which will increase capacity
to 71,000 bbls. Construction of
a new crude unit is now scheduled
to begin in January 2010.
Frontier Cheyenne 52.0 The refinery is operating at n/a
WY reduced rates for economic
reasons.
WEST COAST
Alon Paramount 55.0 Hydrocracker project post-
CA poned indefinitely, the Co.
said on Feb. 4
Chevron Richmond, 243.0 Hydrocracking Unit and re- Jun 27
CA former shut May 28 for 30-
days planned maintenance.
Judge halts construction on
expansion project July 1.
Exxon Torrance 155.0 Maintenance will begin in July July
Mobil at one of two 26,000-b/d coker
units, traders said on May 22.
Work began July 7, on SRU
Hydrogen Unit. Will last
few weeks
Flint North Pole 210.0 One of three processing n/a
Hills AK units has been shut due
to low jet fuel demand,
the co. confirmed on Mar.
19.
Shell Martinez 155.0 Crude Unit and Coker Unit Aug 15
CA to shut for planned main-
tenance on July 10; re-
start seen Aug. 15.
Tesoro Wilmington, 97.0 39-days of turnaround main-
CA tenance is planned for
fourth-quarter 2009.
Tesoro Wilmington, 97.0 39-days of turnaround main-
CA tenance is planned for
fourth-quarter 2009.
Order free Annual Report for BP plc
Visit http://djnewswires.ar.wilink.com/?link=BP or call
1-888-301-0513
Order free Annual Report for ConocoPhillips
Visit http://djnewswires.ar.wilink.com/?link=COP or call
1-888-301-0513
Order free Annual Report for Chevron Corporation
Visit http://djnewswires.ar.wilink.com/?link=CVX or call
1-888-301-0513
Order free Annual Report for Marathon Oil Corporation
Visit http://djnewswires.ar.wilink.com/?link=MRO or call
1-888-301-0513
Order free Annual Report for Exxon Mobil Corporation
Visit http://djnewswires.ar.wilink.com/?link=XOM or call
1-888-301-0513