TIDMPPN 
 
RNS Number : 9686L 
Platmin Limited 
14 May 2010 
 

                                PLATMIN LIMITED 
 
                      MANAGEMENT'S DISCUSSION AND ANALYSIS 
                OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS 
                    FOR THE THREE MONTHS ENDED MARCH 31, 2010 
                                                                    May 14, 2010 
              CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS 
This Management's Discussion and Analysis of Financial Condition and Results of 
Operations ("MD&A") for the three months ended March 31, 2010 contains 
"forward-looking information" which may include, but is not limited to, 
statements with respect to the future financial and operating performance of 
Platmin Limited (the "Company" or "Platmin"), its subsidiaries and affiliated 
companies, and its mineral projects, the future price of platinum or other 
Platinum Group Elements ("PGEs"), PGE production levels, mining rates, the 
future price of other base metals, future exchange rates,   the estimation of 
mineral resources and reserves, the realization of mineral resource estimates or 
their conversion into reserves, costs and future costs of production, capital 
and exploration expenditures, including remaining project development 
expenditure at the Pilanesberg Platinum Mine ("PPM"), costs and timing of the 
development of new deposits, costs and timing of the development of new mines, 
costs and timing of future exploration, requirements for additional capital, 
government regulation of mining operations and exploration operations, timing 
and receipt of approvals, licenses, and conversions under South African mineral 
legislation, environmental risks, title disputes or claims, limitations of 
insurance coverage and the timing and outcome of regulatory matters. Often, but 
not always, forward-looking statements can be identified by the use of words 
such as "plans", "expects", "is expected", "budget", "scheduled", 
"estimates", "forecasts", "intends", "anticipates", "targeted" or 
"believes" or variations (including negative variations) of such words and 
phrases, or state that certain actions, events or results "may", "could", 
"would", "might" or "will" be taken, occur or be achieved. 
Forward-looking statements in this MD&A include, among others, the operation of 
open-cast mining; forecast average annualized production rates at PPM for the 12 
month period ending December 31, 2010; forecasts of actual production during the 
12 month period ending December 31, 2010 and 2011; recovery rates and grade; 
targets, estimates and assumptions in respect of platinum and other PGE prices 
and production; the quantum of PPM development shortfalls; the completion of the 
Sedibelo acquisition; and the timing and completion of definitive feasibility 
work at the Mphahlele, Grootboom and Loskop Projects. 
Such forward-looking statements are based on a number of material factors and 
assumptions, including, that contracted parties provide goods and/or services on 
the agreed timeframes, that equipment necessary for construction and development 
is available as scheduled and does not incur unforeseen break downs, that no 
labour shortages or delays are incurred, that plant and equipment functions as 
specified, that geological or financial parameters do not necessitate future 
mine plan changes, that no unusual geological or technical problems occur, and 
that grades and recovery rates are as anticipated in mine planning. 
Forward-looking statements involve known and unknown risks, uncertainties and 
other factors which may cause the actual results, performance or achievements of 
Platmin and/or its subsidiaries and/or its affiliated companies to be materially 
different from any future results, performance or achievements expressed or 
implied by the forward-looking statements. Such factors include, among others, 
general business, economic, competitive, political and social uncertainties; the 
actual results of current exploration and mining activities; development and 
operational risks; title risks; regulatory risks; conclusions of economic 
evaluations and studies; fluctuations in the value of the United States dollar 
relative to the Canadian dollar or South African rand; changes in project 
parameters as plans continue to be refined; future prices of platinum or other 
PGEs; possible variations of ore grade or recovery rates (including the 
existence of potholes, faults and other geological conditions that may affect 
the existence or recovery of resources and reserves); failure of plant, 
equipment or processes to operate as anticipated; accidents, labour disputes, 
industrial unrest and strikes and other risks of the mining industry; political 
instability, insurrection or war; the effect of HIV/AIDS on labour force 
availability and turnover; delays in obtaining governmental approvals or 
financing or in the completion of development or construction activities, as 
well as those factors communicated in the section entitled "Risk Factors" of 
Platmin's current annual information form ("AIF") and its final short form 
prospectus dated May 5, 2010, which can both be viewed at www.sedar.com. 
Although Platmin has attempted to identify important factors that could cause 
actual actions, events or results to differ materially from those described in 
forward-looking statements, there may be other factors that cause actions, 
events or results to differ from those anticipated, estimated or intended. 
Forward-looking statements contained herein are made as of the date of this MD&A 
and Platmin disclaims any obligation to update any forward-looking statements, 
whether as a result of new information, future events or results or otherwise. 
There can be no assurance that forward-looking statements will prove to be 
accurate, as actual results and future events could differ materially from those 
anticipated in such statements. Accordingly, readers should not place undue 
reliance on forward-looking statements due to the inherent uncertainty therein. 
1.      Introduction 
The Management's Discussion and Analysis of Financial Condition and Results of 
Operations ("MD&A") is provided to enable the reader to assess and understand 
the financial position and results of operations for the three months ended 
March 31, 2010, in comparison to corresponding periods. Certain information in 
this MD&A must be read in conjunction with the audited consolidated financial 
statements of Platmin for the year ended December 31, 2009 (prepared in 
accordance with International Financial Reporting Standards ("IFRS")). 
The MD&A should be read in conjunction with the condensed consolidated interim 
financial statements for the three months ended March 31, 2010 and supporting 
notes. 
The MD&A should also be read in conjunction with the company's Annual 
Information Form ("AIF") and the technical reports prepared by qualified persons 
in accordance with NI 43-101 on file with the Canadian provincial securities 
regulatory authorities. These documents can be found at www.sedar.comand at 
www.platmin.com. 
All dollar amounts in this MD&A are expressed in United States dollars ("US$"), 
unless otherwise specified. When used, C$ refers to Canadian dollars. References 
to quarters are to financial quarters and not to calendar quarters, unless 
otherwise specified. 
