RNS Number:3463D
Marakand Minerals Limited
27 September 2004


        MARAKAND ANNOUNCES COMPLETION OF THE KHANDIZA FEASIBILITY STUDY

London, 27th September 2004

Marakand Minerals Limited ("Marakand") is pleased to announce a positive
completion of the Feasibility Study on the Khandiza polymetallic deposit in
Uzbekistan, the results of which confirm the project is robust.

With a pre-production capital requirement of US$71.23 million, operating costs
are $35.35 per tonne of ore mined and cost of sales (transportation, smelter
refining and treatment costs) are $37.83 per tonne of ore mined. All operating,
transport, refining and treatment, and capital costs include a 15% contingency.

Based on a zinc price of US$970 per tonne (USc44/lb), a lead price of US$570 per
tonne (USc26/lb), a copper price of US$2000 per tonne (USc91/lb), a silver price
of US$5.50 per ounce and a gold price of US$385 per ounce the revenue less
operating costs show a payback of less than 2.5 years.

Significant improvements to earlier studies have been made, resulting in lower
capital and operating costs, whilst minimizing environmental impacts.
Underground mining operations will commence at levels that require minimal
access development and have above average ore grades and widths. A simplified
flow-sheet has been developed encompassing primary milling at the Khandiza mine
followed by gravity transport of the ore by pipeline to the flotation plant and
tailings facility at the existing Shargun railhead. Planned annual production is
650,000 tonnes of ore with 500,000 tonnes planned during ramp up in the first
year.

Underground mine development and process plant construction are scheduled to be
completed within a 13 month period following project approvals and availability
of finance.

The completed Feasibility Study will now be lodged with the State Committee of
Geology and Mineral Resources for the Republic of Uzbekistan ("Goscomgeology").
In accordance with Decree No 359, Marakand and the Uzbek Government will
finalise terms of the Concession Contract on an exclusive rights basis. This
will confirm ownership rights and the fiscal terms for the project development
and the proposed 15-year concession period.

The Khandiza project is included in the Republic of Uzbekistan Foreign
Investment Programme pursuant to Decree No 444 adopted on 19th December 2002.
Marakand is being encouraged by the Uzbek government to develop the project as
soon as possible and is targeting completion of the concession documentation in
Q1 2005.

Concurrent with the above Marakand intends to explore project-financing options
and to complete the Environmental Impact Assessment ("EIA").


FEASIBILTY SUMMARY

Resource

Russian and Uzbek geologists have extensively explored the Khandiza Deposit,
with 77,000m of core drilling and 19,000m of underground development, enabling a
Soviet Feasibility Study to be prepared. The project was further evaluated by
Oxus Resources Corporation ("Oxus") from 1996 until the formation of Marakand in
November 2003. A confirmation drilling programme (30 holes totalling 3,776m) was
completed by Oxus in 2001, improving the resource confidence and providing
further geological and geotechnical data for mine design purposes.

Prior to undertaking the mine design, a revised geostatistical resource block
model was prepared. The table below summarises the geological resource above an
assay cut-off of 2.0% zinc. The resource is classified in compliance with the
internationally recognised JORC Code.

========       =======    ======    ======       ======       ======    ======
Class       Resource      Zinc      Lead       Copper       Silver      Gold
                  Mt         %         %            %          g/t       g/t
========       =======    ======    ======      =======       ======    ======
Measured       4.176      8.33      3.60         0.93          124      0.38
Indicated      7.649      7.29      3.67         0.90          131      0.38
Subtotal      11.825      7.66      3.65         0.91          129      0.38
========       =======    ======    ======      =======       ======    ======
Inferred       2.587      5.36      2.81         0.65          161      0.38
Total         14.412      7.24      3.50         0.86          134      0.38
========       =======    ======    ======      =======       ======    ======

The contained metal in the above resource estimation amounts to 1,044,000 tonnes
of zinc, 505,000 tonnes of lead, 125,000 tonnes of copper, 62.3 million ounces
of silver and 176,000 ounces of gold.

Mine Design and Reserve

A ramp-access, mechanised underground mine is proposed with a production rate of
650,000 tonnes of ore per year. Ore recovery, using the cut and fill mining
method, will be high due to the wide ore zones and excellent ground conditions.
To maximise use of existing workings and reduce costs ore will be crushed
underground and transported to surface by conveyor.

The table below details the mineable reserves for the first 14 years of
production, above a break-even cut-off of 4% zinc.

========     =======    ======    ======        ======        ======    ======
Class      Reserve      Zinc      Lead        Copper        Silver      Gold
                Mt         %         %             %           g/t       g/t
========     =======    ======    ======       =======        ======    ======
Proved       3.377      8.38      3.60          0.95           122      0.36
Probable     5.507      7.83      3.95          0.98           128      0.37
Total        8.884      8.04      3.82          0.97           126      0.37
========     =======    ======    ======       =======        ======    ======

In addition 0.72Mt of inferred resource has been included in the production
schedule in year 15 at an average grade of 6.08% zinc, 3.31% lead, 0.75% copper,
166 g/t silver and 0.39 g/t gold (with dilution and recovery applied). The total
production for the first 15 years mine-life will be 9.61Mt at an average grade
of 7.90% zinc, 3.78% lead, 0.95% copper, 129 g/t silver and 0.37 g/t gold.

