RNS Number : 4958M
Sylvania Platinum Limited
30 April 2024
 

Description: C:UsersIanDesktopSYLVANIA PLATINUMSylvania Platinum logo.jpg

 

 

 

 

                            

 

30 April 2024

 

Sylvania Platinum Limited

 ("Sylvania", the "Company" or the "Group")

 

Third Quarter Report to 31 March 2024

 

Sylvania (AIM: SLP), the platinum group metals ("PGM") producer and developer with assets in South Africa, announces its results for the three months ended 31 March 2024 (the "Quarter" or the "Period"). Unless otherwise stated, the consolidated financial information contained in this report is presented in United States Dollars ("USD" or "$").

 

Highlights

·    Sylvania Dump Operations ("SDO") produced 17,232 4E (21,857 6E) PGM ounces in Q3 FY2024 (Q2 FY2024: 18,232 4E (23,105 6E) PGM ounces);

·      SDO recorded $20.3 million net revenue for the Quarter (Q2 FY2024: $20.9 million);

·      Group EBITDA of $3.2 million (Q2 FY2024: $4.4 million);

·      Cash balance as at 31 March 2024 of $101.3 million;

·      Thaba Joint Venture ("Thaba JV") project is on schedule with all elements of the project progressing well;

·      A share Buyback from the market commenced on 4 March 2024 and a total of 1,713,000 Ordinary Shares at an average price of 57.06 pence per share, equating to $1.2 million in aggregate, were repurchased;

·      Doornbosch operation achieved three years total injury-free during the Quarter;

·      Lannex secondary milling and fine grinding circuit has been completed, with optimisation continuing; and

·      Publication of updated Mineral Resource Estimates ("MREs") for the Volspruit project.

 

Post Period - Special Dividend Declared

·     Following the Period end, an interim cash dividend for HY1 FY2024 of 1 pence per Ordinary Share, amounting to $3.3 million, was paid in April 2024; and

·      The Company received early settlement of the loan and sale price relating to the sale of Grasvally Chrome Mine (Pty) Ltd amounting to an equivalent of $6.2 million.

 

The Board is very pleased to declare that a portion of the proceeds received will be distributed to shareholders as a special dividend in the amount of 1p per Ordinary Share, amounting to approximately $3.3 million, payable on 7 June 2024. Payment will be made to shareholders on the register at the close of business on 10 May 2024 and the ex-dividend date is 9 May 2024.

 

Outlook

·      Guidance for the full year of 74,000 to 75,000 4E PGM ounces for FY2024 is maintained;

·      Optimisation efforts continue to address lower PGM recoveries associated with the blend of feed sources;

·    Progress on the design, bulk power supply, environmental approvals, procurement and construction elements of the Thaba JV project to continue;

·     SRK Consulting has been appointed to undertake the completion of the combined (North and South ore bodies) Preliminary Economic Assessment ("PEA") for the Volspruit project. Upon completion of the PEA, if warranted, a Preliminary Feasibility Study ("PFS") will commence thereafter; and

·     The Group maintains strong cash reserves enabling funding of expansion and joint venture ("JV") initiatives, process optimisation capital and upgrading of the Group's exploration and evaluation assets.

 

 

Commenting on the results, Sylvania's CEO, Jaco Prinsloo, said:

 

"Doornbosch continues to be an industry leader on the safety front, achieving three years total injury-free during the Quarter and maintaining its eleven years Lost-Time Injury ("LTI") free status, which is a remarkable health and safety milestone for the operation.

 

"Despite a wage strike by members of the National Union of Mineworkers South Africa ("NUMSA") during February 2024 at our Western operations that impacted production at the Mooinooi and Millsell operations in particular, I am pleased that we were able to produce 17,232 4E PGM ounces for the Quarter and that we are able to maintain our full-year guidance of 74,000 - 75,000 4E PGM ounces.  The treatment of higher grade external third-party feed sources to supplement feed grades assisted to mitigate losses due to the strike action, and whilst profitable, contributed towards higher SDO cash costs per 4E ounce, which increased 15% in dollar and 16% in rand terms, respectively during the Period, and were also negatively affected by the lower ounces produced compared with Q2 FY2024.