2.      Overview 
Platmin Limited (the "Company" or "Platmin") is continued under the laws of 
British Columbia, Canada and its common shares are listed on the Toronto Stock 
Exchange ("TSX"), the Alternative Investment Market of the London Stock Exchange 
("AIM") and the Johannesburg Securities Exchange Limited ("JSE").  The Company 
trades under the symbol "PPN" on both TSX and AIM, whilst the symbol 
"PLN" 
 identifies the shares on the JSE. 
Platmin is a mineral exploration, development and operating company engaged in 
the exploration for, development of and operation of mines exploiting Platinum 
Group Element ("PGE") deposits in South Africa. The Company has developed and 
completed the construction of PPM, which is currently ramping up to full 
production, and is exploring for PGEs on its other three key projects namely 
Mphahlele, Grootboom and Loskop. 
The Group changed its financial year end from the last day of February in each 
calendar year to the last day of December, effective for the period ending 
December 31, 2009. As a result of the change in year end, and the requirements 
of the Ontario Securities Commission ("OSC") for comparable quarters the 
comparatives for the quarter ending February 28, 2009, are not directly 
comparable with the current balances for the quarter ended March 31, 2010. 
3.      Overall Performance 
The Company recorded a loss for the quarter ended March 31, 2010 of US$5.181 
million, or a loss per share of US$0.01, compared with a net loss of US$12.490 
million or a net loss per share of US$0.07, for the quarter ended February 28, 
2009. The decrease in loss quarter on quarter was principally the result of 
consulting and professional fees of US$0.172 million in the quarter under review 
compared consulting and professional fees of US$7.061 million for the quarter 
ended February 28, 2009. The consulting and professional fees expense in the 
quarter ended February 28, 2009 relate to the Pallinghurst transaction concluded 
in December 2008. 
The principal focus of the Company's operations is the development and operation 
of PPM. For a full description of the development activities, please refer to 
section 7.1 of this MD&A. 
As at the quarter ended March 31, 2010, total plant capital expenditure at PPM 
amounted to US$266.625 million (ZAR1.953 billion) compared to US$266.079 million 
(ZAR1.949 billion) at the financial year ended December 31, 2009. As at March 
31, 2010, the total outstanding plant capital expenditure to completion of the 
construction phase was US$16.102 million (ZAR117.948 million) which will bring 
the total projected plant capital expenditure to US$282.727 million (ZAR2.071 
billion). This amount is higher than the original amount per the BFS of ZAR1.670 
billion (which equated to US$231.940 million based on an exchange rate of 
ZAR7.20 at the time of the study), due to changes in scope, particularly the 
inclusion of a10MVA standby power station (see page 7 of this MD&A), cost 
increases experienced in general terms by the global mining industry over the 
past two years and variances in foreign exchange rates. 
As at March 31, 2010, the total project capital expenditure, for the development 
of PPM, including capitalised pre-production costs, plant capital expenditure 
and offsetting revenue from metal sales during the pre-production phase amounted 
to US$440.815 million (ZAR3.229 billion). Outstanding plant capital expenditure 
to completion of the construction phase of US$16.102 million (ZAR117.948 
million) will bring the total project capital expenditure spent to US$456.917 
million (ZAR3.347 billion). During the quarter under review, the ramp-up of 
mining operations to commercial production continued with associated costs 
capitalized as part of the total project capital expenditure. 
On May 13, 2010, the Company issued, by way of a prospectus offering, a total of 
205,761,317 new common shares of Platmin at a price of $1.215 per common share 
for gross proceeds of US$250 million.  The transaction included (i) 95,358,025 
common shares being underwritten by RBC Capital Markets and Investec Bank 
Limited for gross proceeds of US$115,860,000; and (ii) the balance being 
acquired directly from Platmin in the form of a subscription for 41,152,263 
common shares by Ridgewood Investments (Mauritius) Pte Ltd ("Ridgewood"), an 
indirect subsidiary of Temasek Holdings (Private) Limited ("Temasek"), and a 
subscription for 69,251,029 common shares by Platmin's largest shareholder, 
Pallinghurst. 
In light of the fact that the board has decided to focus cash resources and 
capacity on bringing the PPM into full production, the Mphahlele, Grootboom and 
Loskop projects have been placed on a reduced work program for the short term. 
Platmin will commit sufficient expenditure to these projects to ensure that the 
new order Prospecting and Mining Rights are preserved. This expenditure will be 
funded from existing cash on hand and where necessary, additional funding will 
be raised to fund future exploration and development expenditure. 
Significant developments in the three months ended March 31, 2010 were as 
follows: 
·    On March 22, 2010, a subsidiary of Platmin entered into a ZAR191 million 
(an equivalent of US$26.0 million at an exchange rate of ZAR7.38 = US$1) short 
term lending facility with Pallinghurst Resources Limited ("Pallinghurst"). As 
at the date of this MD&A, the first tranche of ZAR95.5 million (an equivalent of 
US$13.0 million) had been drawn against this facility. 
·     On March 29, 2010, the company entered into an agreement with Ridgewood to 
purchase a non-interest bearing secured Convertible Debenture with a principal 
amount of US$100 million and with a maturity date of December 31, 2010. Until 
converted, the US$100 million will be deposited and held in a cash 
collateralized account. The funds will be released to Platmin upon conversion in 
full, at the sole discretion of the holder, into 82,304,526 common shares at a 
price of US$1.215 per common share (being an effective price of C$1.25). In the 
event the convertible debenture is not converted in full prior to the maturity 
date, the funds will be returned to the subscriber. 
Important events which occurred subsequent to March 31, 2010 include: 
·     On April 16, 2010 the company concluded an agreement to acquire the 10% 
interest in the Sedibelo Platinum Project ("Sedibelo") held by Barrick Gold 
Corporation ("Barrick") for a consideration of US$15 million. In addition, 
Barrick has undertaken to transfer to Platmin, at cost, various long lead items 
required for the development of Sedibelo. The final consideration, up to US$45 
million, is still to be determined. 
