud to release the Pre-Feasibility Study for the Amapá Iron Ore Project in Brazil. This study, which we consider to be a definitive moment for our company, re-enforces Cadence's analysis that the Amapá Project can be regenerated and restarted on a profitable basis over an initial 16-year mine life."

"The Study outlines a robust 5.28 Mtpa operation which can deliver excellent cash flows, and a post-tax NPV of US$949 million producing 4.36 Mtpa of 65.4% iron ore concentrate and 0.92 Mtpa of 62% iron ore concentrate."

"We are also pleased to declare a maiden Ore Reserve of 195.8Mt at 39.34%, representing 85% resource to reserve conversion and confirming the robust project fundamentals."

"The Project benefits from integrated infrastructure under the owner's control, a well-established processing route, low capital intensity and a quality product with an international reputation. Along with a skilled workforce, proximity to operational infrastructure and the potential to increase the mineral resource means that Amapá remains an incredibly attractive investment opportunity."

"The opportunity for DEV is to advance the Amapá Iron Ore Project to a Financial Investment Decision. This could be completed along with securing a strategic investor, offtake partner, separate listing, or a combination of these options. However, we recognise that there is still much work to complete at Amapá, which will ultimately deliver a Feasibility Study."

"I look forward to reporting further progress across all our projects in the coming months."

Table 1.1 Key Project Metrics (100% project basis)

 
 Metric                                  Unit        2022 PFS 
                                                      Data 
 Total ore feed to the plant             Mt (dry)    176.88 
                                        ----------  --------- 
 Life of Mine                            Years       16 
                                        ----------  --------- 
 Fe grade of ore feed to 
  the plant                              %           39.34 
                                        ----------  --------- 
 Recovery                                %           76.27 
                                        ----------  --------- 
 62.0% iron ore concentrate 
  production                             Mtpa        0.89 
                                        ----------  --------- 
 65.4% iron ore concentrate 
  production                             Mtpa        4.23 
                                        ----------  --------- 
 C1 Cash Costs FOB *                     US$/dmt     35.53 
                                        ----------  --------- 
 C1 Cash Costs CFR **                    US$/dmt     64.23 
                                        ----------  --------- 
 Pre-Production capital investment***    US$M        399 
                                        ----------  --------- 
 Sustaining capital investment 
  over LOM****                           US$M        245 
                                        ----------  --------- 
 Post-tax NPV (10%)                      US$M        949 
                                        ----------  --------- 
 Post-tax IRR                            %           34 
                                        ----------  --------- 
 Project payback                         Years       4 
                                        ----------  --------- 
 Total profit after tax (net 
  operating profit)                      US$B        2.96 
                                        ----------  --------- 
 
 
    *   Means operating cash costs, including mining, processing, 
         geology, OHSE, rail, port and site G&A, divided by the tonnes 
         of iron ore concentrate produced. It excludes royalties 
         and is quoted on a FOB basis (excluding shipping to the 
         customer). 
   **   Means the same as C1 Cash Costs FOB; however, it includes 
         shipping to the customer in China (CFR). 
  ***   Includes direct tax credit rebate over 48 months 
 ****   Includes both sustaining CAPEX and deferred capital expenditure, 
         specifically, improvements to the railway and the installation 
         of conveyor belt and mine site to rail load out 
 

Summary of Amapá Iron Ore Project PFS Results

The information in the press release contains a summary of the PFS and its results

Introduction

The Project consists of an open-pit iron ore mine, a processing and beneficiation plant, a railway line, and an export port terminal. DEV and its subsidiaries own the Amapá Project. DEV is owned by PBA, a joint venture between Cadence Minerals Plc ("Cadence") and Indo Sino Trade Pte Ltd ("Indo Sino").

The Project ceased operations in 2014 after the port facility suffered a geotechnical failure, which limited the export of iron ore. Before the cessation of operations, the Project generated an underlying profit of US$54 million in 2012 and US$120 million in 2011 ([1]) . Operations commenced in December 2007, and in 2008, the Project produced 712 thousand tonnes of iron ore concentrate. Production steadily increased, producing 4.8 Mt and 6.1 Mt of iron ore concentrate products in 2011 and 2012, respectively.

DEV continued to operate the Project and rehabilitate the port up until 2014. However, due to the restricted iron ore exports, and cash flow constraints, in August 2015, DEV filed for judicial protection in Brazil, and operations at the Project ceased.

In 2019 Cadence and Indo Sino, alongside DEV, submitted a judicial restructuring plan ("JRP") for approval by the unsecured creditors. As part of the JRP, DEV sought to redevelop the Amapá Project. This strategy includes a plan to resume operations after plant revitalisation and modifications, aimed at improving product quality and increasing recovery, along with recovery of the port, railway, and support areas.

It should be noted that the Amapá Project, and Pre-Feasibility Study ("PFS"), has been managed by Indo Sino and Cadence in co-operation with Wardell Armstrong International ("WAI"); the latter has reviewed the work completed and compiled the PFS. The PFS and supporting reports, engineering designs and data are the sole property of PBA.

The Mineral Resource and Ore Reserve statements have been prepared in accordance with the Guidelines of the Australasian Code for Reporting of Exploration Results, Mineral Resources, and Ore Reserves, the JORC Code, 2012 Edition (JORC Code (2012)). Cost estimations were prepared by DEV, with input from third-party independent engineers and subsequently reviewed by WAI using the internationally accepted practice for PFS-level studies.

Location

The Amapá Project is in Amapá state, northeast Brazil. Amapá is the second least populous state and the eighteenth largest by area. Most of the Amapá state territory is covered with rainforest, while the remaining areas are covered with savannah and plains. The State capital and largest city is Macapá (pop. circa 500,000), with the similarly sized municipality of Santana (pop. circa 120,000) located just 14 km to the southwest.