 

"Net profit increased 62% from Q2 FY2024 due to a reduction in net tax as no dividend withholding tax was paid on inter-company dividends in Q3 FY2024. Net revenue was down mainly due to lower PGM ounce production during the Quarter, while Group EBITDA decreased owing to the decline in revenue and increased direct costs during the Quarter. Nonetheless, the SDO remained cash generative.

 

"Elsewhere across the portfolio, the Thaba JV continues to make excellent progress with the design, procurement and construction elements of the project all on schedule. Additionally, on the exploration front, an updated MRE statement for both Volspruit North and South orebodies was released. The PEA for the Volspruit project, along with the results from the metallurgical test-work are now expected during Q4 FY2024.  

 

"Following the Period end, the Company paid the HY1 FY2024 interim dividend of 1 pence per Ordinary Share in April 2024. In the face of current market headwinds, the Group remains in a strong cash position allowing it to continue funding its existing capital projects and growth opportunities, and to return value to shareholders. In addition to the interim dividend, the Company negotiated early settlement of the Grasvally loan and sale price of ZAR115.0 million ($6.2 million at date of payment) and has taken the decision to declare a special dividend in the amount of 1p per Ordinary Share; the balance of the proceeds will assist to fund the current project pipeline and technological developments."

 

 

 

 



Operational and Financial Summary

Production

 

 

 

 

Unit

Q2 FY2024

Q3 FY2024

% Change

Plant Feed

T

636,156

580,572

-9%

Feed Head Grade

g/t

1.84                       

2.07

13%

PGM Plant Feed Tons

T

342,548

330,379

-4%

PGM Plant Feed Grade

g/t

2.84

3.06

8%

PGM Plant Recovery1

%

58.33%

53.03%

-9%

Total 4E PGMs

Oz

18,232

17,232

-5%

Total 6E PGMs

Oz

23,105

21,857

-5%

Unaudited

 

USD

 

ZAR

 

Unit

Q2 FY2024

Q3 FY2024

% Change

Unit

Q2 FY2024

Q3 FY2024

% Change

Financials 3

Average 4E Gross Basket Price2

$/oz

1,305

1,303

0%

  R/oz

24,444

24,624

1%

Revenue (4E)

$'000

17,386

16,086

-7%

R'000

325,634

304,017

-7%

Revenue (by-products including base metals)

$'000

3,331

3,121

-6%

R'000

62,393

58,992

-5%

Sales adjustments

$'000

155

1,115

619%

R'000

2,905

21,081

626%

Net revenue

$'000

20,872

20,322

-3%

R'000

390,932

384,090

-2%










Direct Operating costs

$'000

13,144

14,233

8%

R'000

246,196

269,011

9%

Indirect Operating costs

$'000

2,567

2,354

-8%

R'000

48,082

44,484

-7%

General and Administrative costs

$'000

667

653

-2%

R'000

12,493

12,342

-1%

Group EBITDA

$'000

4,437

3,164

-29%

R'000

83,105

59,800

-28%

Net Profit

$'000

1,559

2,530

62%

R'000

29,200

47,817

64%










Capital Expenditure

$'000

3,924

3,514

-10%

R'000

73,488

66,410

-10%










Cash Balance4

$'000

107,232

101,342

-5%

R'000

1,963,418

1,916,377

-2%










Ave R/$ rate





R/$

18.73

18.90

1%

Spot R/$ rate





R/$

18.31

18.91

3%









Unit Cost/Efficiencies

SDO Cash Cost per 4E PGM oz5

$/oz

721

826

15%

R/oz

13,503

15,611

16%

SDO Cash Cost per 6E PGM oz5

$/oz

569

651

14%

R/oz

10,656

12,308

16%

Group Cash Cost Per 4E PGM oz5

$/oz

897

980

9%

R/oz

16,801

18,522

10%

Group Cash Cost Per 6E PGM oz5

$/oz

708

772

9%

R/oz

13,261

14,591

10%

All-in Sustaining Cost (4E)

$/oz

957

1,008

5%

R/oz

17,931

19,046

6%

All-in Cost (4E)

$/oz

1,096

1,145

4%

R/oz

20,533

21,643

5%

 

 

 

The Sylvania cash generating subsidiaries are incorporated in South Africa with the functional currency of these operations being ZAR.  Revenues from the sale of PGMs are received in USD and then converted into ZAR.  The Group's reporting currency is USD as the parent company is incorporated in Bermuda.  Corporate and general and administration costs are incurred in USD, GBP and ZAR.