·     On April 16, 2010 the company filed a preliminary short form prospectus in 
Canada in connection with a US$250 million marketed offering of new common 
shares. 
·     On May 4, 2010, Pallinghurst Investor Consortium ("Pallinghurst") and 
Investec Bank Limited ("Investec") each subscribed for US$30 million and US$5 
million, respectively, of principal amount of a non-interest bearing secured 
convertible debentures on the same terms and conditions as the Convertible 
Debenture issued to Ridgewood.  If Pallinghurst converts its convertible 
debenture in full, a total of 24,691,358 shares will be issued to Pallinghurst. 
·     On May 5, 2010, following a marketing period, the Company agreed to issue 
205,761,317 new common shares at a price of US$1.215 per common share for a 
total consideration of US$250 million. An aggregate of 95,358,025 common shares 
are being underwritten by RBC Capital Markets and Investec Bank Limited for 
gross proceeds of US$115.860 million with the balance of US$134.140 million to 
be acquired directly from Platmin by Ridgewood Investments (Mauritius) Pte Ltd, 
an indirect subsidiary of Temasek Holdings (Private) Limited, Algemene Pensioen 
Groep N.V., and Platmin's largest shareholder, Pallinghurst Investor Consortium 
(Lux) S.a.r.l. As part of the funds-raising process US$135 million of 
convertible debentures have been placed. The total funding from the prospectus 
offering and private placement is US$385 million. 
·     The sales of the convertible debentures to Ridgewood, Pallinghurst and 
Investec each closed concurrently with the closing of the prospectus offering on 
May 13, 2010. 
·     On May 13, 2010, the Company completed the previously announced issuance 
of 205,761,317 new common shares at a price of US$1.215 per common share for a 
total consideration of US$250 million, and the issuance of US$135 million of 
convertible debentures. 
4.     Selected Quarterly Results 
Expressed in US$'000 except per share amounts. 
 
+------------+--------+--------+---------+--------+--------+---------+-------+ 
|            |                    In accordance with IFRS                    | 
+------------+---------------------------------------------------------------+ 
|            | Mar'10 | Nov'09 |  Aug'09 |    May |    Feb |     Nov |   Aug | 
|            |        |        |         |    '09 |    '09 |     '08 |   '08 | 
+------------+--------+--------+---------+--------+--------+---------+-------+ 
| Loss /     |  5,181 |  2,276 | (6,620) | 13,585 | 12,490 | (6,686) | 3,387 | 
| (profit)   |        |        |         |        |        |         |       | 
| for the    |        |        |         |        |        |         |       | 
| period     |        |        |         |        |        |         |       | 
+------------+--------+--------+---------+--------+--------+---------+-------+ 
| Basic and  |   0.01 |   0.01 |  (0.02) |   0.03 |   0.07 |  (0.06) |  0.03 | 
| diluted    |        |        |         |        |        |         |       | 
| loss /     |        |        |         |        |        |         |       | 
| (profit)   |        |        |         |        |        |         |       | 
| per share  |        |        |         |        |        |         |       | 
+------------+--------+--------+---------+--------+--------+---------+-------+ 
5.     Results of Operations 
Quarter ended March 31, 2010 compared to the quarter ended February 28, 2009 
For the quarter ended March 31, 2010, mining and processing activities continued 
in the ramp-up phase to commercial production and the delivery of PGE 
concentrate to Northam continued at regular intervals. As a development stage 
company, Platmin will offset revenue from mining activities against capitalised 
operating costs until such time as PPM is brought into commercial production. In 
accordance with IFRS, revenue is recognised when the transfer of the risks and 
rewards of ownership takes place. During the quarter under review, revenue 
recognised in respect of concentrate deliveries made to Northam was offset 
against capitalized project development costs. 
For the quarter ended March 31, 2010, development expenditure at PPM capitalized 
against project capital expenditure of US$36.023 million (ZAR269.656 million) 
was offset by US$18.503 million (ZAR138.506 million) of operating revenue. For 
the quarter ended February 28, 2009, development expenditure at PPM capitalized 
against project capital expenditure was US$18.738 million (ZAR187.085 million). 
As PPM was still in the development phase, there was no operating revenue for 
the quarter ended February 28, 2009. 
The Company recorded a net loss for the quarter ended March 31, 2010 of US$5.181 
million, or US$0.01 per share, compared with a net loss of US$12.490 million, or 
a loss of US$0.07 per share, for the quarter ended February 28, 2009. The 
results are summarized as follows: 
 
+--------------------------------------+----------+----------+ 
|                                      |       For the three | 
|                                      |        months ended | 
+--------------------------------------+---------------------+ 
|                                      |    March | February | 
|                                      |      31, |      28, | 
|                                      |     2010 |     2009 | 
|                                      |    $ 000 |    $ 000 | 
+--------------------------------------+----------+----------+ 
| General expenses                     |  (4,393) | (12,716) | 
+--------------------------------------+----------+----------+ 
| Other (expenses) / income            |      (9) |    1,508 | 
+--------------------------------------+----------+----------+ 
| Finance costs                        |    (779) |  (1,282) | 
+--------------------------------------+----------+----------+ 
| Loss profit before taxation          |  (5,181) | (12,490) | 
+--------------------------------------+----------+----------+ 
| Income tax                           |        - |        - | 
+--------------------------------------+----------+----------+ 
| LOSS FOR THE PERIOD                  |  (5,181) | (12,490) | 
+--------------------------------------+----------+----------+ 
 
General expenses totalled US$4.393 million for the quarter ended March 31, 2010, 
compared to the US$12.899 million for the quarter ended February 28, 2009. The 
decrease in general operating expenses was principally the result of increased 
consulting and professional fees during the quarter ended February 28, 2009, 
associated with the Pallinghurst transaction concluded in December 2008. 