The Amapá mine is some 125 km northeast of the state capital Macapá, and the port facility is located on the Amazon River in the municipality of Santana, close to Macapá, as shown in the figure here.

The port site in the municipality of Santana is located 90 km from the mouth of the Amazon River. The nearest populace centre to the Amapá mine is Pedra Branca Do Amapari, some 10 km west, with the larger conurbation of Serra do Navio 18 km to the northwest.

Amapá Project Components

The Amapá Project PFS encompasses four distinct but completely integrated operational components that form part of the study, as illustrated in the figure here .

Amapá Mining Complex

An open-pit iron ore mine with various open pits, an iron ore concentration and beneficiation plant, associated waste rock dumps, and a tailings management facility.

Railway Line

Integrated 194 km railway line connecting Serra do Navio to the port terminal at Santana. The rail passes via Pedra Branca do Amapari (180 km from the port), located 13 km away from the Amapá mine and plant complex by graded road.

Export Port Terminal

An integrated industrial port site, privately-owned and controlled by DEV, is located in Santana. The terminal had the capacity for loading Supramax and Handymax vessels.

Transhipment Solution

A Capesize vessel is partially loaded at the berth in Santana port and topped off in the open ocean, 200 nautical

miles from the berth.

Pre-Feasibility Study

The PFS scope covers the existing mine, plant, rail, and port. Capital and operational estimates were developed for refurbishing the facilities to a safe working level. The study investigates all the design and business parameters necessary to operate the Amapá Project, including the railway system and privately owned port for loading vessels with iron ore concentrate. It has also included an upgrade to the existing plant with new equipment and improved efficiency to produce 4.36 Mtpa of Blast Furnace Pellet Feed ("BFPF") and 0.92 Mtpa of spiral concentrate, a total of 5.28 Mtpa (on a dry basis).

Cost Estimates

The capital costs ("CAPEX") estimate is based on the layout for all areas of the Project and is supported by mechanical equipment lists and engineering drawings. The costs for these items have been derived from vendor quotes for the equipment and materials or consultant engineering databases. The CAPEX estimate is after tax (any duties and taxes deemed to be recoverable are calculated separately), includes contingency, and excludes escalation. The CAPEX estimate includes all the direct and indirect costs, local taxes and duties and appropriate contingencies for the facilities required to bring the Project into production, as defined by a Pre-Feasibility level engineering study.

As this is a PFS, the cost accuracy is estimated at +/- 25% and has a base date of June 2022. Pre-Production capital cost estimates are provided below.

Table 1.2 Pre-Production capital cost estimates

 
 Description                             (US$M) 
 Direct Capex Mining                     2.8 
                                        ------- 
 Direct Capex Beneficiation Plant and 
  Mining                                 155.1 
                                        ------- 
 Direct Capex Rail                       28.5 
                                        ------- 
 Direct Capex Port                       113.9 
                                        ------- 
 Sub-total Direct Capex                  300.4 
                                        ------- 
 Sub-total Indirect Capex                65.2 
                                        ------- 
 Environment and Community Cost          7.1 
                                        ------- 
 Deduct Tax Credit                       25.6 
                                        ------- 
 Contingency                             52.1 
                                        ------- 
 Pre-Production Capex Cost               399.1 
                                        ------- 
 

Table 1.3 Deferred, sustaining, and closure capital costs over LOM

 
 Description                                (US$M) 
 Capex Tailings Storage Facility ("TSF")    9.8 
                                           ------- 
 Capex Rail (2(nd) Phase)                   20.0 
                                           ------- 
 Capex Conveyor Belt                        61.2 
                                           ------- 
 Stay in Business                           90.7 
                                           ------- 
 Closure Costs                              62.8 
                                           ------- 
 Sustaining Capex Cost                      244.5 
                                           ------- 
 

Operating expenditures ("OPEX") for the Project have been prepared based on the Project physicals, detailed estimates of the consumption of key consumables based on those physicals, and the unit cost of consumables.

The periods considered are annual, and production follows the production plan produced by DEV, based on a yearly output of 4.36 Mtpa of BFPF and 0.92 Mtpa of spiral concentrate, a total of 5.28 Mtpa (on a dry basis).

OPEX comprises physicals, labour, reagents and operating consumables, freight and power costs, mobile equipment, utilities, maintenance and mining contract costs, external contractor costs, environmental, and miscellaneous/other General and Administrative (G&A) expenses. OPEX estimates were prepared or advised by independent consulting engineers. The estimate is supported by engineering, benchmarking, and pricing of key consumables and costs were derived from past production figures and informal quotes from suppliers. The table below illustrates the operating costs developed by discipline during the PFS. The project FOB and CFR average cash cost per tonne of dry product over the LOM is summarised below.

Table 1.4 FOB and CFR average cash cost per tonne of dry product over the LOM

 
 Cash Cost Per Discipline                US$/dmt 
 Mine                                    17.05 
                                        -------- 
 TSF                                     0.08 
                                        -------- 
 Beneficiation Plant, Road / Conveyor 
  Transfer & Rail Loading                12.43 
                                        -------- 
 Rail Freight                            2.43 
                                        -------- 
 Port                                    1.55 
                                        -------- 
 G & A (5% total cost)                   1.99 
                                        -------- 
 FOB Cash Costs                          35.53 
                                        -------- 
 Marine Logistics                        28.70 
                                        -------- 
 CFR Cash Costs                          64.23 
                                        -------- 
 

Project Financial Analysis

A PFS financial model was developed to evaluate the economics of the Project. Summary results from the financial model outputs are presented in tables within this section, including financial analysis. The financial model considers 100% equity funding for the Project, although, in reality, the financing of the Project will be a mix of debt and equity. However, the existing obligations in terms of principal repayment and current interest liabilities payable have been included in the financial model. A summary of the key financial information is presented below.