                       

1  PGM plant recovery is calculated on the production ounces that include the work-in-progress ounces when applicable.

2  The gross basket price in the table is the March 2024 gross 4E basket used for revenue recognition of ounces delivered in Q3 FY2024, before penalties/smelting costs and applying the contractual payability.

Revenue (6E) for Q3 FY2024, before adjustments is $19.1 million (6E prill split is Pt 52%, Pd 18%, Rh 9%, Au 0%, Ru 16%, Ir 5%). Revenue excludes profit/loss on foreign exchange.

4  The cash balance excludes restricted cash held as guarantees.

The cash costs include operating costs and exclude indirect costs for example mineral royalty tax and Employee Dividend Entitlement Plan ("EDEP") payments.

 

 

 

 

 

 

A.  OPERATIONAL OVERVIEW

 

Safety, health and environment

During the Period under review, our Eastern operations remained total injury-free and Doornbosch in particular achieved the remarkable milestone of being total injury-free for three years.

Unfortunately, Mooinooi experienced one LTI when an employee sustained sprained ribs during a rigging task, after previously achieving 318 injury-free days.

Overall, a steadfast commitment to safety and security remains paramount for the success of Sylvania and the well-being of employees and contractors. Management's emphasis on putting in place robust safety measures, which include routine risk assessments, has played a critical role in nurturing a workplace ethos that places the well-being of both employees and contractors as a top priority.

Operational performance

The SDO delivered 17,232 4E PGM ounces for the Quarter. This equates to a decrease of 5% on Q2 FY2024, largely as a result of NUMSA embarking on a twenty-two-day wage strike at the Company's Western Operations during February 2024.

 

Following the strike action, operations have returned to normal after initial ramp-up challenges during March 2024. The treatment of higher-grade external feed sources of third-party material has assisted in mitigating losses due to the strike action. Optimisation efforts continue to address lower PGM recoveries at Tweefontein in particular, associated with a blend of specific feed sources during the Quarter.

 

Direct operating costs have increased by 9% in rand terms with the main contributor being the purchase and treatment of the higher-grade external feed material. Focus on optimisation and cost saving initiatives remains a priority on all operations.

 

SDO operating cash costs per 4E PGM ounce increased 16% in rand terms to ZAR15,611/ounce and in dollar terms, it increased 15% in dollar terms to $826/ounce (Q2 FY2024: ZAR13,503/ounce and $721/ounce) primarily as a result of the 5% reduction in production. The average ZAR:USD exchange rate remained largely unchanged during the Quarter at ZAR/$18.90 (Q2 FY2024: ZAR/$18.73).

 

The Group incurred capital expenditure of ZAR66.4 million ($3.5 million), in line with planned capital project schedules.

 

Operational opportunities

The availability of maintenance personnel during the strike action placed strain on equipment runtimes at the Western operations, which has been subsequently positively addressed with performance showing improvements. Ore blending from various available resources as well as those from external providers has continued to contribute towards higher PGM feed grades.

 

The focus on improving instabilities together with mass pull is expected to show improved PGM flotation performance and concentrate grades during Q4 FY2024, with an anticipated improvement in metal recoveries. Additionally, the commissioning of the Lannex secondary milling and fine grinding circuit has been completed, with optimisation continuing.

 

No load curtailment has been experienced at any of the operations during the Quarter. The installation of the Lesedi back-up generator has been completed and is now available, while the installation of the Millsell standby generator is in progress for completion during Q4 FY2024.

 

A feasibility study in terms of a potential new treatment facility for chrome tailings and run-of-mine ore sources at the Eastern operations is in progress.

 

 

 

 

 

B. FINANCIAL OVERVIEW

 

Financial performance

Revenue (4E) for the Quarter decreased by 7% to $16.1 million (Q2 FY2024: $17.4 million) due to lower PGM ounce production whilst, the average 4E gross basket price for the Quarter was steady at $1,303/ounce against $1,305/ounce in Q2 FY2024.