Other expenses and income includes foreign exchange losses of US$0.009 million 
for the quarter ended March 31, 2010, compared to foreign exchange gains of 
US$1.507 million for the quarter ended February 28, 2009. The net decrease in 
foreign exchange gains was due to the strengthening of the South African Rand 
against other foreign currencies and the resultant differences in the closing 
and average exchanges rates quarter on quarter. For the quarter under review, 
the South African Rand exchange rate to the US dollar moved within a range of 
ZAR7.77 and ZAR7.23 to US$1.00 compared to a range of ZAR9.28 and ZAR10.51 to 
US$1.00 for the quarter ended February 28, 2009. 
Finance costs of US$0.779 million were recorded in the quarter ended March 31, 
2010, compared to US$1.282 million in the quarter ended February 28, 2009. The 
net decrease in finance costs is due to the bridge loan facility with the 
Standard Bank of South African Limited ("Standard Bank") being repaid on August 
31, 2009. 
A total of US$0.422 million (ZAR3.092 million) of deferred exploration 
expenditure was capitalized in the quarter ended March 31, 2010 compared with 
US$1.666 million (ZAR12.207 million) in the quarter ended February 28, 2009. 
This decrease in costs is due to reduced activities on all projects in the short 
term, whilst PPM ramps up to commercial production. 
6.     Liquidity and Capital Resources 
The Company had cash and cash equivalents of US$17.892 million at March 31, 
2010, as compared with US$127.950 million at February 28, 2009. The net decrease 
in cash and cash equivalents is primarily due to the settlement of the bridging 
finance facility, costs associated with plant capital expenditure and 
pre-production costs incurred during the ramp-up of operations at PPM. 
The Company finances its exploration and development activities by raising 
capital from equity markets or debt funding and through contributions by joint 
venture partners. Funding requirements for the Company's projects have 
historically been satisfied through the advance of shareholders' loans, by 
Platmin and Boynton Investments (Pty) Ltd ("Boynton") or subscription for shares 
(rights issues to shareholders of Boynton). The shareholders' agreements or 
joint venture agreements of Platmin's subsidiaries also generally make provision 
for the board of directors of each relevant company to seek finance on behalf of 
each company, although this has not been utilized to date. The expenditure for 
future exploration and development projects may require that the Company raise 
additional funds. 
The Company's principal subsidiary, Boynton, operates in South Africa and as a 
result is subject to the South African Reserve Bank ("SARB") exchange control 
regulations. Shareholder loans from Platmin to Boynton, amounted to US$444.160 
million (which includes capitalised interest of US$25.590 million) at March 31, 
2010. Any repayment of foreign currency loans by a South African company to an 
offshore company, are subject to prior approval by the SARB. 
Bridging finance facility 
A bridge loan facility for PPM of US$35 million (ZAR350 million) was concluded 
with Standard Bank in May 2008. The bridge loan facility was used to fund a 
portion of the costs associated with the development and construction of PPM. 
The term of the bridge loan facility was initially to August 31, 2008 but 
subsequently extended to August 31, 2009. At the outset, the facility incurred 
interest at the Johannesburg Interbank Lending Rate ("JIBAR") plus 3.0%. From 
March 1, 2009 to August 31, 2009, Platmin provided cash collateral to Standard 
Bank of US$49.870 million (ZAR387.800 million) as security against the loan. 
This resulted in a reduction in the interest rate to JIBAR plus 0.5%. The 
Company earned interest at JIBAR plus 0.1% on cash collateral, bringing the net 
finance cost on the loan to 0.4%. At the financial quarter ended August 31, 2009 
the outstanding balance on the bridge loan facility was US$51.987 million 
(ZAR404.354 million) but has subsequently been repaid in full on September 3, 
2009. 
 
In relation to the original bridge loan facility, the Company issued 300,000 
warrants at $6.95 per common share, exercisable from September 15, 2008 until 
expiry on May 14, 2011. The Company has classified this facility as held to 
maturity, and the fair value of the warrants of US$0.846 million has been 
treated as a cost of the loan transaction. In the year ended February 28, 2009, 
the fair value of these warrants was fully amortized to net income over the 
original loan term of 6 (six) months, using the effective interest method. 
New equity raisings 
On May 13, 2010, the Company completed an issuance of 205,761,317 new common 
shares at a price of US$1.215 per common share for a total consideration of 
US$250 million, and the issuance of US$135 million of convertible debentures. 
Common shares to the value of US$115.860 million were underwritten by RBC 
Capital Markets and Investec Bank Limited, while shares to the value of 
US$134.140 million were acquired directly from Platmin by Ridgewood Investments 
(Mauritius) Pte Ltd, an indirect subsidiary of Temasek Holdings (Private) 
Limited, Algemene Pensioen Groep (APG) N.V., and the Pallinghurst Investor 
Consortium (Lux) S.a.r.l. The total funding from the prospectus offering and 
private placement is US$385 million. Proceeds from the convertible debenture 
financing have been deposited to cash collateralized accounts, and in the event 
the convertible debentures are not converted in full prior to the maturity date, 
the principal amount will be returned to the holders. 
As at March 31, 2010, the Company had 445,018,352 common shares in issue 
compared to 370,002,800 common shares in issue as at February 28, 2009. 
7.      Results of Operations by Project 
In the quarter ended March 31, 2010, the Company spent US$36.023 million 
(ZAR269.656 million) on development expenditure and US$0.422 million (ZAR3.092 
million) on exploration expenditure. All development expenditure was spent on 
PPM and was capitalized as project costs. Amounts spent on exploration were 
capitalized with exploration expenditure on the various key projects as follows: 
20% was spent on the Mphahlele Project, 7% was spent on the Grootboom Project; 
60% was spent on the Pilanesberg Exploration projects and 13% spent on other 
projects. A summary of the expenditures by project along with the current 
proposed programs is set forth below. 