Table 1.5 Summary of key financial information for the Project.

 
 Item Over Life of Mine            Unit    2022 PFS 
                                            Data 
 Gross revenue                     US$M    9,387 
                                  ------  --------- 
 Freight (Maine Logistics)         US$M    (2,350) 
                                  ------  --------- 
 Net Revenue                       US$M    7,037 
                                  ------  --------- 
 Operating costs                   US$M    (2,910) 
                                  ------  --------- 
 Royalties and taxes (excluding 
  income tax)                      US$M    (373) 
                                  ------  --------- 
 EBITDA                            US$M    3,754 
                                  ------  --------- 
 EBIT                              US$M    3,315 
                                  ------  --------- 
 Net Taxes and Interest            US$M    355 
                                  ------  --------- 
 Net Operating Profit              US$M    2,960 
                                  ------  --------- 
 Initial, Sustaining capital 
  costs & repayments               US$M    727 
                                  ------  --------- 
 Free Cash Flow                    US$M    2,672 
                                  ------  --------- 
 
 
 Item               Unit     2022 PFS 
                              Data 
 LOM                Years    16 
                   -------  --------- 
 Discount rate      %        10 
                   -------  --------- 
 NPV                US$M     949 
                   -------  --------- 
 IRR                %        34 
                   -------  --------- 
 Project Payback    Years    4 
                   -------  --------- 
 

Project Sensitivity Analysis

A sensitivity analysis was performed on key parameters within the financial model to assess the impact of changes on the post-tax NPV of the Project (debt-free). To examine the sensitivity of the Project base case NPV the economic and operational conditions of each cost factor were independently varied within a range of +/- 30%, and discount rates were changed within the 8%-15% range.

Project sensitivity analysis demonstrates that the Amapá Project is most sensitive to a change in iron ore concentrate price, followed by logistics costs (marine shipment charges) and operating costs. It was least sensitive to deviation in CAPEX. The figure here shows the results of the project sensitivity analysis.

Mineral Resource Statement

The MRE was previously reported on 7 October 2022 and is available here . The MRE has been reported at a cut-off grade of 25% Fe constrained by a resource open pit and the topography dated April 2014 (grey surface in the figure here ), in line with the Reasonable Prospects For Eventual Economic Extraction (RPEEE) principle. The MRE has been estimated, considering a product revenue of US$120/t. The geotechnical parameters, metallurgical recovery and updated mining costs were all provided by DEV.

Table 1.6 Summary of gross and attributable Mineral Resources for the Amapá Iron Ore Project. Attributable tonnage to Cadence is based on a 30% interest in the Project.

 
Classification   Tonnage  Attributable   Fe (%)  SiO(2)  Al(2)  P (%)  Mn (%) 
                   (Mt)    Tonnage (Mt)            (%)    O(3) 
                                                          (%) 
Measured          55.33       16.60      39.26   30.40   6.54   0.161   1.03 
                 -------  -------------  ------  ------  -----  -----  ------ 
Indicated        174.15       52.25      38.60   28.75   7.86   0.156   0.91 
                 -------  -------------  ------  ------  -----  -----  ------ 
Meas. + 
 Ind             229.48       68.84      38.76   29.15   7.54   0.157   0.94 
                 -------  -------------  ------  ------  -----  -----  ------ 
Inferred          46.76       14.03      36.20   27.62   10.49  0.139   0.86 
                 -------  -------------  ------  ------  -----  -----  ------ 
 TOTAL           276.24       82.87      38.33   28.89   8.04   0.154   0.93 
                 -------  -------------  ------  ------  -----  -----  ------ 
 

Notes:

(1) The Mineral Resource is considered to have reasonable prospects for eventual economic extraction based on an optimised pit shell

(2) Cut-Off Grade reported within an optimised pit and above a cut-off grade of 25% Fe applied

(3) Tonnages are reported as wet tonnes

(4) Mineral Resources are not reserves until they have demonstrated economic viability based on a Feasibility Study or Pre-Feasibility Study

(5) The Mineral Resource Estimate has an effective date of 31 August 2022

(6) Mineral Resources have been classified in accordance with the Australian Code for Reporting of Exploration Results. Mineral Resources and Ore Reserves (JORC Code 2012)

(7) The attributable tonnes represent the part of the Mineral Resource that will be attributable to Cadence Minerals' 30% interest in the Project

(8) The operator is DEV

As required per the JORC Code 2012, Table 1 for reporting MREs is available here .

Ore Reserve Statement

The mine engineering and design work for this PFS, including operational logistics, equipment requirements, mining strategy, and Ore Reserve Estimation, have been undertaken by a Brazilian mining consultancy, Prominas Mining Ltd ("Prominas"). These works have been conducted at the PFS level and incorporate an Ore Reserve Estimate for open pit mining, which was prepared under the guidelines of the JORC Code (2012).

Under the guidelines of the JORC Code (2012), an 'Ore Reserve' is the economically mineable part of a Measured and/or Indicated Mineral Resource. It includes diluting materials and allowances for losses, which may occur when the material is mined or extracted and is defined by studies at Pre-Feasibility or Feasibility level as appropriate that include the application of considerations to convert Mineral Resources to Mineral Reserves. These considerations include, but are not restricted to, mining, processing, metallurgical, infrastructure, economic, marketing, legal, environmental, social, and governmental factors, called 'Modifying Factors'. Such studies demonstrate that, at the time of reporting, the economic extraction could reasonably be justified.

