Urals Energy, the independent exploration and production company with operations in Russia, today announces that Petraco Oil Company Limited ("Petraco") has agreed to restructure the terms of the debt repayment agreement with Petraco, details of which were originally announced on 12 April 2010 (the "Agreement").

Petraco Payment Restructure

Petraco has agreed with Urals Energy to link the repayment of the $4 million tranche, due on 31 July 2011, to a shipment of the tanker from Arcticneft scheduled for late October 2011. The remaining repayment dates are unaltered and are as follows:

 
 Date                Amount (US$) 
------------------  -------------------- 
 30 November 2011    4.0m 
------------------  -------------------- 
 31 July 2012        6.0m 
------------------  -------------------- 
 30 November 2012    5.7m 
------------------  -------------------- 
 31 July 2013        3.0m 
------------------  -------------------- 
 30 November 2013    Outstanding balance 
------------------  -------------------- 
 

This amendment will enable Urals to maximise the efficiency of its next oil shipment by increasing its oil storage, and thereby ensuring that the tanker delivery is as full to capacity as possible.

Drilling Update

Drilling at well #51 has taken slightly longer than originally anticipated: the actual drilling has progressed according to schedule and has reached a depth of 1,650 metres. Before running the production string, the drilling crew started elaboration of the borehole. While working through the borehole at the depth of 1,460, intensive shedding of breeds was discovered and, as such, the crew has installed two cement plugs at the depth of 1,485 to 1,470 meters and 1,470 to 1,450 meters. Subsequently, whilst working through these cement plugs at the depth of 1,471 meters, circulation seized and the drill became stuck. Currently the crew is working to free the drill and recommence drilling through the cement plug and elaborating through the well to run the production string.

Based on current progress, the management anticipates that flow rates will be known over the coming weeks and further announcements will be made at the appropriate time.

Drilling of well #41 will commence once well #51 has been completed.

Current Production

Current production at both Petrosakh and Articneft is 1,437 BOPD and 711 BOPD respectively.

Enquiries:

 
 Urals Energy Public Company Limited    +7 495 795 03 00 
-------------------------------------  -------------------- 
 Alexei Maximov 
-------------------------------------  -------------------- 
 Grigory Kazakov 
-------------------------------------  -------------------- 
 Allenby Capital Limited                +44 (0)20 3328 5656 
-------------------------------------  -------------------- 
 Nick Naylor 
  Alex Price 
-------------------------------------  -------------------- 
 
 Pelham Bell Pottinger                  +44 (0)20 7861 3232 
-------------------------------------  -------------------- 
 Mark Antelme 
-------------------------------------  -------------------- 
 Jenny Renton 
-------------------------------------  -------------------- 
 

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCGCGDICBGBGBX

Urals Energy (LSE:UEN)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Urals Energy Charts.
Urals Energy (LSE:UEN)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Urals Energy Charts.