7.1    Pilanesberg Platinum Mine 
The Company has developed the Pilanesberg Project into the PPM, which 
constitutes an open-cast mining operation and a processing plant, producing a 
PGE concentrate for sale to Northam Platinum Limited ("Northam"), a third party 
smelting and refining operation located approximately 60 kilometres from PPM by 
road. 
Due to the close proximity of the 'PGE-bearing' Merensky and UG2 reef horizons 
in this part of the Bushveld complex, these two ore bodies are exploited in one 
open-cast mining operation at PPM. Other economically viable reefs, commonly 
known as the Pseudo reefs, are also present between the two aforementioned reef 
horizons and will be extracted along with the Merensky reef as an overall 
Silicate Package. The Silicate Package is processed in the Merensky circuit and 
the UG2 reef horizon is processed in the UG2 circuit. Both concentrates are 
blended and forwarded to Northam's smelter in South Africa, for further 
processing into final metals under the current Concentrate Agreement entered 
into on June 30, 2008 with Northam. 
In March 2008, the removal of overburden and waste rock materials from the open 
pit commenced. This was followed in December 2008 with the start-up of reef 
mining. The mine is still in the ramp-up phase, building up to reach the planned 
steady state extraction rates of over 400,000 total tonnes per month or over 5 
million total tonnes per annum of reef. These targets are expected to be reached 
by December 2010. A Reverse Circulation ("RC") grade control drilling program at 
10 meter centers was put in place on the initial mining blocks of the 
Tuschenkomst pit and is maintained a minimum of three months ahead of reef 
mining. Mine planning continues to take place at PPM to continuously update the 
mine scheduling on a short-term and long-term basis. The stock-piling of 
PGE-bearing ore ahead of the processing plant commenced in December 2008 with 
milling operations commencing in March 2009. The delivery of the first 
concentrate to Northam took place on April 1, 2009. 
During the quarter under review, a total of 3.911 million cubic meters of 
top-soil and waste material was removed from the pit, and a total of 711,398 ROM 
tonnes of reef mining took place. The extraction of reef ore during the quarter 
was from the oxidised layer where metallurgical recoveries are traditionally 
lower. As at March 31, 2010 the total stock pile of 883,535 ROM tonnes consisted 
of 70,609 ROM tonnes of Merensky and UG2 ore and 812,926 ROM tonnes of low 
grade, Dense Media Separation ("DMS") ore. 
The total project development expenditures for the quarter ended March 31, 2010 
of US$36.023 million (ZAR269.656 million) has been capitalized. Total 
capitalized project development expenditure to date now stands at US$440.815 
million (ZAR3.229 billion). 
In July 2007, a Bankable Feasibility Study ("BFS") was completed and the total 
estimated value of plant capital expenditure was ZAR1.670 billion. At the time 
of the study, this translated to US$231.940 million at an estimated exchange 
rate of ZAR7.20 to US$1.00. In November 2007, PPM entered into an agreement with 
engineering firm Dowding, Reynard and Associates Engineering (Pty) Limited 
("DRA") to implement the overall design and construction phase at PPM, including 
the processing plant. The processing plant was designed based on two separate 
processing circuits to crush, mill and float the ore from the UG2 and Merensky 
reefs as two separate streams. In addition, the Merensky reef circuit includes a 
DMS circuit to upgrade low grade ore. The overall design of the processing 
plant was based on processing in excess of 5 million tonnes per annum of reef 
ore, including low grade DMS material, milling in excess of 3.4 million tonnes 
per annum of upgraded ore and producing 250,000 ounces of 3PGE+Au on an 
annualized basis. The operation of the processing plant has been sub-contracted 
to Minopex (Pty) Ltd, a division of DRA. 
As part of the construction of PPM, a commitment was secured from ESKOM for the 
supply of the 37MVA of new power by mid 2009 that is required for the full 
operation of the processing plant. The first phase of the implementation plan 
was completed by ESKOM in March 2009, with the installation of 14MVA of new 
power supply for the operation of the UG2 circuit of the plant. Installation of 
the remaining 23MVA of installed power was completed on June 7, 2009 allowing 
for the commencement of the commissioning phase of the Merensky Reef circuit. 
In addition to the regular power supply from ESKOM, the construction of a 
complete 10MVA standby diesel generator power plant ("power plant") at a cost of 
US$19.707 million (ZAR144.350 million), has been completed at PPM. This facility 
is capable of providing sufficient power to run the UG2 section of the 
processing plant on an ongoing basis in the event that ESKOM is unable to 
provide constant power to the mine over an extended period of time, it is also 
able to provide sufficient additional power if ESKOM reduce the contracted power 
supply to the mine by up to 10MVA. This 10 MVA power plant was commissioned on 
December 2, 2009. 
Construction of the processing plant commenced in October 2007 and was completed 
during the first quarter of the current financial year. In March 2009, the 
processing of material through the UG2 circuit commenced, signalling the 
commencement of the plant operation to produce a metal in concentrate ready for 
smelting, refining and sale under the Concentrate Agreement to Northam. In June 
2009, following the installation by ESKOM of the additional 22MVA of power, the 
processing of material through the Merensky circuit commenced. Final 
commissioning will take place subsequent to quarter end. 
For the quarter ended March 31, 2010, the Company dispatched and sold 14,177 PGE 
ounces and subsequently recognised revenue to the value of US$18.503 million 
(ZAR138.506 million). As a development stage company, these receipts are offset 
against the capitalized project costs until such time that commercial production 
is reached. 