 

Net revenue, which includes revenue from by-products, base metals and the quarter-on-quarter sales adjustment, was $20.3 million (Q2 FY2024: $20.9 million). Net revenue includes attributable revenue received for ounces produced from material purchased from third parties.

 

Group cash costs per 4E PGM ounce increased by 10% in rand terms from ZAR16,801/ounce to ZAR18,522/ounce and 9% in dollar terms from $897/ounce to $980/ounce mainly as a result of the 5% decrease in ounce production quarter-on-quarter and the cost of acquiring third party material.

 

General and administrative costs decreased to $0.65 million from $0.67 million in Q2 FY2024. These costs are incurred in USD, Pounds Sterling ("GBP") and ZAR and were minimally impacted by the exchange rate as the USD/ZAR exchange quarter-on-quarter remained aligned.

 

Group EBITDA for the Quarter was $3.2 million (Q2 FY2024: $4.4 million) owing to the decline in revenue and increased direct costs during the Quarter. Net profit was $2.5 million (Q2 FY2024: $1.6 million). The 62% increase in net profit was primarily a result of no dividend withholding tax being paid in Q3 FY2024 as no inter-company dividend was declared.

 

The Group cash balance decreased 5% from $107.2 million to $101.3 during the Quarter. Cash generated from operations before working capital movement was $3.4 million, with net changes in working capital amounting to $2.0 million, which is mainly due to the changes in trade debtors of $2.2 million and includes an amount of $3.3 million pre-payment made to the share registrar in March 2024 for dividends payable in April 2024.

 

The basket price was steady in Q2 FY2024 and Q3 FY2024, but a 5% decrease in ounce production during Q3 FY2024 contributed to the lower trade debtors balance quarter-on-quarter, as trade debtors arise from the concentrate delivered in the Quarter but paid for in the following quarter as per the off-take agreement. 

 

The impact of exchange rate fluctuations on cash held at the end of Q3 FY2024 was a $2.7 million loss due to the spot ZAR to USD exchange rate at 31 March 2024 depreciating by 3%.

 

The Group spent $3.5 million (ZAR66.4 million) on capital projects for the Quarter. The majority of the capital spend was on tailings dams $0.8 million (ZAR15.8 million), generators to supplement electricity supply $0.3 million (ZAR4.8 million), Lannex fines plant project $0.4 million (ZAR7.5 million), Thaba capital expenditure $1.4 million (ZAR26.8 million) and further studies on the exploration projects $0.2 million (ZAR4.0 million).

 

C. THABA JV

 

As previously reported, the unincorporated JV Agreement between the Company's wholly owned South African subsidiary, Sylvania Metals (Pty) Ltd ("Sylvania Metals") and Limberg Mining Company (Pty) Ltd ("LMC"), a subsidiary of ChromTech Mining Company (Pty) Ltd ("ChromTech"), the Thaba JV, is advancing well and as expected. The project execution phase is approximately 18-24 months with first production expected in HY2 FY2025.

 

Design

The overall master 3D model for the plant is complete. The general layout of the Run of Mine ("ROM") Handling is complete and all drawings except for stockpile wing walls were issued for construction. The structural member sizing for the entire area of the ball mills is complete and the model has been updated, while the civil design is ready to be issued for construction.

 

The chrome plant fabrication drawings have been issued for the classification and secondary chrome recovery and the pipe routing and layout are in progress. All drawings for the thickeners, final tailings and process water are complete, while the plate and steel drawings were issued for fabrication. The optimisation of pipe routes is also in progress.

 

The PGM float plant drawings were issued for fabrication for PGM float and reagent plant, and the civil and structural design for reagent plant building are in progress with the model draft having been completed.

 

Bulk Power Supply

The budget quote was accepted, and the initiation fee has been paid to Eskom and the HV Sub-station EIA was approved by the Department of Forestry, Fisheries and the Environment ("DFFE").  Construction of the new sub-station (owner-built) will commence in May 2024.