Prominas has estimated the Ore Reserve for the Amapá Project at 195.8Mt at an average grade of 39.34% Fe, at a cut-off grade of 25% Fe, as presented in the table below.

Table 1.7 Amapá Project Ore Reserve Estimate (JORC Code (2012)) valid on 5 October 2022, DEV Mineral Rights - Fe >= 25. Attributable tonnage to Cadence is based on a 30% interest in the Project.

 
Classification        Material       Tonnage  Attributable            Head Grades (%) 
                                       (Mt)      Tonnage 
                                                  (Mt) 
                                                             Fe    SiO(2)  Al(2)    P      Mn 
                                                                            O(3) 
                                                            -----  ------  -----  -----  ------- 
                 Friable Altered 
    Proven        Itabirite           30.3        9.09      38.88  29.72   7.29   0.169   1.19 
                 ------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Friable Itabirite                    13.7        4.11      39.51  36.37   2.88   0.086   0.90 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Friable Hematite                      0.7        0.21      62.53   4.40   2.23   0.227   0.39 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Colluvium                             5.2        1.56      39.18  20.89   11.90  0.185   0.72 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Canga                                 0.8        0.24      49.99   5.81   10.53  0.964   0.19 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Sub-total                            50.7       15.21      39.58  29.88   6.56   0.162   1.04 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
                 Friable Altered 
   Probable       Itabirite           51.6       15.48      38.34  30.63   6.84   0.174   1.25 
                 ------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Friable Itabirite                    30.9        9.27      40.28  34.75   3.02   0.101   0.92 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Friable Hematite                      1.5        0.45      57.22  13.11   2.30   0.114   0.43 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Colluvium                            56.6       16.98      38.33  22.60   11.71  0.144   0.60 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Canga                                 4.5        1.35      48.68   9.03   10.12  0.587   0.22 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
 Sub-total                            145.1      43.53      39.26  27.53   7.98   0.159   0.89 
 ----------------------------------  -------  ------------  -----  ------  -----  -----  ------- 
               TOTAL                  195.8      58.74      39.34  28.14   7.61   0.160   0.93 
                                     -------  ------------  -----  ------  -----  -----  ------- 
 
 

Notes:

   (1)    The effective date of the Ore Reserve Estimate is 5 October 2022. 
   (2)    Ore Reserves are reported per the guidelines of the JORC Code (2012). 
   (3)    The Ore Reserve Estimate is reported to a cut-off of 25% Fe. 

(4) Ore Reserves were estimated at a selling price of US$120/t (FOB) and include modifying factors related to geotechnical parameters, mining cost, dilution and recovery, process recoveries and costs, G&A, royalties and rehabilitation costs.

(5) A mining dilution factor of 3.0% and a mine recovery of 94% has been estimated and applied for the Ore Reserve Estimate.

(6) Figures have been rounded to an appropriate level of precision for the reporting of Ore Reserves.

   (7)    Due to rounding, some columns or rows may not compute exactly as shown. 
   (8)    The Ore Reserves are stated as wet (in-situ) tonnes processed at the crusher. 
   (9)    All figures are in metric tonnes. 

The Ore Reserve contains only those Mineral Resources which are classified as Measured and Indicated and constrained by an economically and technically mineable engineered pit design, as described previously. The Ore Reserve has also been constrained by the property boundary and considering the position of existing and planned surface infrastructure.

The Competent Person utilised project-specific technical and economic Modifying Factors to estimate the Ore Reserves at Amapá. Sufficient mining and metallurgical work have been completed - and is further reinforced by historical production data - to support the Ore Reserve Estimate.

The Competent Person understands that the Ore Reserve Estimate can be affected by unforeseen metallurgical, environmental, permitting, legal, title, taxation, socio-economic, marketing, or political issues. However, concerning environmental, licensing, legal, title, tax, and marketing considerations, the Competent Person, has relied upon the information presented in the full PFS report. As required per the JORC Code 2012, Table 1, needed for the reporting of Ore Reserves, is available here .

Mine Design

Pit designs and pushbacks were generated using MinePlan(R) software and adopting preliminary geotechnical, hydrological, cost and density parameters. The designs include benches, berms, and haul roads. The final pit mine design is presented in the figure here .

A LOM production plan was scheduled using the MinePlan(R) Scheduler Optimiser. The solids used in the mine schedule were based on the final pit design, with an SMU (Selective Mining Unit) of 100 m x 200 m x 4 m. The mining schedule per year is over 13 pits and is shown in the figure here .

Mining

Mining at the Amapá mine will use conventional open pit methods involving drilling, blasting, loading, and hauling ore and waste by a mining contractor. Operations will be conducted based on 365 operating days per year with three 8-hour shifts per day. An allowance has been made for the weather. Ore production is planned at an optimum rate of 12.6 Mtpa. Generally, the total rock mining rate (ore + waste) has been kept below 20 Mtpa. Grade control drilling will be used to delineate the ore zones for excavation as well as low-grade material and waste. Drilling and blasting of ore and waste rock will be required, while overburden materials will be free digging. Ore and waste will be loaded into 100 t capacity off-highway haul trucks to stockpiles, designated waste dumps, or used for construction of the TSF.

Extraction, loading, hauling, and disposal of ore and waste, internal materials handling, mining access opening and maintenance, drainage system operation, and maintenance will all be undertaken by, and the responsibility of, a specialist mining contractor under the management supervision of DEV. For the PFS, DEV obtained a mining cost quote from an experienced Brazilian mining contractor with over 14 years of operational experience in the mining and heavy construction markets.