As at the quarter ended March 31, 2010, total plant capital expenditure at PPM 
amounted to US$266.625 million (ZAR1.953 billion) compared to US$266.079 million 
(ZAR1.949 billion) at the financial year ended December 31, 2009. As at March 
31, 2010, the total outstanding plant capital expenditure to completion of the 
construction phase was US$16.102 million (ZAR117.948 million) which will bring 
the total projected plant capital expenditure to US$282.727 million (ZAR2.071 
billion). This amount is higher than the original amount per the BFS of ZAR1.670 
billion (which equated to US$231.940 million based on an exchange rate of 
ZAR7.20 at the time of the study), due to changes in scope, particularly the 
inclusion of a10MVA standby power station, cost increases experienced in general 
terms by the global mining industry over the past two years and variances in 
foreign exchange rates. 
As at March 31, 2010, the total project capital expenditure, for the development 
of PPM, including capitalised pre-production costs, plant capital expenditure 
and offsetting revenue from metal sales during the pre-production phase amounted 
to US$440.815 million (ZAR3.229 billion). Outstanding plant capital expenditure 
to completion of the construction phase of US$16.102 million (ZAR117.948 
million) will bring the total capital expenditure spent to US$456.917 million 
(ZAR3.347 billion). 
During the quarter under review, the ramp-up of mining operations to commercial 
production continued with associated costs capitalized as part of the total 
project capital expenditure. 
Platmin plans to conduct further exploration in the vicinity of PPM with the 
view to increasing its mineral resource base in the Pilanesberg area. 
7.2    Pilanesberg Exploration projects 
The total exploration expenditure on various Pilanesberg exploration projects 
totalled US$0.252 million (ZAR1.847 million) for the quarter ended March 31, 
2010. Total exploration expenditure since the inception of the Pilanesberg 
Project of US$15.449 million (ZAR113.163 million), has been capitalized. In 
accordance with the Group's accounting policies, these costs are capitalised as 
part of "Exploration and evaluation assets". 
Work program 
The Pilanesberg exploration projects consist of properties adjacent to PPM. The 
focus is on advancing earlier stage properties, through programs of soil 
sampling, trenching, percussion drilling and ultimately diamond drilling. 
Platmin is also conducting limited chrome exploration on properties in the 
Pilanesberg Project area where these rights are held. 
7.3    Mphahlele Project 
In the quarter ended March 31, 2010, a total of US$0.083 million (ZAR0.608 
million) was spent on the Mphahlele project bringing the cumulative expenditure 
to date on the project by the Company to US$12.889 million (ZAR94.411 million), 
excluding acquisition costs. In accordance with the Group's accounting policies, 
these costs are capitalised as part of "Exploration and evaluation assets". 
During the quarter under review, the Company continued with the Definitive 
Feasibility Study ("DFS)" on the Mphahlele project. 
Work program 
In light of the fact that the board have decided to focus cash resources and 
management on bringing PPM into full production, this project has been put on a 
reduced work program for the short term. The reduced primary expenditure at 
Mphahlele during the 2010 fiscal year is expected to be limited to activities 
related to the DFS including metallurgical test work, and revision of resource 
models to include mining dilution (various scenarios), mining design, 
geotechnical investigations and the environmental impact assessment/management 
program. 
The Social and Labour Plan, which is a program  covering the social and economic 
development plan for the communities affected by the operations, was completed 
during August 2008 and was submitted in September 2008 to the Department of 
Mineral Resources ("DMR"), as required for the approval of the mining right. The 
DMR subsequently approved the plan. 
7.4    Grootboom Project 
In the quarter ended March 31, 2010, the Company spent US$0.031 million 
(ZAR0.230 million) on Grootboom and Annex Grootboom (upon which Platmin has an 
option to acquire the PGE rights on completion of a DFS), bringing the 
cumulative expenditure to date on the project to US$5.845 million (ZAR42.817 
million). In accordance with the Group's accounting policies, these costs are 
capitalised as part of "Exploration and evaluation assets". 
The project advanced to the DFS stage during the quarter under review. The DFS 
is expected to be completed in the third quarter of fiscal 2010. 
Work program 
In light of the fact that the board have decided to focus cash resources and 
management on bringing PPM into full production, this project has been put on a 
reduced work program for the short term. The reduced primary expenditure at 
Grootboom during the 2010 fiscal year is expected to be limited to activities 
related to the DFS including metallurgical test work, and the revision of 
resource models to include mining dilution (various scenarios), mining design, 
geotechnical investigations and the environmental impact assessment/management 
program. 
7.5    Loskop Project 
Lonmin Plc is the operator of the Loskop Project and funds all exploration 
expenditures on the project (except for a portion of Rietfontein as mentioned 
below), as part of their option to acquire 50% in the joint venture. As a result 
thereof, limited expenditure has been incurred by Platmin. 
In the quarter ended March 31, 2010, the Company incurred less than US$0.001 
million (ZAR0.008 million) on the Loskop Project. Total cumulative exploration 
expenditure on this project since inception is US$0.850 million (ZAR6.228 
million). In accordance with the Group's accounting policies, these costs are 
capitalised as part of "Exploration and evaluation assets". 
Work program 
Lonmin Plc announced in a press release on November 18, 2008 that their 
management has decided, given their focus on cash management and the current 
state of the worldwide credit markets, to put a number of their projects, 
including Loskop, on a reduced work program for the short term. This is likely 
to affect the work program at Loskop in the 2010 financial year. 
Although work has continued during the year in order to assist in increasing our 
understanding of the Loskop mineralization, the mineral resources were not 
revised during the quarter ended March 31, 2010. 