 

Environmental Approvals

EIA Reports, required for tailings deposition and new water storage dams, were delivered to the Department of Mineral Resources and Energy ("DMRE") on 8 March 2024. The legislated timeframe for the DMRE to issue a decision is 107 calendar days, being 23 June 2024.

 

Procurement

All procurement packages have been issued for tender and 99% of the project value has been received back as market tenders. There have been 38 of 99 procurement packages issued as procurement orders and all long lead items have been ordered.

 

Construction

The reinforcement steel and shutters for the base of Primary Milling are 70% complete. Building is complete and installation of reinforcement steel for the Secondary Milling has commenced. Concrete pour for floors and sumps of the Spiral Plants are complete.

 

In terms of the Thickeners and Process Water the surveying and setting out is in progress. The concrete pour for floors and bunds of the Float Plants have been completed and a small number of plinths are in progress.

 

The box cut and rock fill for the rock of the concentrate access and load area are complete. However, rain delayed construction of the layers during March.

 

D.  MINERAL ASSET DEVELOPMENT AND JOINT VENTURES

 

The Group holds approved mining rights for three PGM-base metal projects on the Northern Limb of the Bushveld Igneous Complex in South Africa.  Following on from the Exploration Results and Resource Statement that was released in FY2023, the Company continues to develop the projects through additional technical studies and re-interpretation of historical information. A PEA is ongoing for Volspruit and possible further drilling is being planned for the Aurora project. This additional information will assist the Company in ascertaining how best to develop these projects.

  

Volspruit Project

Updated MREs for the Volspruit Project were published on 16 February 2024. The results include revised MREs for the Volspruit North and Volspruit South ore bodies, including for rhodium ("Rh") and ruthenium ("Ru"), both of which had previously not been assayed. The MRE is in line with the JORC (2012) Standard as a whole. The key highlights of the updated MRE statement are as follows:

 

·      Volspruit North JORC MRE (Indicated):

16.42 million tons ("Mt") at a 4E (4E includes platinum ("Pt"), palladium ("Pd"), Rh and gold ("Au")) grade of 2.52 grams per ton ("g/t");

1.33 million 4E ounces at a grade of 2.52 g/t;

21.94 million pounds ("lb") of copper ("Cu") at a grade of 0.07%;

61.50 million lb of nickel ("Ni") at a grade of 0.18%;

The MRE represents a 10% increase in the indicated tonnage from the previously reported MRE (October 2022) resulting from a more defined geological modelling exercise that has also resulted in the 4E grade improving by 4%; and

The addition of Rh estimates has improved the overall grade by approximately 7%.

 

·      Volspruit South JORC MRE (Inferred):

10.60 Mt at 4E grade of 2.11 g/t;

14.83 million lb of Cu at a grade of 0.06%;

46.96 million lb of Ni at a grade of 0.20%;

This MRE is the first one completed since the mineralised zones have been redefined and, as expected, it reports approximately a third of the tonnages at almost double the grades previously reported by Integrated Geological Solutions (Pty) Ltd ("IGS") in 2012.

 

SRK Consulting continues its work on the PEA Study to include contributions from rhodium and the additional resources from the South ore bodies. Results are expected in Q4 FY2024, and if warranted, a PFS will commence thereafter. Metallurgical test work for the PFS is currently underway at Mintek South Africa on samples obtained during an FY2023 drilling campaign.

 

Steady progress is being made in the permitting process necessary for the existing mining right. Local Economic Development projects are gaining traction and the Water Use License application for mining and on-site processing operations, as well as the updated Environmental Impact Assessment ("EIA") submissions, are expected to be made in the first Quarter of FY2025, allowing for a more comprehensive public engagement process to be completed.

 

Far Northern Limb Projects

Relogging has been completed for the entire Aurora project area with core from Kransplaats having been recently relogged. Compilation and interpretation of the data is on-going and once completed a decision will be taken on whether to implement a drilling programme to assess gaps in the current database. If warranted, drilling would likely commence during the fourth quarter of FY2024 and would allow for an updated MRE and PEA to be commissioned for Aurora if positive results were obtained.

A Technical Report on the Hacra North Underground Target was received from the independent consultants, Earthlab Technical Division, during the Quarter. The results will be presented to the Board in early Q4 FY2024, after which an announcement to the market will be prepared and released to the public.