Processing

Historically the beneficiation plant at the Amapá Project produced four product iron ore concentrates. The development strategy of DEV was to simplify the product stream and focus on higher grade and higher value products, albeit at a lower volume than historical production. The plan is to produce 5.28 Mtpa (dry) of Fe concentrate, consisting of 4.23 Mtpa at 65.4% Fe and 0.92 Mtpa at 62% Fe concentrate. Due to the production history and the metallurgical test work previously completed to achieve the production targets, no further test work was carried out for this PFS.

As far as processing engineering, there were two main work programmes. The first was assessing the current condition of the plant and infrastructure and the work required to refurbish the plant back to its previous state. The second was the flowsheet upgrade and improvements needed to achieve the production mix and targets as proposed within the PFS. ECM Projetos Industriais ("ECM"), who constructed the original Amapá processing plant, was responsible for designing and costing the required process flowsheet modifications and upgrades. ECM conducted an independent analysis of all the data and information available to validate it as the basis for the process design requirements of the PFS Study.

In summary, the process flow sheet consists of an initial crushing, screening, and homogenisation stage. This process produces two streams of crushed ore. The first stream is a +1mm -12mm product fed into the first milling circuit, magnetic separators and then to a desliming circuit before floatation.

The second stream is a -1mm product passed through a spiral circuit to produce a 62% Fe spiral concentrate. Various other flows from the second stream then report either back to the first milling circuit, the second ball mill circuit or the new magnetic separator circuit. The product from the new magnetic separator circuit is sent back to the first milling and then onto a desliming circuit before floatation.

The feed to the deslime circuit consists of the second milling ground product, the first milling circuit magnetic concentrate and the spiral concentrate dewatering screen undersize streams. Desliming occurs via three stages of hydrocyclones. The second and third-stage underflow streams are combined to report to the reverse floatation circuit.

The feed from the desliming circuit is sent to conditioning tanks, where the material is prepared for reverse floatation. The reverse floatation consists of two rougher stages and a final cleaner stage, where the floatation cell tails form the feed for the next step. The final cleaner produces an iron concentrate in which the silica and other impurities have been floated off. This iron concentrate is fed into a concentrate thickener which increases sedimentation. This stream then reports to the filter plant. The filtered concentrate is conveyed to a sampling system and then to the 65.4% Fe BFPF product stockpile. A summary of the process flow sheet can be found here .

Infrastructure

The surface infrastructure from the previous mining and processing operations still exists, including roads, administrative buildings, workshops, and processing buildings. When the mine closed, the mine's facilities, processing plant, railway and port fell into disrepair. DEV has already begun the rehabilitation of some of the administrative buildings. The intent is to rehabilitate this infrastructure as part of the restart of the Amapá Project, and the costs associated with this were included in the PFS CAPEX.

The Amapá mine's previous demand was stated as 25 MW; the new power requirement is 30 MW. The existing transmission line, at 69 kV voltage, which interconnects the UHE Coaracy Nunes (Hydroelectric Dam) to Serra do Navio, will not support Amapá mine's power requirement.

DEV has been in discussion with Companhia de Eletricidade do Amapá ("CEA") and has been informed that CEA is upgrading the regional transmission lines. CEA intends to construct and upgrade the current transmission line at a voltage of 138 kV from UHE Coaracy Nunes to Pedra Branca do Amapari, then to the plant, connecting to a new 138 kV - 30 MVA substation which DEV will construct. The CEA project timeline for this upgrade is in line with the development timeline of the Amapá Project. Power to the port is provided via connection to the Santana grid provided by CEA and is not expected to require any significant upgrade.

The water supply for the processing plant will come from the accumulated water in the TSF's water retention ponds. In addition to the TSF return water from normal operations, fresh water will be taken from a local creek and pumped to the TSF. A separate line from the TSF's return water supply will supply the potable water plant for potable water requirements.

Logistics

As mentioned, DEV owns or has concessions over the key logistics from the mine site to loading vessels at the Port of Santana on the Amazon River. The key logistical components are shown in the figure here .

The access haul road, approximately 13 km in length, is used to access the mine and haul concentrates between the concentrate stockpiles and the railhead at Pedra Branca do Amapari. The option to construct an overland conveyor belt to replace the truck haulage operation is viewed as the best way forward, and this has been included in the process plant upgrade work undertaken by ECM. This work will be completed in the initial two years after start-up.

The rail infrastructure is standard gauge and is 194 km in length, with a distance of 180 km between the railhead and the port. The capital expenditure on the railway will occur over two stages, the latter occurring as deferred CAPEX. Once the second stage of investment is completed, the estimated cargo handling capacity of the railway is estimated to be 6.4 million wet tonnes of ore.

The original port facility was constructed in the 1950s to handle manganese ore and consists of a rail loop, dual bottom-car dumper, central out load conveyor with stacker and reclaimer connected to a floating dock. In March 2013, the port suffered a failure. After the failure, DEV engaged an EPCM contractor to oversee the design and reconstruction of the port facility and associated works. Phase one of the work was completed; however, due to the iron ore price, the construction work stopped shortly after in 2014. Since operations ceased, the port was abandoned and fell into disrepair. The PFS study and CAPEX anticipate the continuation of the works per the EPCM contractor design. The repair of the jack-up rig and the rehabilitation of the port facilities. The figure here shows the planned materials handling and ship loading at the Santana port.

Mineral Title / Permitting

DEV and its subsidiaries own the Amapá Project and its licenses, mining rights and concessions. As the Project was previously operating, it held all the necessary permission to operate. However, since it ceased operations, many have lapsed.

DEV owns four Mining Concessions. The first three concessions are for iron ore, and the last is a gold extraction license. DEV has a joint venture with Mina Tucano Ltda ("Mina Tucano"), which allows Mina Tucano to mine gold and allows DEV to mine iron ore from Mina Tucano's license. None of the historical mineral resources on license Mina Tucano is included as part of this PFS.