8.     Contractual Obligations 
The Company's contractual obligations are as follows: 
 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Contractual     |        Payments due by period as at March 31,        | 
| obligations     |                        2010                          | 
| US$'000         |                                                      | 
+                 +------------------------------------------------------+ 
|                 |           Total |    < 1 |     1-3 |    4-5 |  After | 
|                 |                 | year * |   years |  years |      5 | 
|                 |                 |        |         |        |  years | 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Employee        |             349 |    349 |       - |      - |      - | 
| entitlements    |                 |        |         |        |        | 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Operating lease |             382 |    138 |     244 |      - |      - | 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Committed       |          16,102 | 12,393 |   3,709 |      - |      - | 
| Capital Cost    |                 |        |         |        |        | 
| (1)             |                 |        |         |        |        | 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Asset           |          86,741 |      - |       - |      - | 86,741 | 
| Retirement      |                 |        |         |        |        | 
| Obligation (2)  |                 |        |         |        |        | 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Mining and      |         465,845 | 74,465 | 292,094 | 99,286 |      - | 
| Processing      |                 |        |         |        |        | 
| costs (3)       |                 |        |         |        |        | 
+-----------------+-----------------+--------+---------+--------+--------+ 
| Total           |         569,419 | 87,345 | 296,047 | 99,286 | 86,741 | 
| Contractual     |                 |        |         |        |        | 
| Obligations     |                 |        |         |        |        | 
+-----------------+-----------------+--------+---------+--------+--------+ 
(1)     The Committed Capital Cost includes outstanding amounts in respect of 
plant capital expenditure to the completion of the plant construction project. 
(2)     This amount represents the gross asset retirement obligation incurred to 
date, to rehabilitate the opencast pit and plant at PPM at the end of life of 
mine, in accordance with the mining licence, The amount disclosed in note 9 of 
the condensed consolidated interim financial statements of $64,985 million 
represents the discounted value of such amount. 
(3)     Committed mining expenses include the remaining value of the agreement 
with engineering firm DRA to implement the design and construction phase of PPM, 
the contracts with Minopex for managing the plant operations and maintenance of 
the Merensky and UG2 metallurgical concentrator plants, and MCC for carrying out 
the opencast mining operations. 
9.      Off-Balance Sheet Arrangements 
The Company has not entered into any off-balance sheet transactions. 
10.    Related Party Transactions 
On April 22, 2010, the Company entered into a ZAR191.0 million (an equivalent of 
US$26 million at an exchange rate of ZAR7.39 =US$1.00) short term lending 
facility with Pallinghurst. 
11.    Proposed Transactions 
The Company continues to evaluate opportunities in the market with a view to 
expand the current business. At the current time there are no reportable 
proposed transactions. 
12.    Black Economic Empowerment ("BEE") 
Pursuant to the investors and subscription agreement entered into in December 
2008 with, among others, Ivy Lane Capital Limited, being the South African 
investment vehicle of the Pallinghurst Investor Consortium, the 
Bakgatla-Ba-Kgafela Tribe and the Bakgatla Pallinghurst JV (Proprietary) 
Limited, the Moepi Group was required by March 31, 2010, subject to certain 
conditions precedent, to exchange its 27.61% interest in Boynton for common 
shares in Platmin ("The Moepi Exchange"). Not all the conditions were satisfied 
by March 31, 2010 and the parties to the agreement agreed not to extend the 
fulfilment date thereof and accordingly the Moepi Exchange was not completed. 
Platmin has funded a total of US$9.536 million on behalf of its BEE partners for 
exploration activities, by way of loan account to date. All such amounts remain 
outstanding on inter-company loan accounts. 
13.    Environmental Matters 
The Company conducts exploration on its key projects and prospects subject to 
mineral exploration permit applications made to and issued by the DMR. For each 
exploration program, a rehabilitation plan is included with the application and 
where required the appropriate bond or funds are lodged with the relevant agent 
of the DMR in respect of the rehabilitation work which may have to be carried 
out when the exploration program is completed and no further work is planned on 
the property. All such environmental plans or bonds are in the normal course of 
the business. 
In respect of PPM, the DMR required a rehabilitation guarantee of US$7.027 
million before approving the application for a Mining Right. This guarantee has 
been provided by Guardrisk Insurance Company Limited ("Guardrisk") on an 
insurance basis, with an amount of US$1.835 million (ZAR13.500 million) paid 
over into a separate PPM bank account and ceded in favour of Guardrisk as 
collateral against the issuance of this guarantee. Ongoing contributions are 
made by PPM to fund the balance of the liability over the remaining life of 
mine. Further guarantees to the amount of US$14.268 million (ZAR104.987 million) 
have been provided to ESKOM on the same basis. 
In respect of the Mphahlele Project, the DMR required a rehabilitation guarantee 
of US$2.135 million (ZAR16.609 million) before the issuing of the Mining Right. 
This guarantee has been provided by Guardrisk on an insurance basis, with an 
amount of US$1.576 million (ZAR11.600 million) paid over into a separate Boynton 
bank account and ceded in favour of Guardrisk as collateral against the issuance 
of this guarantee. Ongoing contributions are made by Boynton to fund the balance 
of the liability over the remaining life of the prospecting permit. 
In respect of the Grootboom project, negotiations with the DMR are currently in 
progress to determine the amount of the rehabilitation guarantee required by the 
DMR before it issues the Mining Right. 
Environmental guarantees are released by the DMR on completion of the 
obligations in terms of the rehabilitation plans contained within either the 
application for the prospecting permits, or the mining right. 
14.    Mineral and Petroleum Resources Royalty Act, 2008 (Act no. 28 of 2008) 
The South African government has enacted the Mineral and Petroleum Resources 
Royalty Act (the "Royalty Act"), which imposes a royalty payable to the South 
African government by businesses based upon financial profits made through the 
transfer of mineral resources. 
The legislation was passed on November 17, 2008 and was due to come into 
operation on May 1, 2009. During his budget speech in February 2009, the South 
African Minister of Finance deferred the implementation of the Royalty Act to 
March 1, 2010. In terms of the legislation resulting from the Royalty Act, a 
royalty will be levied for the benefit of the National Revenue Fund of the 
government of the Republic of South Africa. The amount levied will be based on a 
percentage calculated by means of a formula, from a minimum of 0.5% up to a 
maximum of 5% on gross sales of refined mineral resources or 7% on gross sales 
of unrefined mineral resources. 