Grasvally

Following the Period end, the Company agreed early settlement, in the amount of ZAR115.0 million ($6.2 million on date of payment), of the loan and sale price related to the sale of Grasvally Chrome Mine (Pty) Ltd to Forward Africa Mining (Pty) Ltd. The terms of the initial sale and loan agreements provided for payments in 15 quarterly instalments commencing at the end of the quarter following the first anniversary of the agreements becoming unconditional. During the Quarter, the parties negotiated an early settlement date for payment of the capital amount at 31 March 2024, with the Company agreeing to forego the interest. The full ZAR115.0 million ($6.2 million on date of payment) was received in April 2024. The Board has declared a portion of the proceeds received be distributed to shareholders as a special dividend in the amount of 1p per Ordinary Share, amounting to aproximately $3.3 million, payable on 7 June 2024. Payment will be made to shareholders on the register at the close of business on 10 May 2024 and the ex-dividend date is 9 May 2024.

 

E. CORPORATE ACTIVITIES

 

Notification of Transaction by PDMR

Eileen Carr, Non-Executive Director and Chair, purchased 60,000 ordinary shares of $0.01 each in the Company ("Ordinary Shares") at 49.74 pence per Ordinary Share on 23 February 2024. Following this transaction, her shareholding in the Company totals 130,000 Ordinary Shares, representing 0.05% of the total number of Ordinary Shares with voting rights.

 

 

 

Share Buyback

During the Period, the Company commenced a Share Buyback from the market and, as at 26 April 2024, has bought back a total of 1,843,000 Ordinary Shares at an average price of 57.21 pence per share, equating to $1.3 million in aggregate. The purpose of the Share Buyback is to reduce the share capital of the Company.

 

Additionally, during the Period, the Company acquired 166,000 Ordinary Shares from employees. The Ordinary Shares were purchased at the 30-day VWAP price of 54.95 pence per Ordinary Share and placed into Treasury.

 

For the purposes of the Financial Conduct Authority's Disclosure and Transparency Rules, the Company's issued share capital is 275,375,725 Ordinary Shares. Following the above purchases, a total of 13,774,211 Ordinary Shares, including 2,009,000 pending cancellation, are held in Treasury. Therefore, the total number of Ordinary Shares with voting rights in Sylvania was 261,601,514 Ordinary Shares.

 

CONTACT DETAILS

 

For further information, please contact:

 

Jaco Prinsloo CEO

Lewanne Carminati CFO

+27 11 673 1171



Nominated Adviser and Broker


Liberum Capital Limited

+44 (0) 20 3100 2000

Richard Crawley / Scott Mathieson / Joshua Borlant




Communications


BlytheRay

+44 (0) 20 7138 3205

Tim Blythe / Megan Ray

sylvania@BlytheRay.com

 

CORPORATE INFORMATION

 

Registered and postal address:

Sylvania Platinum Limited

 

Clarendon House

 

2 Church Street

 

Hamilton HM 11

 

Bermuda

 

 

 

SA Operations postal address:

PO Box 976

 

Florida Hills, 1716

 

South Africa

 

 

Sylvania Website: www.sylvaniaplatinum.com

 

 

About Sylvania Platinum Limited

 

Sylvania Platinum is a lower-cost producer of platinum group metals (PGM) (platinum, palladium and rhodium) with operations located in South Africa. The Sylvania Dump Operations (SDO) comprises six chrome beneficiation and PGM processing plants focusing on the retreatment of PGM-rich chrome tailings materials from mines in the Bushveld Igneous Complex. The SDO is the largest PGM producer from chrome tailings re-treatment in the industry. Additionally, the Thaba JV comprises chrome beneficiation and PGM processing plants, which will treat a combination of run of mine (ROM) and historical chrome tailings from the JV partner, adding a full margin chromite concentrate revenue stream. The Group also holds mining rights for PGM projects in the Northern Limb of the Bushveld Complex.