Although DEV owns the Mining Concessions, it does not currently have a Mine Extraction and Processing Permit. To do so, DEV must obtain an Operational License ("LO") from the state environment authority. Once this has been completed, DEV will apply for Mine Extraction Permit. Since the Project was acquired by its current owners in 2022, DEV has been making the required regulatory filings and embarking on studies and maintenance works to comply with the National Mineral Agency requirements.

Before the suspension of mining, the Project had numerous LOs across the mining, rail, and port operations. These LOs expired between 2013 and 2018. In 2022 DEV began the regularisation of the expired environmental permits. In consultation with the Amapá State Environmental Agency, and the relevant state authorities, DEV has requested that the requirement for an environmental impact study be waived. This request for a waiver was on the basis that the previous LOs were granted on an operation that is substantially the same as is currently planned and remains applicable to future operations. DEV proposes that the company submit an Environmental Control Plan - "PCA" (Plano de Controle Ambiental); and Environmental Control Report - "RCA" (Relatório de Controle Ambiental). DEV has begun its proposed permit pathway for the Project based on the above requirements of a PCA and RCA.

The proposed permit pathway for the Project has both legal and practice precedent and is a reasonable approach, given the Projects status and level of development.

The state owns the railway line and associated land; therefore, for the Project to utilise this, it requires both the LO and a concession agreement with the State of Amapá. The previous operators of the Project were granted this concession in 2006 for 20 years under specific terms and conditions. The reinstatement of this concession to one of DEV's 100% owned subsidiaries was in December 2019 and was extended to 2046. The concession allows DEV's 100% owned subsidiary to operate the railway to primarily transport iron ore from the mine to its port in Santana. The State of Amapá owns the surface rights associated with the railway, and under the Railway Concession, DEV has been granted use over these surface rights.

In addition to the LO detailed above, the company's port is regulated by the Agencia Nacional de Transportes Aquaviários ("ANTAQ"). As a result of the change of ultimate beneficiary of DEV, a change of control request was filed. This change of control was granted in November 2021. As part of the port change of control, ANTAQ has agreed to cease the recommended abrogation of the port concession. DEV owns the surface rights associated with the port.

The principal surface rights applicable to the Project are those above the mining concessions, those associated with the railway from the mine to the port and those associated with the port in Santana, Amapá. The surface rights above the Mining Concessions cover approximately 5,580 ha. DEV has lease agreements which cover this area.

Competent Person's Statement

The information that relates to Mineral Resources and Ore Reserves is based on information compiled by Geraldo Majella, who is an associate of Prominas and a Member of the Australian Institute of Geoscientists (AIG). Geraldo Majella has sufficient relevant experience to the style of mineralisation and type of deposit under consideration and to the activity for which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for reporting of Exploration Results, Exploration Targets, Mineral Resources and Ore Reserves" (JORC Code). Geraldo Majella consents to the inclusion in the announcement of the matters based on their information in the form and context in which it appears and confirms that this information is accurate and not false or misleading.

Kiran Morzaria has also reviewed and approved the technical information in his capacity as a Qualified Person under the AIM Rules.

Opportunities

The PFS identified several opportunities that DEV intends to investigate further before the start of the feasibility study.

Mina Tucano Exploration Target

DEV has a right to explore mine for iron ore on Mina Tucano's licenses. In 2011 DEV evaluated all the historical drilling on this license and further explored the license. DEV evaluated some 986 holes to establish a mineral resource estimate. The mineral recourse was estimated at a 25% Fe cut-off, 142.51 Mt at 36.77% Fe. This estimate covered measured, indicated, and inferred mineral resources. This historical mineral resource estimate cannot be considered a mineral resource estimated under JORC 2012.

The initial data and core will need to be reviewed and audited to develop this exploration target, and additional resource drilling will need to be carried out. From this, if applicable, a JORC 2012mineral resource could be estimated.

Port Loading Configuration

As part of a trade-off study on port loading, consulting engineers identified a modification of the railway loop and a change in the stockpile arrangement and associated product transportation. If these could be achieved, it would substantially reduce the retaining wall costs, as the rail loop would be moved approximately 100 m further away from the riverbank.

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

Cautionary and Forward-Looking Statements

Certain statements in this announcement are or may be deemed to be forward-looking statements. Forward-looking statements are identi ed by their use of terms and phrases such as "believe", "could", "should", "envisage", "estimate", "intend", "may", "plan", "will", or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the company's future growth results of operations performance , future capital, and other expenditures (including the amount, nature, and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward-looking statements re ect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes actions by governmental authorities, the availability of capital markets reliance on key personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that actual results will be consistent with such forward-looking statements.

The Ore Reserve and Mineral Resource Estimate have been prepared by Competent Persons, with Competent Person's Statements at the end of the release. The Ore Reserves and Mineral Resources that underpin the production target have been prepared by a Competent Person that meets the requirements of the JORC Code.

The PFS developed engineering designs to provide costs at a +/- 25% level of accuracy. The company has concluded that it has a reasonable basis for giving the forward-looking statements and forecasted financial information included in this announcement.

This announcement has been prepared in accordance with JORC code 2012 and AIM listing rules. All material assumptions relating to production and financial forecasts are detailed in this report. Material and economic assumptions are summarised in the body of this release. Rounding may cause some computational discrepancies for totals in the tables in this announcement.

The information contained within this announcement is deemed by the company to constitute Inside Information as stipulated under the Market Abuse Regulation (EU) No. 596/2014, as it forms part of UK domestic law under the European Union (Withdrawal) Act 2018, as amended. Upon the publication of this announcement via a regulatory information service, this information is considered to be in the public domain.