15.  Critical Accounting Estimates 
The Company's significant accounting principles and methods of application are 
disclosed in the notes of the Company's consolidated financial statements for 
the year ended December 31, 2009. The following is a discussion of the critical 
accounting policies and estimates which management believes are important for an 
understanding of the Company's financial results. 
Functional and presentation currency 
Items included in the financial statements of each of the Group's entities are 
measured using the currency of the primary economic environment in which the 
entity operates ("the functional currency"). The Group's functional currency, as 
determined at the transition date of March 1, 2008, is the South African Rand 
("ZAR"). The consolidated financial statements are presented in US dollars 
("USD") which is the Group's presentation currency for purposes of dual listing 
and foreign shareholders. 
The results and financial position of all the Group entities (none of which has 
the currency of a hyper-inflationary economy) that have a functional currency 
different from the presentation currency are translated into the presentation 
currency as follows: 
-    assets and liabilities for each statement of financial position presented 
are translated at the closing rate at the date of that financial period end; 
-    income and expenses for each statement of income and comprehensive income 
are translated at average exchange rates (unless this average is not a 
reasonable approximation of the cumulative effect of the rates prevailing on the 
transaction dates, in which case income and expenses are translated at the rate 
on the dates of the transactions); 
-    equity transactions are translated using the exchange rate at the date of 
the transaction; and all resulting exchange differences are recognized as a 
separate component of equity. 
Exploration and evaluation assets and development expenditure 
Exploration and evaluation costs, including the cost of acquiring licenses, are 
capitalized as exploration and evaluation assets on a project-by-project basis 
pending determination of the technical feasibility and the commercial viability 
of the project. The capitalized costs are presented as either tangible, or 
intangible exploration and evaluation assets according to the nature of the 
assets acquired. 
Capitalised costs include costs directly related to exploration and evaluation 
activities in the area of interest. General and administrative costs are only 
allocated to the asset to the extent that those costs can be directly related to 
operational activities in the relevant area of interest. When a license is 
relinquished or a project is abandoned, the related costs are recognized in 
profit and loss immediately. 
Inventory 
Inventories are measured at the lower of cost and net realisable value. The cost 
of inventories includes expenditure incurred in acquiring the inventories, 
production or conversion costs and other costs incurred in bringing them to 
their existing location and condition. 
Provisions 
Provisions are measured at the present value of the expenditures expected to be 
required to settle the obligation using a pre-tax rate that reflects current 
market assessments of the time value of money and the risks specific to the 
obligation. The increase in the provision due to passage of time is recognized 
as interest expense. 
The costs for the restoration of site damage, which arises during production, 
are provided at their net present values and charged against their operating 
profit as extraction progresses. Changes in the measurement of a liability which 
arises during production are charged against operating profit. 
The discount rate used to measure the net present value of the obligations is 
the pre-tax rate that reflects the current market assessments of the time value 
of money and the risks specific to the obligation. 
In accordance with the Group's policy and applicable legal requirements, a 
provision for decommissioning liabilities is recognized when the asset is 
installed and rehabilitation liabilities are recognized when the land is 
disturbed. 
Revenue 
The Group recognises revenue when the amount of revenue can be reliably 
measured, it is probable that future economic benefits will flow to the entity 
and when specific criteria have been met for each of the Group's activities as 
described below. The amount of revenue is not considered to be reliably 
measurable until all contingencies relating to the sale have been resolved. 
Revenue from the sale of goods is recognized when the significant risks and 
rewards of ownership have been transferred to the buyer. Revenue is not 
recognized if there are significant uncertainties regarding recovery of the 
consideration due. 
No revenue is recorded in the condensed consolidated interim statement of income 
and comprehensive income as the Pilanesberg Mine has not yet reached commercial 
production. 
16.  Financial Instrument and Other Instruments 
The Company has the following financial instruments: cash and cash equivalents, 
other receivables, accounts payable, accrued liabilities and a bridge loan 
facility. These instruments are short-term financial instruments whose fair 
value approximates their carrying value given that their maturity period is 
short. 
17.  Outstanding Share Data 
As at March 31, 2010, the Company had 445,018,352 issued and outstanding common 
shares. 
As at March 31, 2010, there were 4,947,266 outstanding options exercisable for 
common shares and a further 2,984,467 unvested share options, which, if 
exercised, would result in the issue of an additional 2,984,467 common shares. 
The total options outstanding at March 31, 2010, totalled 7,931,733 options. 
As at May 14, 2010, the Company had 650,779,669 issued and outstanding common 
shares. 
18.  Risks and Uncertainties 
The Company is in the business of the exploration and development of mineral 
properties and the operation of mines directly or through third parties. There 
are numerous risks associated with this business and specific risks with regards 
to the South African mining environment. 
Readers are urged to review the section titled "Risk Factors" appearing in 
Platmin's current AIF for the financial year ended December 31, 2009, which can 
be viewed at www.sedar.com. 
19.  Internal control over financial reporting 
Management has evaluated or caused to be evaluated, the effectiveness of the 
Company's disclosure controls and procedures and the internal control over 
financial reporting and concluded that the Company's disclosure and internal 
control over financial reporting was effective as of the end of the financial 
quarter ended March 31, 2010. Platmin has identified no material weakness in the 
design of its internal controls over financial reporting. There has been no 
change in Platmin's internal controls over financing reporting since its 
year-end MD&A for the period ended December 31, 2009 or in the quarter ended 
March 31, 2010, that has materially affected, or is reasonably likely to 
materially affect, Platmin's internal controls over financial reporting. 
 
 
This information is provided by RNS 
            The company news service from the London Stock Exchange 
   END 
 
 QRFSFDFDLFSSEDI 
 

Platmin (LSE:PPN)
Historical Stock Chart
From Oct 2024 to Nov 2024 Click Here for more Platmin Charts.
Platmin (LSE:PPN)
Historical Stock Chart
From Nov 2023 to Nov 2024 Click Here for more Platmin Charts.