 

 

For more information visit https://www.sylvaniaplatinum.com/



ANNEXURE

 

GLOSSARY OF TERMS FY2024

The following definitions apply throughout the period:

3E PGMs

3E ounces include the precious metal elements platinum, palladium and gold

4E PGMs

4E ounces include the precious metal elements platinum, palladium, rhodium and gold

6E PGMs

6E ounces include the 4E elements plus additional Iridium and Ruthenium

AGM

Annual General Meeting

AIM

Alternative Investment Market of the London Stock Exchange

All-in costs

All-in sustaining cost plus non-sustaining and expansion capital expenditure

All-in sustaining cost

Production costs plus all costs relating to sustaining current production and sustaining capital expenditure

CLOs

Community Liaison Officers

Current arisings

Fresh chrome tails from current operating host mines processing operations

DFFE

Department of Forestry, Fisheries and the Environment

DMRE

Department of Mineral Resources and Energy

EBITDA

Earnings before interest, tax, depreciation and amortisation

EA

Environmental Authorisation

EAP

Employee Assistance Program

EEFs

Employment Engagement Forums

EDEP

Employee Dividend Entitlement Programme

ESG

Environment, social and governance

EIA

Environmental Impact Assessment

EIR

Effective interest rate

EMPR

Environmental Management Programme Report

ESG

Environment, Social and Governance

GBP

Pounds Sterling

GBV

Gender based violence

GHG

Greenhouse gases

GISTM

Global Industry Standard on Tailings Management

GRI

Global Reporting Initiative

HWS

Harriets Wish Succession

JORC

Joint Ore Reserves Committee

IASB

International Accounting Standards Board

ICE

Internal combustion engine

IFRIC

International Financial Reporting Interpretation Committee

IFRS

International Financial Reporting Standards

Lesedi

Phoenix Platinum Mining Proprietary Limited, renamed Sylvania Lesedi

LSE

London Stock Exchange

LTI

Lost-time injury

LTIFR

Lost-time injury frequency rate

MF2

Milling and flotation technology

MPRDA

Mineral and Petroleum Resources Development Act

MRA

Mining Right Application

MRE

Mineral Resource Estimate

Mt

Million Tons

NWA

National Water Act 36 of 1998

PGM

Platinum group metals comprising mainly platinum, palladium, rhodium and gold

PAR

Pan African Resources Plc

PDMR

Person displaying management responsibility

PEA

Preliminary Economic Assessment

PFS

Preliminary Feasibility Study

Pipeline ounces

6E ounces delivered but not invoiced

Pipeline revenue

Revenue recognised for ounces delivered, but not yet invoiced based on contractual timelines

Pipeline sales adjustment

Adjustments to pipeline revenues based on the basket price for the period between delivery and invoicing

PTM

Platinum Group Metal's Joint Venture

Project Echo

Secondary PGM Milling and Flotation (MF2) program announced in FY2017 to design and install additional new fine grinding mills and flotation circuits at Millsell, Doornbosch, Tweefontein, Mooinooi and Lesedi

RPEEE

Reasonable Prospects for Eventual Economic Extraction

Revenue (by products)

Revenue earned on Ruthenium, Iridium, Nickel and Copper

ROM

Run of mine

SDO

Sylvania dump operations

SHE

Safety, health and environmental

SLP

Social and Labour Plan

Sylvania

Sylvania Platinum Limited, a company incorporated in Bermuda

Sylvania Metals

Sylvania Metals (Pty) Limited

tCO2e

Tons of carbon dioxide equivalent

Thaba JV

Thaba Joint Venture

TRIFR

Total recordable injury frequency rate

TSF

Tailings storage facility

UNSDGs

United Nations Sustainability Development Goals

USD

United States Dollar

WULA

Water Use Licence Application

UK

United Kingdom of Great Britain and Northern Ireland

ZAR

South African Rand

Zero Harm

The South African mining industry is committed to the shared aspiration of achieving the goal of Zero Harm, which aims to ensure that mineworkers return home from work healthy and unharmed every day

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
QRTBKLLLZZLBBBD
Sylvania Platinum (LSE:SLP)
Historical Stock Chart
From Oct 2024 to Nov 2024 Click Here for more Sylvania Platinum Charts.
Sylvania Platinum (LSE:SLP)
Historical Stock Chart
From Nov 2023 to Nov 2024 Click Here for more Sylvania Platinum Charts.