 
 For further information 
  contact: 
 Cadence Minerals plc           +44 (0) 20 3582 6636 
 Andrew Suckling 
 Kiran Morzaria 
 
 
   WH Ireland Limited (NOMAD 
   & Broker)                      +44 (0) 207 220 1666 
 James Joyce 
 Darshan Patel 
 

Glossary

 
 Al(2) O(3)           Aluminium oxide is a chemical compound of aluminium 
                       and oxygen 
 C1 Cash Costs        Means operating cash costs, including mining, processing, 
                       geology, OHSE, rail, port and site G&A, divided 
                       by the tonnes of iron ore concentrate produced 
 Canga                An iron-rich rock formed where material weathered 
                       from an original iron ore deposit has been cemented 
                       by iron minerals. 
 Colluvium            Loose, unconsolidated material that accumulates 
                       above the weathering iron ore bodies. 
 Core                 A cylindrical section of a naturally occurring 
                       substance. Most core samples are obtained by drilling 
                       with special drills into the substance, such as 
                       sediment or rock, with a hollow steel tube called 
                       a core drill . The hole made for the core sample 
                       is called the "core hole." 
 Cut-off grade        The lowest grade of mineralised material that qualifies 
                       as ore in a given deposit or rock of the lowest 
                       assay is included in an ore estimate. 
 Discount             The interest rate is used in discounted cash flow 
  rate                 analysis to determine the present value of future 
                       cash flows. 
 Drillhole            A drill hole is formed by the act or process of 
                       drilling boreholes using bits s the rock-cutting 
                       tool. The bits are rotated by various types and 
                       sizes of mechanisms motivated by steam, internal 
                       combustion, hydraulic, compressed air, or electric 
                       engines or motors. 
 EBITDA               Earnings before interest, taxes, depreciation, 
                       and amortisation is an alternate measure of profitability 
                       to net income. By stripping out the non-cash depreciation 
                       and amortisation expense as well as taxes and debt 
                       costs dependent on the capital structure, EBITDA 
                       attempts to represent cash profit generated by 
                       the company's operations. 
 EPC                  means a company is contracted to provide engineering, 
                       procurement and construction services by the owner. 
                       The EPC contractor has direct contracts with the 
                       construction contractors. 
 EPCM                 means a company contracted to provide engineering, 
                       procurement and construction management services. 
                       The owner contracts other companies directly to 
                       offer construction services, and they are usually 
                       managed by the EPCM contractor on the owner's behalf. 
 Fe                   Chemical symbol for iron. It is a metal that belongs 
                       to the first transition series and group 8 of the 
                       periodic table . It is, by mass, the most common 
                       element on Earth , right in front of oxygen (32.1% 
                       and 30.1%, respectively), forming much of Earth's 
                       outer and inner core . It is the fourth most common 
                       element in the Earth's crust . 
 Feasibility          This study is the most detailed and will determine 
  study                definitively whether to proceed with the Project. 
                       A detailed feasibility study will be the basis 
                       for capital appropriation and will provide the 
                       budget figures for the Project. Detailed feasibility 
                       studies require a significant amount of formal 
                       engineering work, are accurate to within 10-15% 
                       and can cost between 1/2 -1 1/2 % of the total 
                       estimated project cost. 
 Final Investment     FID is the point in the capital project planning 
  Decision             process when the decision to make major financial 
  ("FID")              commitments is taken. At the FID point, major equipment 
                       orders are placed, and contracts are signed for 
                       EPC 
 Floatation           is a standard technology for concentrating a broad 
  circuit              range of minerals and wastewater treatments. Froth 
                       floatation is based on differences in the ability 
                       of air bubbles to adhere to specific mineral surfaces 
                       in a solid/liquid slurry. 
 Flowsheet            The flowsheet or a process flow diagram ("PFD") 
                       is commonly used in chemical and process engineering 
                       to indicate the general flow of plant processes 
                       and equipment. The PFD displays the relationship 
                       between major plant facility equipment and does 
                       not show minor details such as piping details and 
                       designations. 
 Itabirite            Itabirite is a banded quartz hematite schist, very 
                       similar to banded iron formation in appearance 
                       and composition. Friable Itabirite is extensively 
                       weathered, leading to disaggregation of the individual 
                       mineral grains comprising the rock; 
 Internal             is a method of calculating an investment's rate 
  Rate of Return       of return. The term internal refers to the fact 
                       that the calculation excludes external factors, 
                       such as the risk-free rate, inflation, the cost 
                       of capital, or financial risk. 
 Haematite            An iron oxide mineral with the chemical formula 
                       Fe(2) O(3) ; 
 Hydrocyclone         is a type of cyclonic separator that separates 
                       product phases mainly on the basis of differences 
                       in gravity with aqueous solutions as the primary 
                       feed fluid 
 Grade                Relative quantity or the percentage of ore mineral 
                       or metal content in an ore body; 
 Indicated            That part of a Mineral Resource for which tonnage, 
  Mineral Resources    densities, shape, physical characteristics, grade, 
                       and mineral content can be estimated with a reasonable 
                       level of confidence. It is based on exploration, 
                       sampling and testing information gathered through 
                       appropriate techniques from locations such as outcrops, 
                       trenches, pits, workings and drillholes. The locations 
                       are too widely or inappropriately spaced to confirm 
                       geological and/or grade continuity but are spaced 
                       closely enough for continuity to be assumed; 
 Inferred             That part of a Mineral Resource for which tonnage, 
  Mineral Resources    grade and mineral content can be estimated with 
                       a low level of confidence. It is inferred from 
                       geological evidence and assumed but not verified 
                       geological and/or grade continuity. It is based 