Metallurgy and process design

Metallurgical test-work conducted by Marakand has confirmed results of previous
test-work programmes including a 15 tonne pilot scale test. The optimised
metallurgical process selected provides the following recoveries:

   *89.1% of the zinc recovered into the zinc concentrate (with a concentrate
    grade of 54.8% zinc)


   *74.7% of the lead recovered into the lead concentrate (with a concentrate
    grade of 56.1% lead)


   *77.5% of the copper recovered into the copper concentrate (with a
    concentrate grade of 25.3% copper)


   *23.6% of the silver is recovered into the lead concentrate, and 41.8%
    into the copper concentrate


   *21.0% of the gold is recovered into the lead concentrate, and 24.3% into
    the copper concentrate.


Site layout and plant design

The milled ore will be gravity transported by a 43km pipeline from Khandiza to
the coal-mining town of Shargun, where the secondary milling and flotation plant
will be located. The flotation circuit will produce separate zinc, lead and
copper concentrates.

Marakand has acquired industrial land ideally located next to the Shargun
railhead, which will enable receipts of construction and operating supplies, and
despatch of the concentrates produced.

A disused clay pit, located approximately 1km from the flotation plant, is to be
used as the tailings storage facility.

Power, water and transport infrastructures are already available.

Environmental

An EIA is being prepared to meet standards required by international funding
agencies, with completion expected by the end of the year.

Concentrate smelting and refining

A concentrate and metal marketing study has been completed. For the purposes of
the Feasibility Study, it has been assumed that 100% of the zinc and copper
concentrates will be toll-smelted at the Almalyk Smelter in Uzbekistan, and that
100% of the lead concentrates will be sold for smelting in Kazakstan.
Nevertheless management, in discussion with a number of smelters, has received
letters of intent indicating that demand for concentrates and metals is well in
excess of planned production.

Concentrate production, in dry metric tonnes, is scheduled as follows:

   *Zinc concentrate - average of 101,800 tonnes per year for the first five
    years, and 82,200 tonnes per year over 15 years


   *Lead concentrate - average of 35,600 tonnes per year for the first five
    years, and 32,300 tonnes per year over 15 years


   *Copper concentrate - average of 23,400 tonnes per year for the first five
    years, and 18,700 tonnes per year over 15 years

Revenues are generated from:

   * Sale of zinc metal returned (93%) after toll smelting of zinc
    concentrates

   * Sale of copper metal returned (94%) after toll smelting of copper
    concentrates; plus credits for 70% of the contained silver and gold above
    the payable threshold.

   * Sale of lead concentrates, with payment on the basis of 95% of the
    contained lead; plus 95% of the contained silver and 90% of the contained
    gold above the payable threshold.

Gross revenue contribution comprises 60.45% from zinc, 14.54% from lead, 13.20%
from copper, 11.03% from silver and 0.78% from gold using the metal prices
assumed.

Operating costs

Cash operating costs (US$ per tonne of ore mined) averaged over the first 15
years are estimated as follows:

                                                                         US$/t*
===========                                                             =======

Mining                                                                   16.23
Processing                                                                9.53
G&A                                                                       4.98
15% contingency                                                           4.61
-----------                                                             -------
Total                                                                     35.35
===========                                                             =======
* per tonne ore mined


Capital costs
Pre-production capital costs are estimated as follows:

                                                                          US$m
=============                                                         ========

Mining                                                                   13.43
Processing                                                               22.38
Infrastructure                                                           13.44
Contractor and Freight                                                    8.25
Owners costs                                                              3.80
First fills                                                               0.68
15% contingency                                                           9.25
-------------                                                         --------
Total                                                                    71.23
=============                                                         ========


The initial working capital funding requirement is estimated at US$ 6.21m

Marakand Minerals is a mining exploration and development company focused in
Central Asia, and listed on the Alternative Investment Market (AIM) in London,
ticker symbol MKD.L.

For further information, please contact:

Alasdair Stuart            Joanna Solino               Alex Buck
Chief Executive Officer    Investor Relations Officer  Buck Communications
Marakand Minerals Limited  Marakand Minerals Limited   Tel: +44 (0)7932 740 452
Tel: +998 93 171 2401      Tel: +44 (0)20 7907 2000




                      This information is provided by RNS
            The company news service from the London Stock Exchange

END
MSCQKAKNOBKDOCB

Marakand Minerals (LSE:MKD)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Marakand Minerals Charts.
Marakand Minerals (LSE:MKD)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Marakand Minerals Charts.