                       on information gathered through appropriate techniques 
                       from locations such as outcrops, trenches, pits, 
                       workings, and drill holes which may be limited 
                       or of uncertain quality and reliability; 
 Kt                   Thousand tonnes; 
 Measured             The part of a Mineral Resource for which tonnage, 
  Mineral Resources    densities, shape, physical characteristics, grade, 
                       and mineral content can be estimated with a high 
                       level of confidence. 
 Metallurgical        This is the process of testing how the resource 
  test work            material will respond to standard metallurgical 
                       processes, such as floatation, gravity concentration 
                       and leaching. They are conducted on coarse assay 
                       reject material using standard test conditions. 
                       The objective is to determine how the resource 
                       material reacts to commonly accepted recovery processes 
                       and gain a preliminary estimate of metal recoveries. 
 Mine planning        A plan or schedule of the extraction of ore to 
                       optimise the return (of profit) on investment through 
                       capital investment, design, extraction scheduling, 
                       and preparation of the mineral product according 
                       to specifications. 
 Mineral Reserves     The economically mineable part of a Measured and/or 
                       Indicated Mineral Resource. It includes diluting 
                       materials and allowances for losses, which may 
                       occur when the material is mined. Appropriate assessments 
                       and studies have been carried out and include consideration 
                       of and modification by realistically assumed mining, 
                       metallurgical, economic, marketing, legal, environmental, 
                       social, and governmental factors. These assessments 
                       demonstrate at the time of reporting that extraction 
                       could reasonably be justified. Ore Reserves are 
                       subdivided in order of increasing confidence into 
                       Probable Ore Reserves and Proved Ore Reserves. 
 Mineral Resource     A concentration or occurrence of material of intrinsic 
                       economic interest in or on the Earth's crust in 
                       such form, quality, and quantity that there are 
                       reasonable prospects for eventual economic extraction. 
                       The location, quantity, grade, geological characteristics, 
                       and continuity of a Mineral Resource are known, 
                       estimated, or interpreted from specific geological 
                       evidence and knowledge. Mineral Resources are subdivided, 
                       in order of increasing geological confidence, into 
                       Inferred, Indicated and Measured categories. 
 Mn                   Chemical symbol for Manganese. It has the atomic 
                       number 25. It is not found as a free element in 
                       nature; it is often found in minerals in combination 
                       with iron . 
 Modifying            The term 'modifying factors' is defined to include 
  factors              mining, metallurgical, economic, marketing, legal, 
                       environmental, social and governmental considerations. 
 Net present          This is the difference between the present value 
  value                of cash inflows and the present value of cash outflows 
                       over a period of time. NPV is used in capital budgeting 
                       and investment planning to analyse the profitability 
                       of a projected investment or Project. 
 Open pit             An excavation or cut made at the surface of the 
                       ground for the purpose of extracting ore and which 
                       is open to the surface for the duration of the 
                       mine's life 
 Ore                  is natural rock or sediment containing one or more 
                       valuable minerals, typically metals, that can be 
                       mined, treated and sold at a profit. 
 P                    The chemical symbol for Phosphorus with atomic 
                       number 15. 
 Pellet feed          Iron ore fines used to produce pellets 
 Pit Optimisation     A process whereby a series of optimised shells 
                       for open pits are generated, each corresponding 
                       to a specific commodity price assumption. 
 Pit shell            A design of an open pit obtained from the process 
                       of open-pit optimisation 
 Prefeasibility       It is more detailed than a Scoping Study. A Prefeasibility 
  study                study is used in determining whether to proceed 
                       with a detailed feasibility study and as a " reality 
                       check " to determine areas within the Project that 
                       require more attention. Prefeasibility studies 
                       are done by factoring known unit costs and by estimating 
                       gross dimensions or quantities once conceptual 
                       or preliminary engineering and mine design has 
                       been completed. Prefeasibility studies have an 
                       accuracy of 20-30%. 
 Proven Ore           is the economically mineable part of a Measured 
  Reserve              Mineral Resource. It includes diluting materials 
                       and allowances for losses which occur when the 
                       material is mined. A Proven Orel Reserve represents 
                       the highest confidence category of Mineral Reserve 
                       estimate. It implies a high degree of confidence 
                       in the geological factors and a high degree of 
                       confidence in the Modifying Factors. 
 Probable             is the economically mineable part of an Indicated 
  Ore Reserve          Mineral Resource and, in some circumstances, a 
                       Measured Mineral Resource. It includes diluting 
                       material and allowances for losses which may occur 
                       when the material is mined. A Probable Mineral 
                       Reserve has a lower level of confidence than a 
                       Proved Mineral Reserve but is of sufficient quality 
                       to serve as the basis for a decision on the development 
                       of a deposit. 
 SiO(2)               Silicon dioxide, also known as silica, is an oxide 
                       of silicon most commonly found in nature as quartz 
                       and in various living organisms. In many parts 
                       of the world, silica is the major constituent of 
                       sand . 
 Spiral concentrate   Iron Ore product produced from the beneficiation 
                       plant. 
 t                    Tonnes 
 

- Ends -

([1]) Anglo American (2012), Annual Report (pp.89)

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

DRLSSFFAEEDSESF

(END) Dow Jones Newswires

January 03, 2023 02:00 ET (07:00 GMT)

Cadence Minerals (LSE:KDNC)
Historical Stock Chart
From Oct 2024 to Nov 2024 Click Here for more Cadence Minerals Charts.
Cadence Minerals (LSE:KDNC)
Historical Stock Chart
From Nov 2023 to Nov 2024 Click Here for more Cadence Minerals Charts.